An agile team is working on a new product and is behind with their deliverables for the quarterly release. The team discovers new issues during each iteration. They start working on the critical issues and sometimes forget to update the backlog. This leads to confusion, delays, and occasional rework.
How should the agile practitioner improve the team’s productivity?
The customer asked the IT project manager to change a few specifications for the software being developed, which will affect the project budget. The financial sponsor is having difficulty approving changes to the budget that was already allocated to the project.
What should the project manager do next?
An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.
Which approach should the agile lead take?
An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.
Which approach should the agile lead take?
What should the agile project leader do?
What should the team do?
If an individual is working on a project team in a phase delivering an increment, according to the definition of done (DoD), who was that defined by?
A scrum master is working with a team on a complex software project that is scheduled to run for 2 years with a series of product releases. The scrum master is responsible for planning the project for the next 6 months and has advised planning the project up front.
What should the scrum master do?
A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).
At the end of which sprint will the minimum viable product (MVP) be completed?
What should the agile practitioner do?
What should the agile practitioner do?

Accessibility – color blind → 4 story points
Increase security → 21 story points
Add AI chatbot → 5 story points
The risk register mentions a reduction of 1 story point per sprint from sprints 4 through 6 due to the holiday schedule.
If we assume the team ' s normal velocity is 10 story points per sprint (hypothetically), it would drop to 9 story points per sprint for sprints 4-6.