What is an advantage of dividing the project into stages?

A.

Detailed plans can be prepared closer to the time events will take place

B.

the project board can delegate management of the project to team managers

C.

The project can be authorized by the project manager on a stage by stage basis

D.

The project brief can be updated towards the end of each stage

When developing a business case, the project manager reviewed the end project report from & previous similar project that stated had been underestimated on the project.

Which principle is being applied by the project manager when reviewing this information?

A.

Learn from experience

B.

Tailor ta Suit the project

C.

Manage by stages

D.

Ensure continued business justification

In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?

A.

Preparing estimates

B.

Defining and analyzing the products

C.

Organizing work packages

D.

Preparing a schedule

A new team member has joined the project team and wants to understand who else is on the project team, and who they report to.

Which management product should the team member review?

A.

Project plan

B.

Project management team structure

C.

Role descriptions

D.

Project log

Which is an objective of the 'controlling a stage' process?

A.

To review the business justification for the project

B.

To replan the current stage when directed

C.

To develop products to defined quality criteria

D.

To produce a learn plan for the work package

Which process is used by the project board to respond to on exception report?

A.

Controlling a stage

B.

Managing a stage boundary

C.

Managing product delivery

D.

Directing a project

How does PRINCE2 ensure that the specific management needs of an organization are met?

A.

By incorporating tailoring

B.

By mandating training

C.

By focusing on viability

D.

By representing best practice

Which process provides information for the project board to review an updated project plan?

A.

Initiating a project

B.

Controlling a stage

C.

Directing a project

D.

Managing a stage boundary

When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.

A.

Defined acceptance criteria

B.

the PRINCE2 principles

C.

the terminology used

D.

the number of themes applied

What is the result of the change derived from using the project’s product?

A.

Benefit

B.

Dis-benefit

C.

Outcome

D.

Output