Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMI-SP - PMI Scheduling Professional

Page: 10 / 10
Total 323 questions

Tom is the project manager of the GHQ Project for his organization and he is working on recovering the project schedule. As Tom examines his schedule, he is especially aware of project activities with hard logic. What is hard logic?

A.

Hard logic describes activities that can be completed in any order but are positioned with finish-to-start relationships.

B.

Hard logic describes activities that have external constraints, such as a vendor.

C.

Hard logic describes activities that must be completed in a particular order unless additional resources with comparable skill sets can be added to the project.

D.

Hard logic describes activities that must be completed in a particular order.

You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:

MeasurementsValues

BCWP (or EV)325

BCWS (or PV) 300

ACWP (or AC)410

What is the schedule variance (SV) of the project at the current point of time?

A.

+110

B.

-25

C.

-110

D.

+25

Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vendor, the project is going well. What should Billy report as her schedule performance index for this project?

A.

1.23

B.

100 percent because the vendor caused her lateness

C.

.80

D.

$524,000

You are the project manager for your organization. Your current project has a schedule variance of -$37,500 and a schedule performance index of 0.94. What do these values mean in regard to project performance?

A.

Your project is likely to be late and over budget.

B.

Your project is performing well.

C.

Your project has a planned value of $600,000.

D.

Your project is six percent off schedule and has a considerable schedule variance.

Which of the following processes fall under the Project Integration Management knowledge area? Each correct answer represents a complete solution. Choose all that apply.

A.

Quality Assurance

B.

Project Plan Development

C.

Integrated Change Control

D.

Project Plan Execution

You are the project manager for the NGH project. The figure given below represents the small project you are completing for your organization.

How much float can you use on Activity G if Activity B actually takes eight days to complete?

A.

Four

B.

Three

C.

Seven

D.

Zero