Cisco 350-801 - Implementing Cisco Collaboration Core Technologies (350-801 CLCOR) v2.0
Which two steps should be taken to provision a phone after the Self-Provisioning feature was configured for end users? (Choose two.)
Refer to the exhibit.

An engineer must deploy a Cisco Unified Border Element that will allow the last four digits of a dialed number to be sent from the Cisco Unified Border Element to Cisco UCM. The configuration in the exhibit already exists on the Cisco Unified Border Element. Which additional configuration must be performed on the Cisco Unified Border Element?
A)

B)

C)

D)

An administrator is in the process of moving Cisco Unity Connection mailboxes between mailbox stores. The administrator notices that some mailboxes have active Message Waiting Indicators. What happens to these mailboxes when they are moved?
Which DSCP value must be selected to mark video traffic between two Cisco 8845 phones?
An administrator troubleshoots call flows and suspects that there are issues with the dial plan. Which tool enables a quick analysis of the dial plan and provides call flows of dialled digits?
What is the traffic classification for voice and video conferencing?
A company hosts a conference call with no local users. How does the administrator stop the conference from continuing?
Refer to the exhibit. An engineer is confining class of control for a user in Cisco UCM. Which change will ensure that the user is unable to call 2143?
What are two features of Cisco Expressway that the customer gets if Expressway-C and Expressway-E are deployed?(Choose two.)
-
Guidelines
-
This is a lab item in which tasks will be performed on virtual devices.
• Refer to the Tasks tab to view the tasks for this lab item.
• Refer to the Topology tab to access the device console(s) and perform the tasks.
• Console access is available for all required devices by clicking the device icon or using the tab(s) above the console window.
• All necessary preconfigurations have been applied.
• Do not change the enable password or hostname for any device.
• Save your configurations to NVRAM before moving to the next item.
• Click Next at the bottom of the screen to submit this lab and move to the next question.
• When Next is clicked, the lab closes and cannot be reopened.
Topology

Tasks
-
The operations team started configuring network devices for a new site.
Complete the configurations to achieve these goals:
1. Ensure that port channel Po1 between DISTRO-SW01 and DISTRO-SW02 is operational using the LACP protocol. Configuration changes for this task must be made on DISTRO-SW01.
2. Ensure that traffic on VLAN 10 is carried as untagged traffic between DISTRO-SW01 and DISTRO-SW02.
3. Complete the Rapid-PVST+ configuration on DISTRO-SW2 by ensuring it it the secondary root switch for all VLANs in the range of 1 to 1005.
DISTRO-SW01



DISTRO-SW02
-