Assume you are working in a division in your country's Department of Interior. The Department is set up in Bureaus, and your work falls within Natural Resources. Your division is the Water Resource Division. You are responsible as the portfolio manager for the work in this Division. As you work on the portfolio for the upcoming year, you point out to the members of the Portfolio Review Committee that:

A.

The projects in the portfolio have interdependencies between them

B.

Your portfolio reflects your Division's objectives

C.

Each program and project in the portfolio have related objectives

D.

Your portfolio addresses different strategies than those in other parts of the Department

In your diversified chicken products company, your portfolio of components in progress consists of approximately 175 programs, projects, and other work. Generally, at each Portfolio Review Board meeting, about 35 new proposals are reviewed to see if they should be part of the portfolio. As the portfolio manager, you have set up categories for these components. They are useful to facilitate portfolio optimization because:

A.

They use filtering to eliminate certain components from consideration

B.

They help identify the components that meet requirements for consideration

C.

They serve as key evaluation criteria

D.

They address organizational strategy and objectives

Your organization conducted an OPM3 assessment focusing on its best practices in portfolio management and also on those that were needed. The OPM3 Certified Professional felt greater attention was needed managing strategic change. This means:

A.

The project charter should be reviewed

B.

The strategic plan should be updated

C.

Budget allocation can be handled more effectively

D.

It is easier to determine which components will require specialized resources

Working as the portfolio manager for your business unit of a major aerospace organization means you have a variety of programs, projects, and operational activities under way. You have set up a number of reports on the progress of the portfolio for your various stakeholders, but the best approach is to monitor the progress of the portfolio against:

A.

Organizational strategy

B.

Organizational goals

C.

Specific key performance indicators for the business unit

D.

Organizational critical success factors

The portfolio undergoes a lot of changes through the portfolio life cycle, and the state of the portfolio changes on the go. Some components are terminated, other are added and initiated. When it comes to the authorize portfolio process, which of the following represents the state of the portfolio

A.

List of current components that need to be weighted, scored and ranked

B.

List of selected and balanced components

C.

List of strategically aligned portfolio components without the need for them to be balanced

D.

List of selected, balanced and authorized components ready to be initiated

A portfolio manager needs to continuously balance the need and requirements with the available resources and needs to maintain a balanced portfolio and portfolio resources in order to optimize delivery. Capability and Capacity analysis is performed in 4 of the portfolio management processes and it serves a slightly different purpose in each and every one of them. When it relates to optimizing portfolio, what is the purpose of using this analysis?

A.

To study the capability of resources, match them against the portfolio’s objectives and goals, and translate the capability into what capacity is possible to meet the portfolio demands

B.

Performed to understand the human, financial, and asset capacity and capability of the organization in order to select, fund, and execute portfolio components

C.

To understand how much work is able to be performed based on the resources available (capacity), as well as the ability of the organization to source and execute the selected portfolio

D.

It enables the organization to achieve maximum portfolio benefits given current resource constraints

Your sponsor has urged you to analyze Portfolio Risk before the end-of-week governance board meeting as the CEO will be present and is interested in Portfolio risk data in particular. Currently, you do not have adequate risk information in order to analyze data and give recommendations. Which tool is the most suitable for you to use in this case?

A.

Cumulative distribution

B.

Weighted Ranking and Scoring Techniques

C.

Delphi

D.

Graphical Analytical methods

During one of the management meetings, an opportunity was identified. This opportunity has a huge impact on the portfolio. What is your first action as a portfolio manager?

A.

Document it in the benefits register

B.

Update the portfolio management plan

C.

Document it in the risk register

D.

Update the portfolio roadmap

As the portfolio manager you have worked to consider the complexities involved of the interdependencies in your programs, projects, and ongoing work. As your portfolio process has been implemented for three years, a key challenge is that senior executives tend to change priorities often even though programs and projects are being implemented. Often these programs and projects are cross-functional, and the result is your process is not coordinated. You recognize there is a need to change, and you met with the Chair of the Portfolio Review Board and have her support for a transparent approach for portfolio standards and prioritization. You should:

A.

Revise the balancing process

B.

Revise the portfolio management plan

C.

Revise the scoring model

D.

Set up a standard method to communicate change

The interest, influence, and communication needs of business operational stakeholders who are looking to ensure alignment between portfolio components, while minimizing negative impact and maximizing positive benefits of all portfolio-managed changes to their business operations, relate to which type of stakeholders?

A.

Internal and External Stakeholders

B.

External Stakeholders

C.

Does not relate to stakeholders

D.

Internal Stakeholders