Which statement about the length of management stages in a project is CORRECT?

A.

A higher level of major risk will require a stage to be longer

B.

Stage length is influenced by project board availability

C.

A higher level of major risk will require a stage to be shorter

D.

Use of management stages represents a time driven control

Who is responsible for documenting any tailoring of the business case theme?

A.

Executive

B.

Business project assurance

C.

Project manager

D.

Corporate management

Which management level should approve a course of action if project-level tolerance is exceeded?

A.

Corporate, programme management or the customer

B.

Project board

C.

Project manager

D.

Team manager

Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?

A.

Each party may have their own business case for undertaking the project

B.

Both parties must apply the same external governance to the project

C.

The risk appetite should be collaboratively set before the project starts

D.

Management systems need to be unified for successful project delivery

Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?

A.

Increase the frequency of checkpoint reports

B.

Allow the team manager more flexibility to exceed cost tolerance

C.

Increase the frequency of event-driven controls

D.

Increase the frequency of escalations by the team manager

Which is a purpose of a Lessons Log?

A.

Note any lessons that are raised in Checkpoint Reports

B.

Record that corrective action is being taken

C.

Escalate lessons to the Project Board

D.

Raise improvements with Project Assurance

What theme estimates the cost of delivering the project?

A.

Business Case

B.

Change

C.

Plans

D.

Progress

Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.

A.

a solution should be designed for

B.

an issue should be created for

C.

the agreed actions should be recorded for

D.

the chair will approve the solution to

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

A.

Directing a Project

B.

Controlling a Stage

C.

Managing a Stage Boundary

D.

Managing Product Delivery

Which is a type of issue?

A.

A lesson

B.

A request for change

C.

An Exception Report

D.

A risk with an estimated high impact