You are a test manager in charge of integration, system, and acceptance testing for a bank. You are working on a project to upgrade an existing ATM to allow customers to obtain cash advances from supported credit cards. The system should allow cash advances from €20 to €500 (both inclusive) for all supported credit cards. The supported credit cards are American Express, VISA, Eurocard, and Mastercard. The system should be easy to use for all users, including new users.

In the master test plan, the following items are listed in the section named "items and/or features to be tested":

I. All supported credit cards

II. Language localisation

III. Valid and invalid advances

IV. Usability

Assume that the project has now been completed, and the ATM system has been in use for just over two months. You are planning a retrospective meeting for the testing work performed.

Which of the following areas is most likely to be considered in this retrospective?

A.

Operational defects occurred during the first two months of production

B.

Documenting the final and open defect list

C.

The requirements engineering process

D.

Comparing actual tests completed versus estimated number of tests

You are a test manager developing a master test plan. As part of the master test plan, you are defining exit criteria for the various test levels.

Which of the following exit criteria would be most appropriate and SMART for component testing, and which one would be most appropriate and SMART for system testing?

i. 95% of the tests prepared are executed successfully

ii. All test cases have been run

iii. 80% decision coverage for all tests run

iv. At least 30 defects have been found

v. At least two weeks of test execution

vi. No more open defects

A.

iii for component testing, v for system testing

B.

ii for component testing, iv for system testing

C.

iii for component testing, i for system testing

D.

v for component testing, vi for system testing

During a test process improvement initiative, defect information is gathered to perform defect cluster analysis.

Which aspect is most likely being targeted for improvement?

A.

To improve the defect removal efficiency.

B.

To reduce the total number of defects.

C.

To better understand risk and focus testing, as part of risk-based testing.

D.

To minimise the costs associated with defects.

Which of the following factors influences the risk impact?

A.

Complexity of technology being used

B.

Frequency of use of the affected feature

C.

Maturity of the development organisation

D.

Geographically distributed teams

Which of the following tools help to understand which part of the test object has been exercised by testing?

A.

Requirements management tool

B.

Test execution tool

C.

Static analysis tool

D.

Code coverage tool