Scenario:

The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.

According to PRINCE2, which statement about the Configuration Management Strategy for the Outsourcing project is correct?

A.

Every project needs a Configuration Management Strategy, even if the organization has existing configuration management standards, because every project has different circumstances.

B.

A separate Configuration Management Strategy will be required for each of the suppliers within this project because each will have a different way of managing and storing products.

C.

A Configuration Management Strategy is unnecessary for this project because the MFH document control process is documented. It is acceptable simply to reference this in the Quality Management Strategy.

Scenario:

The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.

Having created the Issue Report and analyzed the impact of removing the Facilities Division from the scope of the Outsourcing project, the proposed option exceeds tolerance. \Nhat is the next action the Project Manager should consider?

A.

Create an Exception Report to inform the Project Board of the situation and the available options.

B.

Update the associated Configuration Item Records with details of the Issue Report that caused the change.

C.

Amend the Stage Plan for stage 3: remove all products related to the Facilities Division and add the activities required to deliver the new Government initiative.

D.

Create an Exception Plan to change all of the project's products to reflect the exclusion of services provided by the Facilities Division.

Scenario:

The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.

What additional risk will this place on the project?

A.

None because risks associated with the centralization and rationalization of the Facilities Division will be managed by another project.

B.

These changes will delay stage 3 by three weeks.

C.

There is only £70k left in the project change budget.

D.

The reduced value of the contracted services required by the Outsourcing project may result in an insufficient number of proposals being received.

If the Project Board are too busy to authorize all change requests themselves, they can appoint?

A.

A Change Authority

B.

A Change Board

C.

A Change Committee

D.

A Change Budget

When examining a project issue, which three aspects should be considered?

1. Performance targets

2. Business Case

3. Resources

4. Risk

A.

1, 3, 4

B.

2, 3, 4

C.

1, 2, 4

D.

1, 2, 3

Scenario:

The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.

What products will be impacted by this change?

A.

All of the project's products created so far.

B.

Only those products created in the first three weeks of stage 3.

C.

All of the project's products which relate to or include services provided by the Facilities Division.

D.

No products would need to be changed but some will need to be removed from the project.

STARTING UP A PROJECT

Here are three actions carried out by the project manager during the ‘starting up a project’ process.

As part of which activity (A-F) should each action be carried out?

Choose only one activity for each action. Each activity can be used once, more than once, or not at all.

The senior user is concerned that the trainers' limited availability could delay their accreditation. This was discussed during the 'starting up a project' process, but during the 'initiating a project' process the project manager notices that it has not been recorded.

Which action should the project manager take FIRST?

A.

Add appropriate activities to the project plan to manage the concern and avoid any adverse impact.

B.

Raise an exception report to manage the impact that any such delay would have on the project plan.

C.

Raise an issue report so that the trainers' time can be allocated to the accreditation activities.

D.

Add the information to the risk register so that it can be evaluated and an action decided.

The work package to produce the 'updated corporate quality procedures' was created during stage 3. Before accepting the work package, the team manager produces the team plan and finds that the expected delivery date is unrealistic. As a result, the project manager agrees an extra two weeks to complete the work package, within the current stage tolerance. The work package is then accepted by the team manager.

Is this an appropriate application of the 'manage product delivery' process, and why?

A.

Yes, because the team manager should set the time required to complete a work package.

B.

Yes, because the team manager should agree the limits within which the work is to be completed.

C.

No, because the work package, defined by the project manager, should not be changed.

D.

No, because the use of the stage time tolerance should be authorized by the project board.

At the end of stage 2, an external consultant responsible for developing the 'e-learning course', was appointed to the project board as a senior supplier. The stage 3 plan identifies the consultant as a reviewer of the 'e-learning course'. When preparing for a quality review of the 'e-learning course', the consultant found 15 possible errors. The consultant then documented these possible errors in the quality register.

Is this an appropriate activity when preparing for a quality review, and why?

A.

Yes, because each team manager should update the quality register as quality review activities are completed.

B.

Yes, because the quality reviewers should update the quality register as quality review activities are completed.

C.

No, because possible errors that are found when preparing for a quality review should be documented on a question list.

D.

No, because the senior supplier should not be identified as a reviewer as part of the quality review technique.