Terri is the project manager for her organization and she is working with her project team to develop the project schedule. She has identified the float in her project although some of the activities where float exists may be susceptible to risk in the project execution. She is also concerned that the critical path may change during the project if the risk events come into execution. What scheduling method is Terri using in this example?
You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your cost variance for this project?
Andy is the project manager for his project. Andy and his project team are identifying stakeholders who can significantly impact the project, what the level of participation for each identified stakeholder may be, and classifying the stakeholders by common characteristics, concerns, and their perception of the project. Andy and his project team want to define an approach as a result of this information to gain support from the stakeholders for their project. What should Andy and his project team create in this scenario?
A company hires a scheduler for one of its projects. What skills should he possess to efficiently work with the project team? Each correct answer represents a complete solution. Choose three.
Allen works as a project manager of the NHY project. This project is scheduled to last for two years and has a BAC of $5,400,000. He is currently 45 percent complete with this project, though he is supposed to be at his second milestone, which accounts for half of the project completion. There have been some errors in the project, which have caused Allen to spend $2,093,754. What is this project's schedule variance?
Frank is the project manager in BlueWell Inc. He is working with his project to subdivide the project work packages into smaller, more manageable components. He and the project team are planning in detail all of the things the team will need to create, purchase, or do in order to satisfy the project scope. Management is concerned with the activity which Frank is using in this scenario, as they believe that Frank is taking too long to complete this pre-execution activity. Which of the following techniques of the activity process is Frank using in this example?
Which of the following provides a method to track project progress during project execution against what was planned?
You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project's budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?
You are the project manager for the GRT Project in your organization. You have created your time duration estimates based on historical information, but the estimates are not holding true in your current project. Unfortunately, many activities are late. You have decided to create a PERT estimate with your project team for each of their activities. What is the formula used for PERT?
Lara has been assigned to a construction project. The project includes constructing a residential building with fifty flats. On which of the following events will the project be considered successful?