PMI PMI-SP - PMI Scheduling Professional
You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should at the 45 percent milestone today, but due to some early delays you're running late. What is the schedule variance of your project?
John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:

Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?
You are a project manager in a matrix environment and management is concerned about the utilization of the resources on your project team and when you'll release them. What project management plan will guide how and when project resources will be released from the project team?
Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project schedule. Which of the following is a tool and technique for the Schedule Development process?
You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your project will complete. Assuming that your project will not require any work to be completed over the upcoming weekends and that the remaining project work will commence on a Tuesday, what day of the week will the project end if there are 67 days of project work left to complete?
Which of the following statements best describes an activity in a project?
You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will you record for this activity?
You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?
Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95. What time will she record for this activity?
You are the project manager for your organization. You are working on creating the activity list so that you can create the project schedule. This current project is similar to a project you have completed for your company. You and the project team decide to use the previous project as a template for your current project. A template can help you and the project team do all of the following except for which one?