Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI CAPM - Certified Associate in Project Management (CAPM)

Page: 2 / 8
Total 1320 questions

Plan Schedule Management is a process in which Knowledge Area?

A.

Project Scope Management

B.

Project Human Resource Management

C.

Project Integration Management

D.

Project Time Management

Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project ' s:

A.

Level of control.

B.

Communication channels.

C.

Scope.

D.

Strategic alignment.

Every project creates a unique product, service, or result that may be:

A.

tangible

B.

targeted

C.

organized

D.

variable

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

A.

Critical path method

B.

Critical chain method

C.

Resource leveling

D.

Schedule network analysis

A project team identifies defects that will require a modification to a tool ' s functionality. What process should the project manager follow to obtain stakeholder buy-in?

A.

Control Schedule

B.

Perform Qualitative Risk Analysis

C.

Perform Integrated Change Control

D.

Control Scope

Which is the correct hierarchy in a project environment, from most to least Inclusive?

A.

Projects, portfolios, then programs

B.

Portfolios, programs, then projects

C.

Portfolios, projects, then programs

D.

Projects, programs, then portfolios

What tool or technique will establish expected behaviors for project team members?

A.

Ground rules

B.

Decision mating

C.

Power/influence grid

D.

Stakeholder engagement assessment matrix

Which document in the project management plan can be updated in the Plan Procurement Management process?

A.

Budget estimates

B.

Risk matrix

C.

Requirements documentation

D.

Procurement documents

An organization that is being interviewed online has recently experienced a severe network outage. Consequently, the organization has stated that it is required to have a working data network.

Which classification should be assigned to data network requirements?

A.

Customer requirement

B.

Transition requirement

C.

Solution requirement

D.

Business requirement

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

A.

Diversity background

B.

Stakeholder ' s relationships

C.

Technical expertise

D.

Knowledge management

A procurement management plan is a subsidiary of which other type of plan?

A.

Resource plan

B.

Project management plan

C.

Cost control plan

D.

Expected monetary value plan

Sensitivity analysis is typically displayed as a/an:

A.

Decision tree diagram.

B.

Tornado diagram.

C.

Pareto diagram.

D.

Ishikawa diagram.

Which of the following is an example of facit knowledge?

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

Which three processes are generally included in risk management? (Choose three)

A.

Monitor Risk Costs

B.

Identify Risks

C.

Plan Risk Responses

D.

Perform Qualitative Risk Analysis

E.

Estimate Risk Activity Resources

What process in Project Risk Management prioritizes project risks?

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Responses

D.

Implement Risk Responses

To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

A.

scope creep.

B.

a change request.

C.

work performance information.

D.

deliverables.

In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process ' ?

A.

Assumption log

B.

Milestone list

C.

Business case

D.

Risk register

A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?

A.

Discussing with management

B.

Escalating to the sponsors

C.

Engaging regularly with stakeholders

D.

Engaging only with decision makers

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

A.

Work breakdown structure

B.

Requirements document

C.

Project charter

D.

Project management plan

Recently, the government published a new tax law giving companies one year to implement the changes. A project was initiated to change the accounting system. Which delivery approach is most suitable in this context?

A.

Predictive, because of the high risk that the company can be fined.

B.

Predictive, because the requirements are clearly defined up-front.

C.

Adaptive, because the government will provide constant feedback.

D.

Adaptive, because the changes have never been implemented before.

Which process determines the correctness of deliverables?

A.

Verify Deliverables

B.

Validate Deliverables

C.

Review Deliverables

D.

Analyze Deliverables

Which of the following types of a dependency determination is used to define the sequence of activities?

A.

Legal

B.

Discretionary

C.

Internal

D.

Resource

How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?

A.

Look at the quality metrics.

B.

Validate the scope.

C.

Review the quality checklist.

D.

Conduct a quality audit.

What is the equation to calculate cost variance (CV)?

A.

CV = EV / BAC

B.

CV = EV - AC

C.

CV = EV - BAC

D.

CV = EV / AC

Which of the following factors is lowest at the start of the project?

A.

Cost of changes

B.

Stakeholder influences

C.

Risk

D.

Uncertainty

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

A.

Resource breakdown structure

B.

Staffing management plan

C.

Project organizational chart

D.

Scope management plan

How is the schedule variance calculated using the earned value technique?

A.

EV less AC

B.

AC less PV

C.

EV less PV

D.

