Scrum PSK-I - Professional Scrum with Kanban (PSK 1) Exam

Page: 2 / 3
Total 73 questions

True or False: Little's Law is used to forecast a Scrum Team's output.

A.

True

B.

False

What is Kanban?

(choose the best answer)

A.

A methodology aimed at visualizing your Workflow for effectiveness and enhance

productivity within the team.

B.

A strategy for optimizing the flow of value through a process that uses a visual, Work

in Progress (WIP) limited pull system.

C.

A set of practices that are additive to the Scrum framework.

D.

None of the above.

As input for Daily Scrum, which metrics are likely to provide the most actionable data?

(choose the best answer)

A.

Leading indicators.

B.

Lagging indicators.

Which of the following statements about supplementing Scrum with Kanban practices is true?

(choose the best answer)

A.

Scrum Teams may choose to skip the Sprint Planning event.

B.

It encourages team collaboration/swarming.

C.

It applies primarily to maintenance type of work.

D.

It implies that the Scrum Team must have a sequential approach to work.

A service level expectation (SLE) consists of which two items?

(choose the best two answers)

A.

A cost of delay.

B.

A probability.

C.

A forecasted date.

D.

A period of elapsed days.

Within the same Kanban system, Work in Progress (WIP), is NOT a leading indicator for:

(choose the best answer)

A.

Throughput.

B.

Story points delivered.

C.

Cycle Time.

D.

Number of Product Backlog items finished in a Sprint.

A Scrum Team's service level expectation (SLE) is an input into the various Scrum events. In

which event will SLE provide the most benefit towards maintaining good flow?

(choose the best answer)

A.

Sprint Review.

B.

Sprint Planning.

C.

Sprint Retrospective.

D.

Daily Scrum.

Which of these are typically included in the Definition of Workflow policies?

(Choose the best six answers)

A.

Visualization policies.

B.

Pull/prioritization policies.

C.

Service Level Expectations.

D.

WIP limits.

E.

Burndown chart.

F.

The Increment.

G.

Work Item types.

Which of the following metrics are likely to be reviewed during flow-based Daily Scrum?

(choose the best two answers)

A.

Work Item Age.

B.

Work in Progress (WIP).

C.

Process control chart and Scrum Team's 85th percentile.

D.

Lead Time.

E.

Throughput.

F.

Cycle Time.

G.

Velocity.

What are the four key flow metrics in Scrum with Kanban?

(choose the best answer)

A.

Work in Progress (WIP), Velocity, Lead Time, Cycle Time.

B.

Throughput, Work in Progress (WIP), Velocity, Lead Time.

C.

Velocity, Lead Time, Cycle Time, Cost.

D.

Work in Progress (WIP), Work Item Age, Throughput, Cycle Time.