BICSI RCDDv14.1 - BICSI Registered Communications Distribution Designer – RCDDv14.1
Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?
Exhibit:
In this future marina layout, assuming that there are fewer than 10 slips being cabled, what would be the pre-cabling guideline to follow for terminal A?
Smaller buildings with a serving area larger than 1000 ft2 and less than 5000 ft2 may be served by:
A program to implement a new payroll processing system at a healthcare company is nearing completion and is under budget. What should the program manager do next?
Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? {Select two options.)
For a cost estimate, an ICT distribution designer should produce a document listing each task with a cost placed beside them. The type of document used is a
In a PTP network using optical fiber, the ________ is responsible for media conversions from the optical fiber to the balanced twisted pair network within the residence.
The ICT distribution designer is hired to design a Telecommunications Room on the third floor of a building. The size of the floor is 20 m by 26 m (92 x 85 It). What is to be the MINIMUM size of the TR?
An IT-related program has a critical team in a region experiencing a crisis. Due to uncertainty about the region's changing environment a company's senior leadership asks the program manager to decrease dependencies on the critical team that should the program manager do to mitigate the Impacts of this request?
When sizing an underground entrance facility, what is the MINIMUM amount of 103 metric designator conduits (4 trade size) that should be specified by the ICT distribution design?