Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMI-RMP - PMI Risk Management Professional (PMI-RMP) Exam

Page: 8 / 9
Total 278 questions

The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.

What should the team perform in this scenario?

A.

Quantitative risk analysis

B.

Risk response planning

C.

Monitor and control risks

D.

Risk urgency assessment

The risk manager also serves as a facilitator for a project and realizes the project team members have biases impacting how they perceive risks. What analysis is currently being used?

A.

Quantitative risk analysis

B.

Force field analysis

C.

Qualitative risk analysis

D.

Stakeholder analysis

The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.

What is this an example of?

A.

Risk responses

B.

Risk triggers

C.

Risk registers

D.

Risk categories

A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?

A.

Risk description risk response, and quantitative data

B.

Project plan, risk complexity, and secondary risk

C.

Project plan, risk priority, and tool availability

D.

Risk description, risk probability, and risk impact 

A product roadmap should contain which of these primary components?

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes, detailed design plan

D.

Product vision, business objectives, timeframes

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.

Who should the project manager hold accountable for missing the risks?

A.

The audit team

B.

The risk manager

C.

The risk owners

D.

The discipline engineers

A project team has failed to complete an important project milestone on time. The team was counting on an external provider to deliver key equipment on a specific date but the provider was delayed.

What should the risk manager have done to prevent missing the milestone?

A.

Better schedule monitoring and controlling.

B.

Identify and analyze project plan assumptions.

C.

Have a detailed work breakdown structure (WBS).

D.

Use management reserves to cover delays.

After completing the sprint on an agile project, a team updates the risk burndown chart and notices that risk exposure has increased to levels that could negatively affect project completion. What should the risk manager do to return the project ' s risk exposure to an acceptable level?

A.

Update the definition of done (DoD) to improve risk management.

B.

Review the acceptance criteria for upcoming stories.

C.

Prioritize risk mitigation stories for the next sprint.

D.

Check stories in the product backlog to identify risks.

A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.

What will be the main output of this meeting?

A.

Evaluating the project ' s probability of success

B.

Identifying threats and opportunities

C.

Evaluating the project ' s impact

D.

Performing a qualitative analysis

it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.

Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?

A.

4 hours

B.

5 hours

C.

6 hours

D.

12 hours