What should be decided when configuring PRINCE2 effectively?

A.

What to remove and where to add guidance

B.

Where to put the emphasis and where to add guidance

C.

What to significantly change to create the right blend

D.

Which areas are not enabled to work with agile

Which artifact identifies risks associated with using an iterative project management approach?

A.

Project backlog

B.

Agilometer

C.

Risk management approach

D.

Definition of Done

Which is a benefit of the Lean Startup approach to releasing a product?

A.

It provide a technique to reduce the testing of a product before release

B.

It enables the release plans to be synchronized with the PRINCE2 plans

C.

It reduces the number of people needed to manage a release of a product

D.

It provides quick feedback that can be responded to at the earliest opportunity

What is typically displayed on a board to show progress to people working on a project?

A.

Agilometer assessment

B.

Product backlog

C.

Information radiator

D.

User story

What describes essential aspects of project management that must be applied consistently and throughout the project lifecycle?

A.

The project context

B.

The PRINCE2 practices

C.

The PRINCE2 processes

D.

The people element

When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?

A.

Preferable

B.

Typical

C.

Effective

Which artifact is used to describe the project's major products in the form of epic user stories?

A.

Project dashboard

B.

Release map

C.

Product backlog

D.

Project backlog

Which technique is used in the ’Issues' practice?

A.

Trading/swapping

B.

Objectives and key results

C.

Refactoring

D.

Delegation poker

What term is used to describe boards that display what work needs to be completed for people working on a project?

A.

Work in progress limit

B.

Information radiator

C.

Highlight report

D.

Glad! Sad! Mad!