PMI PfMP - Portfolio Management Professional (PfMP)
When initiating portfolio components and terminating other, you come up with updates to budget, funding and resources allocations. Where should these updates be recorded?
Due to a strategic change, multiple components on your portfolio have been terminated, leaving you with limited remaining funds coming from the terminated components. What should be your best course of action?
Assume you are the portfolio manager for the Federal Railroad Administration. Funding is provided annually according to the Government's budget process. Any monies that are not spent at the end of a fiscal year are lost, and there are some restrictions in place concerning whether funds can be transferred to different programs, projects, or operations work in the agency. Therefore, to maximize the use of funding you require:
You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. Risk Categories, criteria and probability and impact are updated as a result of Developing the Risk Management Plan. These updates are recorded in which of the following?
A portfolio manager needs to continuously balance the need and requirements with the available resources and needs to maintain a balanced portfolio and portfolio resources in order to optimize delivery. Capability and Capacity analysis is performed in 4 of the portfolio management processes and it serves a slightly different purpose in each and every one of them. You are currently using it in the development of your charter. What is its purpose in this case?
In a portfolio, data is an abundant asset, and managing the information aiming for a better decision making is critical. Information is considered to be the link between the portfolio activities and entities. You are currently collecting, analyzing, storing, and delivering portfolio information to stakeholders in accordance with their requirements. What can help you in doing this?
Your company has multiple portfolios on the way and a variety of different clients and industries. Risk levels are high due to recent governmental regulations and the company has recently been penalized due to a non-compliance to one of the standards. You know that you need to closely managing this. As a result, you will be come out with
Following a major organizational restructuring, new portfolios are currently being initiated. You have been assigned the position of portfolio manager on one of the major portfolios and are currently in strategic management. You are currently meeting with stakeholders to document the internal and external financial dependencies and shared resources between different portfolio components. Which of the following techniques are you performing
The governance board has an integral part in the realization of the portfolio strategic value. In your opinion as a portfolio manager, Governance board decisions are based on
As the Director of the Portfolio Management Office at your worldwide furniture store, you prepare a series of reports on the status of the portfolio. One report that you use is a bubble diagram. In using it in terms of resource supply and demand, you should structure it to show: