How does the change theme regard change in PRINCE2 Agile?

A.

As disruptive

B.

As something to be avoided

C.

As a necessity

D.

As inevitable

When creating the project product description, how should the purpose of the project product be defined?

A.

As an opportunity

B.

As a vision

C.

As an outcome

D.

As a goal

What does velocity typically measure?

A.

Work packages completed by the team

B.

The rate of progress the team is making

C.

The number of timeboxes completed

D.

The speed that a minimum viable product is created

To help with prioritization, what is MOST important when understanding the difference between scope and quality?

A.

Combining functional and non-functional requirements

B.

Creating non-functional requirements with user stories

C.

Differentiating functional from non-functional requirements

D.

Defining non-functional requirements before functional requirements

Which statement about the ‘directing a project’ process is CORRECT?

A.

The project board may pull reports from the information radiator

B.

As a minimum, the project board should receive oral reports from the project manager

C.

The project board should attend the delivery team’s daily stand up meeting

D.

The project board should receive regular reports focusing on cost and time overruns

Whose interests are specifically represented by the senior supplier?

1. Those ensuring the project is value for money.

2. Those who will use the project’s products.

3. Those who will be developing the project’s products.

4. Those responsible for the project’s technical integrity.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Which statement about velocity is CORRECT?

A.

It is based on the concept of rationalism

B.

It is shown by the ideal line on a bum-down chart

C.

It describes how much work is getting done

D.

It tracks the time and cost of a timebox

Which statement about timeboxes is CORRECT?

A.

Flow based working partitions work into timeboxes

B.

A project cannot be referred to as a timebox

C.

A timebox can contain another timebox

D.

Timeboxes should be avoided in business as usual environments

Which statement explains how the ‘learn from experience’ principle is applied in an agile context?

A.

It focuses on the prioritization and decomposition of requirements

B.

It integrates releases within management stages

C.

It is supported by the ‘inspect and adapt’ concept

D.

It provides guidance on mapping PRINCE2 roles to an agile environment

What should be decided when configuring PRINCE2 effectively?

A.

What to remove and where to add guidance

B.

Where to put the emphasis and where to add guidance

C.

What to significantly change to create the right blend

D.

Which areas are not enabled to work with agile