PMI PMI-SP - PMI Scheduling Professional
Tom is the project manager of the GHQ Project for his organization and he is working on recovering the project schedule. As Tom examines his schedule, he is especially aware of project activities with hard logic. What is hard logic?
You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below:
MeasurementsValues
BCWP (or EV)325
BCWS (or PV) 300
ACWP (or AC)410
What is the schedule variance (SV) of the project at the current point of time?
Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vendor, the project is going well. What should Billy report as her schedule performance index for this project?
You are the project manager for your organization. Your current project has a schedule variance of -$37,500 and a schedule performance index of 0.94. What do these values mean in regard to project performance?
Which of the following processes fall under the Project Integration Management knowledge area? Each correct answer represents a complete solution. Choose all that apply.
You are the project manager for the NGH project. The figure given below represents the small project you are completing for your organization.

How much float can you use on Activity G if Activity B actually takes eight days to complete?