PMI PgMP - Program Management Professional (PgMP)
A program manager initiates a new global program to create a higher level of protection for a company's intellectual property. The company exhibits a relaxed culture and environment, and is intolerant of processes to the point of being considered process-adverse. However, the company's culture is tolerant of long-term program activities, provided there is continuous progress on improving the protection of its intellectual property. Expectations for rapid progress are low.
What should the program manager do next?
A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting.
What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program?
At what point in the project is the risk of failing to achieve the project objectives the greatest?
An organization requests that a junior project manager, with no previous experience or training in the industry, take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.
How should the junior project manager respond to this request?
A program to implement a company's new system is nearing completion and the program manager attempts to close the program. However, despite training provided to the operational staff on the new system, there is concern that the defined expected benefits will not be fully realized.
To prevent this concern in the future, which of the following should occur?
Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits?
Near the end of an ongoing project, the program manager is terminated due to underperformance and a new program manager joins the team. The program's last component project will go live in one week.
What must the new program manager do before program closure?
A program in a matrix organization includes subprojects for specific required technologies. The program manager assembles a team of project managers to lead each of the component projects. Each component project requires unique technical skills and expertise. To ensure that there are no budget overruns, the program manager leverages the existing time reporting process.
What is a critical component of the Program Schedule Management Process?
The chief executive officer reminds a program manager that a program must deliver a 30% reduction in customer complaints by the end of the year.
Where is this expectation documented?
A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?