True or False: A Product Owner with multiple teams working on one product should maintain

separate Product Backlogs for each team.

A.

True

B.

False

A Sprint Retrospective should be held:

(choose the best answer)

A.

Only when the Scrum Team determines it needs one.

B.

At the end of the last Sprint in a project or a release.

C.

At the end of each Sprint.

D.

At the beginning of each Sprint.

Who is accountable for creating a valuable and usable Increment each Sprint?

(choose the best answer)

A.

The Developers.

B.

The CEO.

C.

The Product Owner.

D.

The Scrum Master.

E.

The Scrum Team.

The length of a Sprint should be:

(choose the best answer)

A.

Short enough to keep the business risk acceptable to the Product Owner.

B.

Short enough to be able to synchronize the development work with other business events.

C.

No more than one calendar month.

D.

All of the above.

Which statement best describes Scrum?

(choose the best answer)

A.

A defined and predictive process that conforms to the principles of Scientific Management.

B.

A complete methodology that defines how to develop software.

C.

A framework to generate value through adaptive solutions for complex problems.

D.

A cookbook that defines best practices for software development.

Why do the Developers need a Sprint Goal?

(choose the best answer)

A.

A Sprint Goal only gives purpose to Sprint O.

B.

Sprint Goals are not valuable. Everything is known from the Product Backlog.

C.

The Developers are more focused with a common yet specific goal.

D.

A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.

True or False: The Scrum Team is accountable for creating a valuable increment every Sprint.

A.

True

B.

False

Which metrics will help a Product Owner determine if a product is delivering value?

(choose the best two answers)

A.

Customer satisfaction.

B.

Productivity.

C.

Velocity.

D.

Time to market.

E.

Percentage of scope implemented.

Which of the following are criteria to order Product Backlog items?

(choose the best three answers)

A.

The value of the Product Backlog items.

B.

The availability of the Scrum Master.

C.

Dependencies between Product Backlog items.

D.

Their relevance to achieving the Product Goal.

E.

The number of stakeholders who approve of the item.

True or False: Scrum has a role called "Project Manager".

A.

True

B.

False