The first step in creating a schedule is to…

A.

Create the WBS

B.

Create the RBS

C.

Estimate task durations

D.

Estimate project duration

True or False: Setting a project goal is the same as setting other goals.

A.

True

B.

False

Which of the following tasks might a project manager perform?

A.

Providing training

B.

Working with executives and sponsors

C.

Managing risks

D.

All of the above

_______ and _________are two ways to calculate activity estimates.

A.

PERT

B.

Scientific

C.

CAM

D.

CPM

If you are using external consultants to help design your plan you should ensure that only ______________ are shared rather than impressions, judgments, or opinions.

A.

Facts

B.

Inferences

C.

Spokespeople

D.

Pictorial Images

True or False: “How could we have handled that better?” is an example of a closed question.

A.

True

B.

False