PMI PMI-ACP - PMI Agile Certified Practitioner (PMI-ACP)

Page: 7 / 15
Total 476 questions

A product owner has various items in a product backlog and does not know how to prioritize them. How should the agile practitioner coach the product owner?

A.

Sort the stories in the backlog by descending story points and release the stories at the top of the list equal to the team's velocity.

B.

Prioritize the most valuable product features in the backlog first.

C.

Determine the features with the highest risk and release those first.

D.

Determine which features comprise the smallest feature set that could be successful in the market and establish viability of the product.

A project manager is leading a large agile project with multiple deliverables at each phase of completion. The project team has informed the project manager that the deliverables are completed per the team agreement.

Which agile practice should the project manager advise their team use to ensure deliverables are completed and ready for release?

A.

Requirements backlog and ready for release

B.

Acceptance criteria and release

C.

Definition of ready (DoR) and review

D.

Definition of done (DoD) and demonstrate

During a sprint review, the Product Owner identifies a required improvement for a feature’s user interface (UI) delivered during the sprint.

What should the Product Owner do next?

A.

Create a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer

B.

Create a user story for this new improvement and prioritize it for the next sprint

C.

Document it as a requirement creep

D.

Ask the team to take on additional story points to improve the UI

The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative's current status.

Which summaries are correct and will be presented during the monthly project review? (Refer to

the email and exhibits to the Team Manager)

A.

MVP has 25 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

B.

MVP has 30 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

C.

MVP has 25 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

D.

MVP has 30 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

An agile team is having difficulties in obtaining the participation of a true user to be a part of their team. In the absence of a true user, the development manager steps in to act as a proxy for the user.

What can the agile team do to improve value delivery in the absence of a true user?

A.

Improve the velocity of each iteration.

B.

Add a variety of skilled programmers and expert testers to the team.

C.

Reduce the length of each iteration.

D.

Add a variety of users, such as business analysts and domain experts, to the team.

An agile team has started to worry because lately they have seen an increase in the number of issues. There seems to be a large variance in the quality of the work items delivered. The team now realizes that a shared understanding of quality may not exist among team members.

What should the team do?

A.

The team should move to test-driven development as defects are not being detected during testing.

B.

The team should account for the increased problems in their velocity forecasts since unexpected changes occur in agile projects.

C.

The team should discuss their definition of done (DoD) and make changes to ensure there is common understanding of the acceptance criteria.

D.

The team's agile project manager should facilitate the development of a new, detailed test procedure that all team members must follow.

What should the team do?

A.

Reduce work in progress (WIP) limits to accommodate slack for riskier stories

B.

Create a triage step on the Kanban board to pre-identify risky stories

C.

Set a policy to break down stories larger than a specified complexity, then adjust the WIP

D.

Create a dedicated overflow swimlane on the Kanban board for stories that are too large

Based on the backlog metrics in the chart, what can explain the jump in points at the end of iteration 4?

A.

The team neglected to account for support and maintenance costs associated with other supported products

B.

The team discovered that previously accepted work could be greatly improved and added story points associated with that work

C.

The team realized that some stories were underestimated relative to other stories and reestimated as needed

D.

The team learned that the product owner needed to increase the output in the next release

New stakeholders are joining a project team where the agile coach will educate them about their roles and responsibilities.

How should the stakeholders ensure their objectives are met by product delivery?

A.

Provide feedback for completed user stories.

B.

Define how the features will be implemented.

C.

Tell the team which features to include in the backlog.

D.

Write acceptance criteria for the user stories.

How should the agile team address this?

A.

Conduct an internal review to validate functionality before shipping

B.

Audit the quality control process to ensure that the product adheres to requirements

C.

Lengthen iterations to ensure there is sufficient time to build functionality

D.

Hold product review sessions with the client to obtain product acceptance