What does the communication management approach define?

1. How versions of products will be described on information sent to interested parties

2. How information should be sent to interested parties

3. How often information should be sent to interested parties

4. How the PRINCE2 roles will be combined during the project

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

During the ‘initiating a project’ process, who specifies the required level of management control?

A.

Corporate, programme management or customer

B.

Project board

C.

Project manager

D.

Project assurance

Which is a purpose of the 'controlling a stage' process?

A.

To review the success of the project at the end of a management stage

B.

To agree work package acceptance and delivery requirements

C.

To produce regular highlight reports for the project board

D.

To re-plan the current stage and the project when requested

Which is a benefit of applying the ‘tailor to suit the project’ principle?

A.

Project management becomes less bureaucratic

B.

The capability of leadership is strengthened

C.

The project environment complexity is reduced

D.

The number of outputs is reduced

Which statement about project roles is CORRECT?

A.

The project organization must be defined using the roles and responsibilities in PRINCE2

B.

The project team structure defined in PRINCE2 must be used, but other roles may be added

C.

The project board roles defined in PRINCE2 must be used, but other roles can be defined as required

D.

Any role can be defined as required the responsibilities defined in PRINCE2 are fulfilled

Which TWO are objectives of the ‘controlling a stage process?

1. To focus attention on achieving Work Within) the agree tolerances

2. To create follow on action recommendations for all open issues and risks

3. To understand how the quality required will be achieved

4. To ensure that the stage’s products meet-agreed quality expectations

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Which is a purpose of the 'initiating a project' process?

A.

To ensure the project has a sound basis before asking the project board to authorize the project

B.

To authorize the stage plan for the next management stage of the project

C.

To establish a contract between the project management team and the commissioning organization

D.

To ensure that prerequisites are in place before starting the project

How should the "managing a stage boundary' process be used towards the end of a project's final delivery stage?

A.

To plan the activities of the closing a project' process

B.

To implement any exception plan requests from the project board

C.

To create a benefits management approach for corporate, programme management or the customer

D.

To review an issue received from a team manager

Which is a benefit of using PRINCE2?

A.

It promotes consistency of project work and the ability to reuse project assets.

B.

It includes techniques for critical path analysis and earned value analysis

C.

It enables a project manager to be accountable for the success of a project

D.

It prevents any changes once the scope of a project has been agreed

Which is a minimum requirement for applying the 'change' theme?

A.

Specify in the change control approach the means by which project products will be protected

B.

Document the format and contents of the issue register

C.

Produce issue reports to document the impact assessment for requests for change

D.

Delegate the change authority to the senior supplier(s) for supplier off-specifications