What is a standardized, effective, and efficient way to manage changes to project documentation?
A business analyst has elicited, documented, and verified the requirements, discovering that there are not enough resources to deliver all the requirements. Which technique should the business analyst employ to rectify the issue?
The technology department identified a defect in the company's software, which leads to an increase in human resource requirements to perform manual transactions as a workaround for tasks that should have been automated. The company begins losing money, so it hires a business analyst to produce a business case that outlines the problem/opportunity, potential options, and a recommendation for how to proceed.
Which of the following analyses must the business analyst perform in order to complete the business case and arrive at a solid
recommendation?
A business analyst created requirements for production of a product extract file for several systems. After reviewing the complex systems and dividing the processes into manageable tasks, the business analyst is able to identify the tasks required to implement the deliverable.
Which analysis technique has the business analyst used?
During a requirements workshop, sponsors and managers from different departments express varying points of view and priorities about the product's functions and requirements. The business analyst struggles with facilitating the group to reach an agreement.
What should the business analyst have defined to avoid this?
A business analyst is documenting the acceptance criteria to support a minor modification in a user portal. The analyst submits the criteria for review, but it is deemed incomplete and returned.
What could have caused the documentation to be returned?
The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.
Which course of action should the business analyst take?
A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in a statistical analysis on user satisfaction with the current business process.
Which of the following types of surveys would be most appropriate to create and why?
A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?
A business analyst has been asked to investigate a problem. This investigation will provide input towards developing a business case. The business analyst wants to first understand the company's current business processes.
Which technique should the business analyst use?