PMI CAPM - Certified Associate in Project Management (CAPM)
Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:
An input required in Define Scope is an organizational:
What name(s) is (are) associated with the Plan-Do-Check-Act cycle?
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
Plan Risk Management is the process of defining how to:
What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?
Organizations perceive risks as:
During a project's execution phase, the project manager reviews the communications management plan for communication technology factors. What can affect the choice of communications?
During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.
What should the project manager do?
A project manager is calculating the current budget. The earned value (EV) of the project is lower than the actual cost (AC) of the project. How should the project manager report the status of the project?
What is main purpose of Project Quantity Management?
Which tool should a project manager use to calculate cost variance for a project?
A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?
An adaptive project team is meeting for the first time and deciding on the project management approach. After defining the project artifacts, one team member argues that the events are missing. The scrum master coaches the team to complete the planning.
Which two of the following elements should be included? (Choose two)
At what stages of project should the identify Stakeholder process be performed?
Which component of the project management plan should be updated if a change occurs?
Which project management process is used by the project manager to ensure that stakeholders receive timely and relevant information?
What is the recommended approach for handling risk in a high-variability environment?
What tern describes an intentional activity to modify a nonconforming product or product component?
The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?
What should be the frequency for meetings when transitioning from Scrum to Kanban?
A project is at risk of delivering the solution late because of poor quality that prevents the user acceptance testing (UAT) from being finalized. The product owner does not want to sign off until all the Severity 1 (S1) defects are fixed. What should the project manager do to manage this risk?
Which sentence summarizes the salience model?
A company is moving from a predictive to an adaptive approach. How should the company now translate the already planned work breakdown structure (WBS) to adaptive iterations?
In agile projects while performing scope management. What is the definition of requirements
Which tools and techniques should a project manager use to monitor risks?
A project manager has reached an agreement on the requirements and now needs to define the workflow for the end user. A critical step must be completed and validated by the end user before proceeding.
Which modeling tool best describes this process?
Following a project planning meeting with the team, a few team members approach the project manager to follow up on actions required. How can the project manager assess the effectiveness of the meeting?
Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?
The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should plan the project manager consult?
Which is a method of prototyping that creates a functioning representation of the final finished product to the user?
What does leadership involve?
What is the Project Schedule Management practice used to deliver incremental value to the customer'?
In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.
Which of the following elements is the team using?
Which behavior relates to team leadership'?
After defining activities in project schedule management, which processes should a project manager follow?
An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float. What is the likelihood the team will complete all 20 story points in the upcoming sprint?
Match the life cycle type to when its requirements are defined.
An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float.
What is the likelihood the team will complete all 20 story points in the upcoming sprint?
During a sprint demo, the customer says that one of the user stories is not ready for customer use. Which checklist should the team look at to find out what has been missed for the user story?
A team member, who is close to an influential stakeholder, has joined the project team. The stakeholder is routing requests for multiple reports through the new team member, and the team member reaches out to the project manager regarding this. What should the project manager do first?
Project managers plan a key role performing integration on the project what are the three different levels of integration?
What purpose does the hierarchical focus of stakeholder communications serve?
What key component of the project charter defines the conditions for dosing a project phase?
Perform Quantitative Analysis focuses on:
The project manager is new to the company in order to effectively manage the project, which components of the organizational governance framework does the project manager need to take into account?
Leadership and management are often used interchangeably. Which of the following is leadership more involved in?
What organizational process asset (OPA) can impact a project?
A product owner reviews the list of stakeholders to confirm their continued involvement with the product team. A new stakeholder is identified as actively involved in the next product release.
What should the project manager do next to engage the new stakeholder?
Which are required to create the schedule management plan?