Scrum PSM-II - Professional Scrum Master II
Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product The stakeholder is unhappy with the slow performance, a complaint that the Product Owner agreeswithAs the Scrum Master how will you move this forward?
(choose the best answer)
Self-management is more effective when it happens within boundaries.
Select two relevant boundaries for self-management provided by the Scrum framework.
(choose the best two answers)
During Sprint Planning, Developers work with the Product Owner to create a forecast for the Sprint. A forecast is a selection of Product Backlog items that the Developers believe are possible to get done by the end of the Sprint. Select two things that explain what done means.
(choose the best two answers)
You are a Scrum Master and one of the Developers approaches you and says: Every Sprint we are not completing regression testing for all of the selected Product Backlog items in the Sprint, but regression testing is part of the Definition of Done. We have discussed with the Product Owner and during the Sprint we decided to change the Definition of Done to remove regression testing. Which two actions are appropriate in this situation?
(choose the best two answers)
Your Scrum Team has been working together for over a dozen Sprints. The Scrum Team consists of 10 members. Each Sprint takes four weeks. As a Scrum Master, you observe that the Developers are hardly collaborating; during the Sprint, members are primarily working on their own items. You also notice that the items on the Sprint Backlog are mostly unrelated. You suspect that the lack of a Sprint Goal might be the cause.
Although you have encouraged the use of a Sprint Goal, both the Product Owner and the Developers have concluded that they are unable to create Sprint Goals based on the wide variety of items on their Product Backlog.
What might explain why this Scrum Team is struggling to craft a Sprint Goal?
(choose all that apply)
True or False: Using Scrum ensures that adding more resources to a project proportionally increases the value delivered.
A Scrum Master colleague of yours wants some guidance on what to do in the following situation. During the Daily Scrum, one Scrum Team member, who is a key central figure in the organization, drags on and on about things which actually are interesting but not relevant for the Daily Scrum, day after day. What are two suggestions you would offer to your colleague?
(choose the best two answers)
What can the Scrum Value of openness easily impact?
(choose the best answer)
In an environment where user acceptance testing is required before the Increment can be put into production, a development manager proposes to have user acceptance testing done every third Sprint, because the feedback from the user acceptance tests are disrupting work in Sprints. Is this a good idea?
(choose the best answer)
Towards the end of Sprint Planning, the Product Owner and the Developers have not been able to reach a clear, mutual understanding about the highest order Product Backlog items. Because of this, the Developers could not figure out how many Product Backlog items they could forecast for the upcoming Sprint. The Product Owner did make it clear what business objective he is hoping to achieve with this Sprint. Which of the following two actions would you support?
(choose the best two answers)