What might be considered during the Sprint Retrospective once a team decides to supplement

their Scrum with Kanban?

(choose the best answer)

A.

Workflow.

B.

Current policies.

C.

WIP Limit.

D.

Metrics and charts such as Cumulative Flow Diagram, Cycle Time Scatterplot, and

Work Item Aging.

E.

All of the answers.

What flow metric best indicates when multiple items from the Product Backlog will be finished?

A.

Throughput.

B.

Cycle Time.

C.

Work Item Age.

D.

Work in Progress (WIP).

What qualitative information can you get from a Cycle Time Scatterplot?

(choose the best answer)

A.

General Cycle Time trends.

B.

Single Cycle Time outliers.

C.

Clusters of Cycle Time outliers.

D.

All of the answers.

When the Developers limit Work in Progress (WIP) inside a Sprint, what would you expect to observe?

(Choose the best three answers)

A.

The Developers would stop beginning work, and instead, start finishing work.

B.

The amount of work done by the end of the Sprint would be reduced.

C.

Increased collaboration/swarming between the Developers.

D.

Self-management would be strengthened as a result of increased transparency.

True or False: The primary effect of limiting Work in Progress (WIP) is that it creates a pull

system.

A.

True

B.

False

For teams practicing Professional Scrum with Kanban, what are the most appropriate metrics

to inspect?

(choose the best answer)

A.

Control Chart, CFD and Aging Chart.

B.

Story points and historical velocity.

C.

User stories t-shirt size.

D.

All of the answers.

E.

None of these are Kanban for Scrum Teams metrics.

What should the Developers do if, during the Sprint, the Product Owner asks them to add an

urgent unplanned work item that aligns to the Sprint Goal but does not fit into the current Work

in Progress (WIP) Limits?

(choose the two best answers)

A.

Add the urgent item to their Sprint Backlog but only start working on it when their

WIP Limits allow it.

B.

Adjust the WIP Limits to allow for taking on the extra item and record it as part of

their Definition of Workflow.

C.

Take on the urgent item as an exception to the WIP Limits and visualize that

they are above their WIP Limit.

D.

Reject the urgent item since the WIP Limits do not allow it. Tell the Product

Owner to wait until the next Sprint.

Little's Law states that:

(choose the best answer)

A.

Average Cycle Time = Average Work in Progress / Average Throughput.

B.

Average Throughput = Average Cycle Time * Average Work in Progress.

C.

Average Work in Progress = Average Cycle Time / Average Throughput.

D.

Average Throughput = Average Cycle Time / Average Work in Progress.

True or False: When the Developers add Kanban to Scrum, the way they use the Sprint Goal

during their Daily Scrum changes.

A.

True

B.

False

True or False: A Scrum Team using Kanban does not need to craft a Sprint Goal during Sprint Planning. They can instead create one “on-demand” as new work flows into the Sprint Backlog.

A.

True

B.

False