Who would be responsible for maintaining the Configuration Item Records?

A.

Project Manager

B.

Project Support

C.

Project Assurance

D.

Team Manager

Scenario:

The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.

Having created the Issue Report and analyzed the impact of removing the Facilities Division from the scope of the Outsourcing project, the proposed option exceeds tolerance. \Nhat is the next action the Project Manager should consider?

A.

Create an Exception Report to inform the Project Board of the situation and the available options.

B.

Update the associated Configuration Item Records with details of the Issue Report that caused the change.

C.

Amend the Stage Plan for stage 3: remove all products related to the Facilities Division and add the activities required to deliver the new Government initiative.

D.

Create an Exception Plan to change all of the project's products to reflect the exclusion of services provided by the Facilities Division.

Which of the following activities could trigger the production of an exception plan?

A.

Review Stage status

B.

Giving ad hoc direction

C.

Escalating a project issue

D.

Report stage end

The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?

A.

Scope, People & Resources, Benefit

B.

Scope, Risk, Product

C.

Risk, Benefit, Product

D.

Scope, Risk, Benefit

Which of the following activities is NOT an action of preparing for planned closure?

A.

Update the project plan with actual

B.

Update the Project Management Team

C.

Request a product status account

D.

Confirm project has delivered what is defined in Project Product Description

When updating the project plan as part of Managing a stage boundary, what else might be updated?

A.

Exception Plan

B.

Project Management team

C.

Business Case

D.

Project Initiation Documentation

Which principle is supported by the activity Evaluate the Project?

A.

Continued Business Justification

B.

Defined roles and responsibilities

C.

Learn from experience

D.

Manage by stages

Which of the following management products ARE updated as part of Managing a stage boundary?

1. Business Case

2. Benefits Review Plan

3. Configuration Item Records

4. Project Brief

A.

1, 2, 3

B.

1, 3, 4

C.

1, 2, 4

D.

2, 3, 4

Which of the following statements is FALSE regarding the Continued Business Justification?

A.

The justification for the project must remain the same throughout the project.

B.

The justification for the project should remain vabd.

C.

The justification for the project may change.

D.

If the project is no longer justified it should be stopped.

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

There is a major concern over an apparent lack of control of project documentation.

For each concern listed in Column 1, select from Column 2 the configuration management task that could help address the problem. Each selection from Column 2 can be used once, more than once or not at all.