Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMI-ACP - PMI Agile Certified Practitioner (PMI-ACP)

Page: 3 / 15
Total 481 questions

An agile team is working on a new product and is behind with their deliverables for the quarterly release. The team discovers new issues during each iteration. They start working on the critical issues and sometimes forget to update the backlog. This leads to confusion, delays, and occasional rework.

How should the agile practitioner improve the team’s productivity?

A.

Work with the team to ensure that both the product and iteration backlogs are up to date.

B.

Work with the team to ensure that the release backlog is in sync with the product backlog.

C.

Work with the team to ensure that the iteration and release backlogs are kept up to date.

D.

Work with the team to ensure that the product backlog is always kept up to date.

The customer asked the IT project manager to change a few specifications for the software being developed, which will affect the project budget. The financial sponsor is having difficulty approving changes to the budget that was already allocated to the project.

What should the project manager do next?

A.

Explain that agile principles mandate that there should be a contingency budget for agile projects.

B.

Request the team work overtime to get the work done on time and within the allocated budget.

C.

Encourage the product owner and team to analyze the impact of the changes and prioritize the backlog.

D.

Review the contract documentation with the customer to clarify the specific agreed-upon budget amount.

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

A.

Coach the team to decompose the backlog activities to granular, simple tasks that are easier to estimate and complete.

B.

Evaluate the team ' s capacity and help them select user stories for the iteration based on 60% of their capacity utilization.

C.

Discuss options to add more people to the team so they can complete the tasks on time and within budget.

D.

Evaluate the team ' s capacity and help them select user stories for the iteration based on 80% of their capacity utilization.

What should the agile project leader do?

A.

Bring up the new member ' s impediments at the next meeting to demonstrate team support of input

B.

Assure the new member that inputs on impediments are valued and demonstrate this at the next meeting

C.

Have a senior lead work with the new member to avoid a negative impact on team productivity

D.

Privately work with the new member to address any impediments

What should the team do?

A.

Reduce work in progress (WIP) limits to accommodate slack for riskier stories

B.

Create a triage step on the Kanban board to pre-identify risky stories

C.

Set a policy to break down stories larger than a specified complexity, then adjust the WIP

D.

Create a dedicated overflow swimlane on the Kanban board for stories that are too large

If an individual is working on a project team in a phase delivering an increment, according to the definition of done (DoD), who was that defined by?

A.

Project sponsor and project team

B.

Scrum master

C.

Product owner

D.

Stakeholders and project team

A scrum master is working with a team on a complex software project that is scheduled to run for 2 years with a series of product releases. The scrum master is responsible for planning the project for the next 6 months and has advised planning the project up front.

What should the scrum master do?

A.

Add the releases into a roadmap with milestones and activities.

B.

Identity dedicated tasks and activities with regular feedback loops.

C.

Deliver in small and continuous iterative releases.

D.

Identify the requirements ' schedule within set time scales.

A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).

At the end of which sprint will the minimum viable product (MVP) be completed?

A.

7

B.

8

C.

9

D.

10

What should the agile practitioner do?

A.

Complete the test cases before creating the story in the backlog

B.

Define the detailed business requirements so that the team can continue with development

C.

Define the user stories with just enough detail so the team can collaborate continuously

D.

Ensure the acceptance criteria includes testing scenarios, so the team can do thorough testing

What should the agile practitioner do?

A.

Defer starting the design of item B until the second iteration is being planned

B.

Proceed with the design of item B, since it will hasten the second iteration

C.

Escalate the issue to the customer, and obtain their approval before starting the design of item B

D.

Log the issue in the risk register, and request change control board (CCB) approval