ISTQB ATM - Advanced Test Management Exam v 3.0 – ISTQB

Page: 1 / 2
Total 50 questions

Which of the following is required to apply an experience-based testing approach''

A.

Detailed requirements

B.

Usage models

C.

Tester knowledge of the system and its usage

D.

A full risk-assessment to support risk prioritization

You are working on a project that is having problems with regressions. Witheach release of software given to the test team. 50% of the defects found are actually regressions.To combat this you have decided to implement test automation.You have given your automation team the following goal

'Implement lest automation to automate 90% of the manual regression tests before the productrelease date.’’

Which of the following is likely an issue with this goal being defined as "SMART?

A.

it is not clear if this is achievable in the time allowed

B.

It is not specific on what needs to be done

C.

It is not relevant to the project objectives

D.

It is not measurable against the goals of the project

Which of the Mowing should be used to understand the context of testing within an organization?

A.

The organizational test strategy

B.

Stakeholder organization chart

C.

The schedule

D.

The budget

Your team has been given the following test objective Ensure that the users are happier with this version thanthey were with the last version?

What is wrong with the way this is defined?

A.

It is unlikely that just a version change will make users happier so this is not achievable

B.

It cannot be measured because happier' is subjective

C.

It does not define a timeframe

D.

It is not aligned with the organization's objectives

When Is the metric for the percentage of requirements coverage defined?

A.

Test planning

B.

Test monitoring

C.

Test execution

D.

Test completion

You have been looking at the actual vs expected defects in one high risk area of the software The actual is much higher than the expected value What should you do?

A.

Reassess the risk with a higher likelihood number

B.

Reassess the risk with a higher impact number

C.

Concentrate more testing in the area because the risk is clearly higher

D.

Concentrate less testing in the area because the defects are already found

You tend to be conservative in your project estimations because you know how many things can go wrong and extend the schedule. You manager is not happy with your estimates and thinks you are being too negative with your numbers and not trying hard enough Which estimation method should you use to provide your manager with a positive' number while still also providing the number you think is more realistic?

A.

Wideband defphi

B.

Planning poker

C.

Three-point estimation

D.

Extrapolation

There is a debate in your organization about who can close a defect report The developers think theyshould be able to reject and close defects without any further steps The testers are not happy with this approach as they are afraid the rejections may go undetected and the developers may close something without understanding the real problem

How can this problem be rectified7

A.

Only testers should be allowed to close defect reports

B.

Only management should be allowed to close defect reports

C.

No one should close a defect report until the release is completed and the product is successfully deployed to production

D.

Closure should only occur when a defect is fixed and tested

Your manager has decided thatyour team of manual testers should all become test automation engineers Your team is much stronger in analysis than In technical testing so youare concerned about their abilityto adapt.What tool capabilities could help with this transition?

A.

Low license costs

B.

Remote storage of the test automation scripts

C.

High usability with Al-assisted object capture

D.

Good reporting

You have been seeing a high number of rejections of defect reports The developers are complaining that they do not understand what the problem is. even though they have been supplied with screenshots. You have checked a number of the 'problem' defect reports and have not found any information that is missing. The descriptions are very detailed and include all the necessary information in a long descriptive paragraph.

What change should you recommend that should help with the developer s problems?

A.

instruct your team to make all defects high priority so the developers have more urgency behind making the fixes

B.

With the problem reports highlight all the information and then walk through it with the developers so they see it is all there

C.

In addition to attaching the screenshots to the defect report, ask the testers to also email them to the developer

D.

Separate out the steps to reproduce the defect in the description so it is clearer for the developers and easier to find