PMI PMI-ACP - PMI Agile Certified Practitioner (PMI-ACP)
A Kanban team is struggling to prioritize and determine which tasks to handle first according to value.
What should the team do to improve this situation?
During a current sprint, a team member asks permission from the Scrum Master to investigate an alternative design approach.
What should the Scrum Master do?
Following approval of a business case, a company will introduce a new mobile app for customers to place orders. Time to market is a key concern. The product has entered into the 3rd iteration, but the team is concerned because they feel the technical designs do not meet the agreed-on definition of done (DoD). An agile coach has been hired to help validate product delivery against business requirements.
What should the agile coach do?
One of the senior stakeholders on a project did not want to be engaged on a daily basis. During the iteration, the team encounters complexities but are convinced these issues can be resolved in time for the demo.
What should the agile practitioner do?
A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).
How many sprints will be needed to complete the entire backlog?
To help the team gain confidence, what should the agile practitioner suggest?
What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?
In a Scrum team, who should be responsible for the budget and release plans?
The product owner is working on an application that will be built in a data lake leveraging a data
integration and transformation software application. With a budget of US$17,000 remaining, how should the product owner allocate the money? (Refer to Exhibit A)

Normal sprint velocity: 5 story points per sprint
Reduced velocity for sprints 4-6: 4 story points per sprint
First 3 sprints: 5 points per sprint → 5 × 3 = 15 story points completed
Sprints 4-6: 4 points per sprint → 4 × 3 = 12 story points completed
Remaining story points after sprint 6: 72 - (15 + 12) = 45 story points
Remaining sprints needed at normal velocity (5 story points per sprint): 45 ÷ 5 = 9 sprints
Sprints 1-6: Already planned.
Additional 9 sprints needed.