Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMI-SP - PMI Scheduling Professional

Page: 7 / 10
Total 323 questions

Which of the following processes involves the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress and performance as well as to forecast the project results?

A.

Identify stakeholders

B.

Performance reporting

C.

Plan communications

D.

Stakeholder analysis

You are the project manager of the NHQ Project. This project has a Budget at Completion of $750,000 and is expected to take 18 months to complete. The project is supposed to be 75 percent complete, but due to some errors the project is only 60 percent complete. At this time the project has spent $465,500. Management has asked you to review the project work and report the project's SPI. What is the SPI for this project?

A.

0.97

B.

0.80

C.

$562,500

D.

-$112,500

Fill in the blank with an appropriate phrase. The ________is defined in terms of either the product or the type of customer or industry sector.

You are the project manager for your project. Your project is scheduled to last for one year and you are currently forty percent complete with the project. Based on your current performance measurements you have an SPI of .95 and a cost variance of -$24,000. You need to report this information to the management, but you will also need a solution to present with the variance information. Which one of the following can you present to the management as a part of the control schedule tools and techniques for variances?

A.

Work performance measurements

B.

Corrective actions

C.

Trim the project scope

D.

Causes of variances

You are the project manager for your organization. You have worked with the project team to create the project scope statement. The key stakeholders have signed off on the project scope and they are eager for you and the project team to begin creating the deliverables identified within the project scope. What process must you and the project team complete next in this scenario?

A.

Create the activity list.

B.

Create the WBS.

C.

Create the risk assessment.

D.

Determine the project budget.

Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?

A.

Stakeholders are usually identified through a stakeholder register.

B.

Stakeholders are identified by the project team, project sponsor, and management.

C.

Stakeholders are identified through the project customers.

D.

Stakeholders are usually identified by interviewing identified stakeholders and expanding the list until all potential stakeholders are included.

Sam is the project manager for his organization. His project is not doing well on project schedule performance, and management wants him to predict how the project schedule and cost will end. Management has asked Sam to report and forecast his project's performance based on the Delphi Method, scenario building, technology forecasting, and to forecast by analogy. What forecasting method is management asking Sam to use?

A.

Judgmental methods

B.

Time series methods

C.

Causal/econometric methods

D.

Earned value management method

You work as a project manager for BlueWell Inc. You would like to crash your project to help the project schedule to get back on track. What is the primary danger of crashing?

A.

Crashing increases project costs.

B.

Crashing is a top-down approach to project completion.

C.

Crashing restricts resource utilization.

D.

Crashing always increases project risks.

Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen.

If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?

A.

$35,000

B.

$41,700

C.

$6,700

D.

$14,000

Ned is the project manager for his organization. Ned is using a standard tool to capture, store, and distribute information to the stakeholders about the project costs, schedule, and performance. What term is assigned to this communication tool?

A.

Project management information system

B.

Table reporting

C.

Reporting system

D.

Communications management system