AC less EV

During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?

A.

Add this risk to the lessons learned register on project completion.

B.

Add the stakeholder to the stakeholder register and add the risk to the risk register.

C.

Make sure proper testing gets completed to minimize the risk highlighted.

D.

Ignore the risk from this stakeholder as this stakeholder never showed up at the start of the project.

Progressively elaborating high-level information into detailed plans is performed by the:

A.

project management office

B.

portfolio manager

C.

program manager

D.

project manager

Which of the following tools or techniques is used for Estimate Activity Durations?

A.

Critical path method

B.

Rolling wave planning

C.

Precedence diagramming method

D.

Parametric estimating

The primary purpose of the stakeholder register is to:

A.

Record stakeholder issues on the project

B.

Maintain lessons learned earlier in the project

C.

Maintain a list of all project stakeholders

D.

Document change requests and their status

The staffing management plan is part of the:

A.

organizational process assets.

B.

resource calendar.

C.

human resource plan.

D.

Develop Project Team process.

A project ' s business analyst has to understand the newly acquired technology and the impact it will have on the organization. Which tool should be used to understand the new technology?

A.

Must have, should have, could have, won ' t have (MoSCoW)

B.

Strengths, weaknesses, opportunities, threats (SWOT)

C.

Work breakdown structure (WBS)

D.

Responsible, accountable, consulted, informed (RACI)

Which procurement management process includes obtaining seller response, seller selection, and contract awarding?

A.

Plan Procurement

B.

Manage Procurement

C.

Conduct Procurements

D.

Perform Procurement

Which baselines make up the performance measurement baseline?

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

A project team is discussing an upcoming planned product launch of a highly visible technologically advanced artificial intelligence tool. The team is debating the aspect of iterative and hybrid approaches. Which aspect of tailoring would this best represent?

A.

Life cycle approaches

B.

Resource availability

C.

Project dimensions

D.

Technology support

The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

A.

US$158,700

B.

US$172,500

C.

US$187,500

D.

US$245,600

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

A.

Close Project or Phase

B.

Conduct Procurements

C.

Control Procurements

D.

Close Procurements

An output of the Develop Project Team process is:

A.

Organizational process assets.

B.

Enterprise environmental factors updates.

C.

Project staff assignments.

D.

Organizational charts and position descriptions.

An output of the Develop Project Team process is:

A.

change requests

B.

team performance assessments

C.

project staff assignments

D.

project documents updates

Which of the following project documents is an input to the Control Scope process?

A.

Vendor risk assessment diagram

B.

Risk register

C.

Requirements traceability matrix

D.

Area of responsibility summary

A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to evaluate the solution in the larger context to ensure it does not behave in unacceptable ways when deployed to production.

Which evaluation technique should be used here?

A.

Performance testing

B.

Integration testing

C.

Day-in-the-life testing

D.

Exploratory testing

Which of the following is a category of organizational process assets?

A.

Government standards

B.

Organizational culture

C.

Employee capabilities

D.

Organizational knowledge bases

Which tools and techniques should a project manager use when estimating costs?

A.

Lessons learned register and cost aggregation

B.

Project schedule and resources requirements

C.

Three-point estimating and risk register

D.

Expert judgempnt and decision making

Which document defines how a project is executed, monitored and controlled, and closed?

A.

Strategic plan

B.

Project charter

C.

Project management plan

D.

Service level agreement

In complex projects/ initiating processes should be completed:

A.

Within a work package.

B.

In each phase of the project.

C.

To estimate schedule constraints.

D.

To estimate resource allocations.

The following is a network diagram for a project.

What is the critical path for the project?

A.

A-B-D-G

B.

A-B-E-G

C.

A-C-F-G

D.

A-C-E-G

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

A.

What-if scenario analysis

B.

Simulation

C.

Alternatives analysis

D.

Reserve analysis

An adaptive project manager is handling a five-sprint cycle to deliver a minimum viable product (MVP). After the third sprint, the productivity of the team drops to 30% due to a change in the way the team operates.

Which of the following changes has caused this loss in productivity?

A.

Two of the team members have been working in silos using different methods to validate their performance.

B.

The team velocity was measured in the third sprint since the tool to measure velocity was introduced only in the third sprint.

C.

The team picked up technical debt items in the third sprint as technical debt can only be picked up after completing two sprints.

D.

Two of the team members were asked to do multitasking, which they did not do in the previous two sprints.