PMI PMI-RMP - PMI Risk Management Professional (PMI-RMP) Exam

Page: 2 / 9
Total 278 questions

A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?

A.

US$20.000 loss

B.

US$20,000 profit

C.

US$40,000 loss

D.

US$100,000 profit

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

A.

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

B.

Create a repository for project documents and related artifacts that can be accessed by all parties.

C.

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

D.

Work with the project manager to develop a start-up workshop and colocate the team if permitted. 

An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?

A.

Update the risk register

B.

Meet with the project ' s stakeholders

C.

Revise the risk management plan

D.

Ensure sufficient resources are available

During a project team meeting, a risk manager realizes that the initial assumptions on the project schedule are too optimistic. The risk manager believes that the project might not meet its deadline as initially stated.

What is the reason for misunderstanding the assumptions from the beginning?

A.

Government regulations have changed in the last week, and now additional approval processes are required.

B.

The team ' s compensation was reduced and they lost the motivation to comply with the project deadline.

C.

The stakeholders prepared the initial schedule assumptions based only on the results of the last project.

D.

The sponsor had neither presented the actual results to the stakeholders nor updated the initial assumptions.

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

Which risk identification technique should the risk manager use?

A.

Prompt lists

B.

Interviews

C.

Delphi technique

D.

Nominal group technique

A risk manager faces resistance as they try to implement the project ' s risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?

A.

Continue to implement the risk strategy

B.

Meet with team members to address their concerns.

C.

Reduce the number of risk management activities.

D.

Raise the concerns with the project sponsor,

An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.

What should the risk manager do next?

A.

Add only the threats to the risk register

B.

Utilize different tools to identify the risks

C.

Plan risk responses to the threats

D.

Update the risk register with the identified risks

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?

A.

Conduct a subject matter expert (SME) meeting.

B.

Perform qualitative analysis.

C.

Prioritize after quantitative analysis

D.

Prioritize the stakeholders affected.

In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers

this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about

to drop their intention to continue executing the project. The risk manager does not understand their decision.

What should the risk manager do next to understand the major stakeholder ' s decision regarding the project?

A.

Perform a risk impact analysis.

B.

Perform a risk reserve analysis.

C.

Perform a procurement analysis.

D.

Perform a stakeholder impact and influence analysis.

A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.

What type of risk response is this?

A.

Transfer

B.

Accept

C.

Mitigate

D.

AvoidÂ