PRINCE2 Prince2-Foundation - PRINCE2 7 Foundation written Exam
Which TWO are objectives of the 'closing a project’ process?
1. To confirm to the project board that each stage’s products are approved
2. To review whether the project was delivered within time and cost tolerances
3. To confirm whether operational staff are happy to take ownership of the products
4. To confirm that there is authority to close the project
In which step of the 'risk management technique should the organization's environment be considered?
When is a work breakdown structure MOST useful?
How is Uncertainty Identified, assessed and controlled?
The senior user needs to understand how user assurance will support the senior user on the project.
Which management product should the senior user review?
The project manager needs to record the impact assessment for a specific business opportunity.
In which management product should the project manager record this?
The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.
Which element of effective business case management is the senior user applying?
Which term is defined as the means by which an organization transitions to a desired future state?
The project board is reviewing the project initiation documentation (PID) to decide whether the project should continue or close. What should the project board ensure the PID is aligned with?
Which statement about capability and competency within a project is CORRECT?