Which statement explains the PRINCE2 Agile behavior of ‘exploration’?

A.

It empowers the project management team at the delivery level

B.

It uses the most effective channel to communicate information

C.

It displays the progress rate to everyone using burn-down charts

D.

It seeks out feedback collaboratively from project stakeholders

Which statement about the ‘accept that the customer doesn’t need everything’ target is correct?

A.

It gives confidence on the progress of the project

B.

It can result in the early delivery of a minimum viable product

C.

It allows misunderstandings to be dealt with appropriately

D.

It is achieved by managing the culture of the team carefully

Which TWO are the purposes of a highlight report?

1. To describe the MoSCoW priority of user stories.

2. To summarize the status of a work package.

3. To summarize the stage status.

4. To report any potential issues and risks

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Which statement defines a PRINCE2 principle?

A.

A PRINCE2 project defines its quality management approach

B.

A PRINCE2 project is monitored and controlled on a stage-by-stage basis

C.

A PRINCE2 project ensures a consistent approach to risk management

D.

A PRINCE2 project is tailored to suit the competitor’s environment

Which two statements about tailoring the business case in an agile environment are CORRECT?

1. It should be unnecessary because products of the highest value will be delivered first.

2. It should identify the minimum viable product and when it will be delivered.

3. It should take into account that the scope may be reduced during the course of the project.

4. It should show the features, the order in which they will be delivered and any dependencies.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

How should team working agreements be created?

A.

By the supplier subject matter expert agreeing what should be included

B.

By the customer representative deciding what should be included

C.

By team members agreeing on what should be included

D.

By the project manager deciding what should be included

Which statement BEST describes the PRINCE2 Agile guidance for change?

A.

The delivery team should be authorized to make changes at the detailed level

B.

The delivery team should quickly approve changes to the project baseline

C.

The executive should manage changes dynamically at the detailed level

D.

The executive should approve delivery level changes to harness the benefits of positive change