Scrum PSM-I - Professional Scrum Master I

Page: 9 / 9
Total 298 questions

(The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a component. Without that component, there will not be enough work in the next Sprint to occupy the full team. As the Scrum Master, what advice would you give the Product Owner?

Choose the best answer.)

A.

Remind the Product Owner that their primary concern is the flow of value reflected in the ordering of the Product Backlog.

B.

Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate Sprint.

C.

Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Developers.

Choose two responsibilities of a self-organizing Development Team. (Choose two.)

A.

Reorder the Product Backlog.

B.

Pull Product Backlog items for the Sprint.

C.

Do the work planned in the Sprint Backlog.

D.

Increase velocity.

E.

Report daily progress to stakeholders.

Every Scrum Team should nave:

(choose the best answer)

A.

One Lead Developer and no more than 8 other members.

B.

The competencies and skills needed to deliver an Increment in a Sprint

C.

At least one representative from each major department, such as, Quality Assurance, Development, and Marketing.

When multiple Scrum Teams are working on the same product, should all of their Increments be

integrated every Sprint? (choose the best answer)

A.

Yes, but only for Scrum Teams whose work has dependencies.

B.

No, that is tar too nard and must be done in a hardening Sprint

C.

No, each Scrum Team stands alone.

D.

Yes, in order to accurately inspect what is done.

During a Sprint Retrospective, for what is the Scrum Master responsible?

A.

Prioritizing the resulting action items.

B.

Participating as a Scrum team member and facilitating as requested or needed.

C.

Acting as a scribe to capture the Development Team’s answers.

D.

Summarizing and reporting the discussions to management.

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What factors likely led to this? (Choose two.)

A.

The Project Management Office (PMO) has not been engaged adequately.

B.

The Product Owner has not been keeping the stakeholders aware of the progress of the project.

C.

The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.

D.

The stakeholders were not allowed to enter the development area.

To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, a Development Team to implement those ideas and a Scrum Master to help guide the process.

A.

True

B.

False

Who is responsible for the sizing of Product Backlog items?

(choose the best answer)

A.

The Developers after clarifying requirements with the Product Owner

B.

The Scrum Master.

C.

The Product Owner with input from the Developers.

D.

The Developers, alone.

E.

The most senior people in the organization, including architects and subject matter experts.