PMI PMI-ACP - PMI Agile Certified Practitioner (PMI-ACP)
A project is to be started with a team of nine existing and nine new members. The Scrum Master feels that the team is too large and wants to break it into three teams. The Scrum Master sets a constraint that each team have an equal number of existing team members for knowledge sharing and experience.
What should the Scrum Master do to accomplish this?
What should the agile coach do next?
An agile project manager is working on a project to develop a customer service website. The project manager is organizing a workshop to plan the next release: To add the feature of receiving and resolving customer complaints. Which two actions should the project manager ask the team members to take before the workshop? (Choose two.)
Unable to meet a sprint's committed velocity, an agile team approaches the agile coach to define the next sprint's velocity. What should the agile coach advise?
A new team member asks what changes could accelerate a change to the project plan.
What should be the proper response?
On a complex project with a large degree of uncertainty, the team’s velocity is declining. Upon testing, it is discovered that many of the work items reported as complete are not meeting the stakeholders' requirements.
Which of the following could help resolve the incomplete work?
Following approval of a business case, a company will introduce a new mobile app for customers to place orders. Time to market is a key concern. The product has entered into the 3rd iteration, but the team is concerned because they feel the technical designs do not meet the agreed-on definition of done (DoD). An agile coach has been hired to help validate product delivery against business requirements.
What should the agile coach do?
A client needs to release their product to market earlier than planned. They need to start receiving the expected revenue, according to their financial forecast, which will require completing the work left on all user stories in the backlog.
What should the project lead do to accommodate this request?
Iterations last between a couple of weeks to a couple of months, with a preference for the shorter time. What is the goal for each iteration?
A product owner adds user stories to the backlog on a daily basis. The stories are vague requests, and the product owner expects the details to be clarified once the team works on the prioritization list.
How should the team members address this challenge so that the prioritization meeting does not become a brainstorming session?