Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

PRINCE2 PRINCE2-Agile-Foundation - PRINCE2 Agile Foundation Exam

Page: 1 / 3
Total 92 questions

Which TWO statements describe a purpose of the business case?

1) To define the acceptance criteria for what the project must deliver.

2) To transfer responsibility for the work to the appropriate delivery team.

3) To document how significant risks will affect the expected project benefits.

4) To outline how and when the anticipated benefits can be measured.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Who needs to be aware that flexing what is delivered may affect the expected benefits of the project?

A.

Customer subject matter expert and the supplier representative

B.

The team manager and the senior supplier

C.

The project manager and the project board

D.

The team quality assurance and project support

Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?

A.

It should always be appropriate to the needs of the project

B.

It should always be addressed during the daily stand-ups

C.

It should always be carried out formally

D.

It should always be carried out informally

During which process should release planning be done for the FIRST time?

A.

Initiating a project

B.

Managing a stage boundary

C.

Managing product delivery

D.

Controlling a stage

Which BEST describes the senior user role when tailoring the organization theme?

A.

An ‘agile sponsor’

B.

An ‘executive sponsor’

C.

A ‘coach’

D.

A ‘super product owner’

Which is the BEST method of communication to gather feedback?

A.

Receiving emailed diagrams to encourage discussion

B.

Conducting online surveys to obtain a range of opinions

C.

Meeting face-to-face to encourage an exchange of views

D.

Discussing over the telephone to gather feedback quickly from stakeholders

Which is a purpose of the ‘controlling stage’ process?

A.

To execute and deliver the project product

B.

To establish whether the project is complete

C.

To report stage progress to the project board

D.

To draft the plan for the next stage’s work

Which statement about the ‘initiating a project’ process is CORRECT?

A.

The initiation stage plan should form part of the project plan

B.

The impact of frequent releases on quality management should be assessed

C.

The process should take more time than usual for disruptive projects

D.

The project solution should be documented in detail in the project product description

Which statement about the ‘keep teams stable’ target is CORRECT?

A.

It applies primarily to the long term, such as a project or a program

B.

It is the primary reason why the tolerance for cost is set to zero

C.

It prevents compromising the overall quality level of the product

D.

It results in the early delivery of a minimum viable product

In Lean Startup, what is based on the concept of ‘learn the most with the least effort’?

A.

A structured, timeboxed event

B.

A minimum viable product

C.

A measurement of lead times

D.

A set of criteria to determine whether work can be started