Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

Scrum PSM-I - Professional Scrum Master I

Page: 8 / 9
Total 298 questions

Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?

A.

It is a complete list of all work to be done in a Sprint.

B.

Every item has a designated owner.

C.

Each task is estimated in hours.

D.

It is the Development Team ' s plan for the Sprint.

E.

It is ordered by the Product Owner.

As the Sprint Planning progresses, the Developers realize that the workload may be greater

than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)

A.

Recruit additional Developers before the work can begim

B.

The Developers ensure that the Scrum Team is aware, start the Sprint, and

monitor progress.

C.

The Developers work overtime during this Sprint

D.

Cancel the Sprint

E.

Remove or change selected Product Backlog items.

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum?

(choose the best two answers)

A.

Identification of impediments that may prevent the Developers from achieving the Sprint Goal.

B.

An update of completed tasks and of the remaining work so the Scrum Master

can plan the next day.

C.

An updated Scrum board to make Sprint progress transparent for the

stakeholders.

D.

A shared understanding of the most important work to be undertaken next to

achieve the best possible progress toward the Sprint goal.

E.

A status report for the upper management indicating what each individual has done, will be doing, and what is impeding him/her.

Which three behaviors demonstrate that a team is self-organizing? (Choose three.)

A.

Stakeholders walking in at the Daily Scrum to check progress and work with the Scrum Master to optimize the functional scope for the Sprint.

B.

The Development Team members are working within the boundaries of their functional description and nicely handing off work from analyst to developer to tester to integration.

C.

The Product Owner doesn’t need to be at Sprint Retrospectives.

D.

The Development Team creating their own sprint backlog, reflecting all work that is part of the definition of “Done”.

E.

The Development Team has all the skills needed to create a releasable Increment.

F.

Development Team members collaboratively selecting their own work during the Sprint.

G.

The Development Team inviting external people to the Sprint Planning to ask them how to turn a Product Backlog item into an Increment via a complete and detailed Sprint Backlog.

How much time is required after a Sprint to prepare for the next Sprint?

A.

The break between Sprints is time-boxed to 1 week for 30 day Sprints, and usually less for shorter sprints.

B.

Enough time for the requirements for the next Sprint to be determined and documented.

C.

Enough time for the Development team to finish the testing from the last Sprint.

D.

None. A new Sprint starts immediately following the end of the previous Sprint.

E.

All of the above are allowed depending on the situation.

When is it most appropriate for a Scrum Team to change the definition of “Done”?

A.

During Spring Planning.

B.

Prior to starting a new Sprint.

C.

During the Sprint Retrospective.

D.

Prior to starting a new project.

(When does a Developer become accountable for an item in the Sprint Backlog?

Choose the best answer.)

A.

During the Daily Scrum.

B.

Never. All Developers on the Scrum Team share accountability for items in the Sprint Backlog.

C.

As soon as a Developer on the Scrum Team can accommodate more work.

D.

At Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers.

Which statement best describes Scrum?

(choose the best answer)

A.

A defined and predictive process that conforms to the principles of Scientific

Management

B.

A framework to generate value through adaptive solutions tor complex problems.

C.

A cookbook that defines best practices tor software development.

D.

A complete methodology that defines how to develop software.

(Why do the Developers need a Sprint Goal?

Choose the best answer.)

A.

A Sprint Goal only gives purpose to Sprint 0.

B.

Sprint Goals are not valuable. Everything is known from the Product Backlog.

C.

A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.

D.

The Developers are more focused with a common yet specific goal.

True or False: The Product Owner makes sure the Developers select enough from the Product

Backlog tor a Sprint to satisfy the stakeholders.

A.

True

B.

False