A circuit breaker is defined as:

A.

a one-shot device that causes the current carrying element to melt open, disconnecting the load from the source voltage.

B.

a type of device used to provide voltage protection.

C.

a means of energizing and de-energizing an electrical circuit.

D.

one or more enclosed vertical sections containing voltage.

According to NEMA ICS 2, a provision for pad locking shall be provided:

A.

on the door to prevent opening the combination starter door.

B.

on the external operating handle.

C.

on the wireway to prevent opening the wireway on the motor control center.

D.

on the rear door of the low voltage motor control center.

What is an insulation resistance test?

A.

A test that determines the adequacy of electrical insulation for the normally occurring over voltage transient

B.

A test that determines the corrosive contaminants around the conductors, terminal spacing problems, and tolerance errors in cables

C.

A spot overvoltage test which uses an applied DC voltage to measure ohms

D.

A test that determines the voltage that electrical insulation can withstand during normal operation

A qualified person, as defined by NFPA 70E, is a person:

A.

designated by the authority having jurisdiction as an electrician, electrical technician, electrical supervisor or electrical engineer.

B.

who has taken the national electrical safety certification and received the certificate.

C.

with a 2 year associate degree in electrical technology or electrical engineer or the IBEW equivalent.

D.

who has demonstrated skills related to the operation of electrical equipment and received safety training to identify and avoid the hazards.

Who should the Source Inspector notify if they believe that product quality may be compromised by schedule pressures?

A.

Master Scheduler

B.

The inspection coordinator

C.

The shop QA Manager

D.

Project Manager

Which of the following is primarily concerned with providing confidence that quality requirements will be fulfilled rather than detection and curing of problems?

A.

Inspection

B.

Quality control

C.

Quality planning

D.

Quality assurance

According to ANSI C57.12, the tank pressure under rated conditions of sealed transformers shall not exceed what value?

A.

One atmosphere

B.

Two atmospheres

C.

Three atmospheres

D.

Four atmospheres

According to the guide definitions, a junction box used within a control building or instrument enclosure may also be referred to as an:

A.

interface box

B.

breaker cubicle

C.

bus duct

D.

starter cell

Metallic shielding components such as tapes, wires, or braids shall be connected to a:

A.

equipment grounding busbar.

B.

low voltage ceramic insulator.

C.

low voltage connector.

D.

center tap of a transformer.

Actual dimensions verified during a source inspection should be recorded in the:

A.

redline drawing.

B.

reference drawing.

C.

shop traveler.

D.

status report.