The main purpose of configuration management is to:

A.

minimise the impact of changes on the scope of the project.

B.

ensure that the final product meets the strategic needs of the business.

C.

provide control of the deliverables and avoid mistakes or misunderstandings.

D.

maximise the impact of agreed enhancements on the project deliverables.

What would be the effect if the resources required for a project's critical path activities were insufficient?

A.

It would reduce the project duration.

B.

It would extend the project duration.

C.

The quality of the deliverables would suffer.

D.

Resource smoothing should be applied to the critical path.