Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

PMI PMI-ACP - PMI Agile Certified Practitioner (PMI-ACP)

Page: 5 / 15
Total 476 questions

An agile team is working well together, but productivity has been flat. What can the project leader do to help them improve performance?

A.

Review the burndown chart to identify ways to increase efficiency.

B.

Chair a weekly team retrospective focusing on identifying areas for continuous improvement.

C.

Ask a senior manager to initiate a root-cause analysis.

D.

Identify team key performance indicators (KPIs) and create positive incentives when targetsare achieved.

Who should the Scrum Master invite to the meeting?

A.

The core team and the customer

B.

The product owner and key stakeholders

C.

The customer and the sponsor

D.

The core team and the product owner

After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met.

If the problem were an issue of requirement elicitation rather than delivery, what should have been done to avoid this situation?

A.

Stakeholders should have regularly been engaged to obtain feedback and reduce the functionality risk.

B.

The team should have used the lean principle of delay, so that actual facts could be considered rather than assumptions and predictions.

C.

Interdependent teams should have been engaged using a collaborative approach to identify and leverage the best support.

D.

An owner should have been identified to obtain timely stakeholder feedback.

What should the agile practitioner do?

A.

Select and implement collaboration tools to augment team interactions

B.

Provide each geographical area with their own product owner and divide the work between the teams

C.

Increase the number of requirements documents and ensure they are clearly communicated

D.

After several sprints, calculate velocity based on primary team location and use secondary team as reserve

A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.

What steps should the project leader take to improve knowledge sharing?

A.

Meet individually with each team member to identify the issues and relay information to the remaining members through status reports.

B.

Establish a live video feed between the dispersed teams to enable spontaneous engagement and collaboration on issues.

C.

Request that the customer co-locate the team to overcome the communication issues, as this is the only method to ensure agility.

D.

Inform the customer of the challenges and lower velocity of the project to accommodate for the slower delivery pace.

What should the agile practitioner do?

A.

Coach the product owner to update only the acceptance criteria.

B.

Instruct the agile team to fix the user stories during the next retrospective.

C.

Facilitate a user story workshop with the agile team.

D.

Inform the product owner's manager that the work items provide insufficient detail.

During a retrospective, a team member claims that a specific set of documentation that is continuously updated during iterations is not being used by any stakeholder.

What should the team do?

A.

Continue updating the documentation but initiate an analysis to identify its value and act on the findings.

B.

Stop updating the documentation since no one is using it.

C.

Continue updating the documentation since it is clearly required by the process.

D.

Stop updating the documentation and initiate an analysis to identify its value and act on the findings.

Two team members are working together to deliver an asset management tool. The code delivered by team member A during this sprint is not aligning with the specifications written by team member B. Both team members do not seem to agree on the look and feel of some functionality.

What should the Scrum Master do in this situation?

A.

Understand the root cause of this issue and recommend discussing their differences to find common ground.

B.

Hold a team meeting to discuss these issues and help direct the whole team on how to proceed further.

C.

Let the two team members resolve the conflict on their own.

D.

Ask their functional manager to intervene and resolve the issue.

The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.

What should the coach do to help the team?

A.

Help the team to remove impediments that stall project progress.

B.

Work with the development team to adjust the work plan.

C.

Ask the product owner to assign more resources to the project.

D.

Command and control the team to achieve plan goals.

The first project vision statement meeting for a newly formed team did not achieve its outcome. Lack of participation combined with conflicting views of those who participated led to disagreement on how to proceed.

How can the team improve their collaboration?

A.

Set clear expectations and allow everyone to contribute.

B.

Prepare the project vision statement and then present it to the team.

C.

Ask senior management to address the situation.

D.

Seek assistance from the scrum master to mediate the conflict.