PMI PMI-ACP - PMI Agile Certified Practitioner (PMI-ACP)
A large, corporate organization is forced to hire new team members in a geographically remote location from the current team. The manager of the department is concerned about the team not being colocated.
What behavior would indicate the team is not working well together?
An agile coach is working on a digital transformation project. The project team is in the middle of a 5-week sprint. The agile coach notices constant arguing among team members on what should be the preferred technical approach to solve a current business problem. What can the agile coach do to promote collaboration and consensus-building among team members?
Midway through a sprint, a team member discovers that the product design fails to adhere to the organization ' s enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled.
What should the team have done to avoid this?
The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during the meetings. What should the project lead do to encourage the team to express themselves?
The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during the meetings. What should the project lead do to encourage the team to express themselves?
The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company’s steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.
What is the estimated project conclusion?
What should the agile team do?
During an iteration, an urgent customer request for support reaches the team. If they work on it, the team ' s commitments in this iteration are at risk.
What should the team do next?
What should a Scrum Master do when an agile team member is behind on their tasks?
A team member does not understand what the project risks are or the impact that they could have.
How should an Agile leader communicate risks in a way that the team will understand?

Velocity = 40 story points per sprint
Remaining Work = 240 story points
Sprint Duration = 2 weeks