What is one anti-pattern of the Inspect and Adapt?

A.

Too many teams present Enablers and technical debt

B.

Product Managers lead the problem-solving workshop

C.

Product Owners present all of the work in the PI System Demo

D.

Not enough preparation goes into the quantitative and qualitative measurement section

According to SAFe, what is one output of a successful Iteration Retrospective?

A.

Updated ART metrics

B.

Iteration Goals

C.

Improvement Stories

D.

Updated dependencies between Stories

What is one trait of a servant leader?

A.

Persuades rather than using authority

B.

Deflects information that could change the team's work

C.

Determines the day-to-day activities for the team

D.

Solves problems on behalf of the team

What is one benefit of having an IP Iteration every PI?

A.

It provides dedicated time for innovation and continuing education

B.

It provides committed time for more team communication

C.

It provides time for teams to take vacation

D.

It provides focused time for teams to complete quality testing

What is one aspect of the Scrum Master/Team Coach role as it relates to PI Planning?

A.

Briefing the team before planning

B.

Participate in management review and problem-solving

C.

Facilitate Coach Sync

D.

Perform the ART confidence vote

What is one benefit of PI Planning?

A.

It maximizes team capacity

B.

It aligns the ART to established DevOps practices

C.

It fosters cross-team dependencies

D.

Allows for faster decision-making

What is the intended value of the Team Sync event?

A.

The team aligns on the progress of Iteration Goals

B.

The team is able to commit to a set of goals to be delivered in the Iteration

C.

The team is able to prepare requirements for Iteration Planning

D.

The team reviews and improves processes before the next Iteration

According to SAFe, what is one Iteration Retrospective anti-pattern?

A.

The team only shares issues that are too small to result in real improvement

B.

The team only shares issues that are too big to be solved

C.

The team only shares issues that cannot be measured

D.

The team only brings up issues that are outside of their control to address

What is one Scrum value that can help Agile Teams create transparency?

A.

Patience

B.

Openness

C.

Commitment

D.

Communication

According to SAFe, how many Stories should teams maintain in their backlog?

A.

2–3 weeks of refined Stories

B.

2–3 Iterations of refined Stories

C.

2–3 months of refined Stories

D.

2–3 PIs of refined Stories