Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

BICSI RCDDv14.1 - BICSI Registered Communications Distribution Designer – RCDDv14.1

Page: 5 / 10
Total 320 questions

In order for an ICT distribution designer to identify the BEST solutions for the client's needs they may have to provide

A.

Operation and Maintenance manuals

B.

subcontractors lists

C.

material lists (e.g., BOM).

D.

shop drawings

An ICT distribution designer is providing labeling for a data center room number 2A, located on the second floor having 10 rows of cabinets. Which of the following identifiers/labels would the designer attach to the bonding and grounding conductor between the first cabinet in the 6th row and the data center ground bar?

A.

2A/R601.1

B.

2A-SBB/R601.1

C.

2/R6

D.

TEF1/R601.1

A large international manufacturing company is centralizing its IT which is currently spread over 16 countries. The transition means physically regrouping the infrastructure and aligning processes and organizations The high-level scope of this transformation encompasses three main areas.

1. The technology area—assessing which technology/tooling should be retained for the target data center

2. The policies and procedure area-aimed at establishing a common set of processes supporting the new way of delivering services

3. The HR area-assuring the new organization best fits the diversity of the countries and functional domains, while offering equivalent compensations for comparable functions

You have selected your team and you are preparing the business case to support 1) the team selections you made and 2) your recommendation to proceed to the program's next phase

Which document should be present m your business case?

A.

A detailed plan showing dependencies among the constituent protects

B.

A comprehensive analysis of the different compensation packages offered in the 16 countries

C.

An inventory detailing all physical and logical components in place and the employees in scope

D.

A cost/benefit analysis of the different scenarios, presenting their respective contributions

When designing horizontal pathways, the ICT distribution designer should consider the design's ability to (Select two options.)

A.

handle only the day one needs as the future is unknown.

B.

minimize occupant disruption when horizontal pathways are accessed.

C.

handle at least 3 different cabling media types.

D.

accommodate cabling changes

E.

accommodate at least 50 percent future growth

A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project which could impact other components if delays occur. The program manager's attempts to reach the stakeholder via email also fail.

What should the program manager do next?

A.

Escalate the issue to the stakeholder's supervisor.

B.

Escalate the issue to the program governance board as delays will impact the program

C.

Update the program risk register to reflect a realized risk and execute the documented risk response

D.

Attempt to call the key stakeholder, if unsuccessful, visit their office to identify potential risks

An ICT distribution designer is preparing a price quote for a building design with multiple floors originally sized at 40.000 ft (3716 m2). While the designer is preparing the quote, the structural engineer indicates the building has been increased in size to accommodate an additional 40,000 ft2 (3716 m3) per floor. The designer's recommendation to the engineer will be to increase the slot area by_____for each additional 40,000 ft3 (3716 m2)

A.

0.006 m2 (8 in2)

B.

0.008 m2 (12 in2)

C.

0.040 m2 (60 in3)

D.

0.60 m2 (80 in3)

Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template while others prefer another

How should the program manager decide which template is appropriate?

A.

Review the issue with the program management office (PMO) to determine which template to use

B.

Review the issue with the project managers and come to mutual agreement on which template to use

C.

Meet with the program governance board to select an appropriate template

D.

Allow the component project managers to use their preferred templates

Exhibit:

A pay telephone using coins needs to be installed in a public area. In the specifications, it is required that the telephone shall meet the ADA (Americans with Disability Act) requirement for side reach using a wheelchair. What will be the maximum reachable height or the value of "X"?

A.

760 mm (30 in)

B.

864 mm (34 in)

C.

1170 mm (46 in)

D.

1220 mm (48 in)

E.

1370 mm (54 in)

What is the MAXIMUM number of work areas served by a single Multiuser Telecommunications Outlet Assembly (MUTOA)?

A.

5

B.

10

C.

12

D.

18

Which requirement does the ICT distribution designer provide to the Mechanical Engineer in charge of the HVAC design for a Telecommunication Space?

A.

The heat load (BTU (calories/hour) of all equipment installed within the space

B.

Location of the telecommunications own dedicated electrical distribution panel

C.

The quantity and size of HVAC vents needed for the room

D.

Location and size of condensate drain