Month End Sale Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: newyear

PMI PMI-RMP - PMI Risk Management Professional (PMI-RMP) Exam

Page: 1 / 9
Total 333 questions

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project ' s risk register and asks the risk manager for an analysis of its effectiveness.

What two actions should the risk manager do next? (Choose two.)

A.

Check to ensure that the risk is supported by a Monte Carlo simul-ation.

B.

Check to ensure that the risks are gathered using Delphi technique.

C.

Check for risk classification and that probability and impact are identified.

D.

Check to ensure that risk origin, triggering event, and ownership is identified.

E.

Check to ensure the risk meeting agenda and supporting documents are distributed.

A risk manager has been assigned to a project in a company that is undergoing a significant cultural and organizational change. The risk manager will start planning risk management. activities with stakeholders but is unsure with whom to engage.

What should the risk manager do?

A.

Assign a subset of stakeholders to work on the risk management process.

B.

Leverage the project manager ' s project stakeholder analysis.

C.

Agree with the project manager not to start risk activities.

D.

Send a communication inviting volunteers to join risk activities.

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?

A.

Product Manager

B.

Risk Action Owner

C.

Risk Owner

D.

Project Manager

A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.

What should the risk manager do?

A.

Import a risk register from other industry chemical laboratories.

B.

Define chemical laboratory safety risk thresholds.

C.

Review published operational experience reports.

D.

Draft threat and opportunity risks that come to mind.

A project manager is educating the project team on risk management regarding the role of threats and opportunities. The team decides to log the opportunities in the current project ' s risk register to try to maximize their chances of occurrence.

What should the project team do next?

A.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

B.

Log the threats in the risk register to try to minimize the probability of occurrence.

C.

Log the threats in the risk register to try to maximize the probability of occurrence.

D.

Update the project management plan to ensure the results of the opportunities are captured.

A technology company is in the final stages of an IT system implementation project. As part of ongoing risk monitoring, the risk manager reviews current risk levels and identifies significant changes in the external regulatory environment that may affect project delivery.

What should the risk manager do next?

A.

Engage the operations team to assess the environment for issues.

B.

Request that the project management office add resources to address these risks.

C.

Expedite project completion to avoid potential impacts from the new risks.

D.

Work with the project team to reassess the environment for new risks.

An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.

What should the risk manager do next?

A.

Add only the threats to the risk register

B.

Utilize different tools to identify the risks

C.

Plan risk responses to the threats

D.

Update the risk register with the identified risks

During a complex infrastructure project, the team successfully mitigated a risk related to equipment failure. However, the mitigation strategy resulted in a secondary issue due to the use of alternative machinery.

What should the risk manager do?

A.

Assign a risk owner and develop the risk mitigations at the next scheduled risk meeting.

B.

Continue with the project as the risk identified is inconsequential.

C.

Assign risk responsibility to the project manager to determine how to proceed.

D.

Update the project stakeholders and seek their input on the resulting secondary risk.

When performing a risk analysis, a risk manager identifies not only negative risks but also positive risks, which might bring added value to the project. What should the risk manager do next?

A.

Prioritize opportunities as they are likely to bring benefits to the project.

B.

Analyze the risks and add them to the risk register to continue the process.

C.

Create a separate project to exclusively manage positive risks and threats.

D.

Assign separate stakeholder groups for positive risks and negative risks.

During the early planning stages of an AI-based software development project, the project team begins outlining the risk management activities. The risk manager notices that key stakeholders, such as data scientists, product owners, and external data vendors, lack a shared understanding of risk management principles.

What should the risk manager do to educate stakeholders?

A.

Conduct risk workshops tailored to all stakeholders.

B.

Invite all stakeholders to daily coordination meetings.

C.

Distribute risk-policy documents to all stakeholders.

D.

Provide project management training to all stakeholders.