What task do you use to view and modify allowed worktags?

A.

Maintain Worktag Usage

B.

Maintain Custom Validations

C.

Maintain Spend Categories

D.

Maintain Related Worktag Usage

When should you close purchase order (PO) lines in Workday?

A.

After the supplier invoice has been paid in full

B.

When all goods on the line are received and invoiced

C.

After the purchase order is approved

D.

At the end of the fiscal year

Refer to the following scenario to answer the question.

You are ready to load a list of procurement items into your system. You will need to report on the items in various capacities for different uses. You must identify all items as Office Supplies. It is possible that you will need to categorize an item to additional uses, such as General Use or Promotional.

What must you set up to fulfill the required association of Office Supplies?

A.

A spend category named Office Supplies

B.

A purchase group named Office Supplies

C.

An item tag named Office Supplies

D.

An alternate item identifier named Office Supplies

What type of procurement do you use to track spend for physical items?

A.

Project-based Services

B.

Goods

C.

Matching

D.

Service

Refer to the following scenario to answer the question below.

You are setting up Workday Procure to Pay and need to manage procurement items. You must ensure that when a requisition or purchase order is created, the system will track the manufacturer part number as well as prioritize suppliers. You need to allow the addition of the manufacturer part number to the procurement item.

How will you do so?

A.

Set up Alternate Item Identifiers on the spend category.

B.

Set up Alternate Item Identifiers on suppliers.

C.

Set up Alternate Item Identifiers on supplier contracts.

D.

Set up Alternate Item Identifiers on purchase items.

You are a supplier contract specialist. One of your approved supplier contracts lists an incorrect contract amount.

How can you correct the amount on the contract?

A.

Change the catalog associated with the contract.

B.

Add an attachment listing the correct amount.

C.

Create an invoice to replace the contract.

D.

Create an amendment with the corrected amount.