PMI CAPM - Certified Associate in Project Management (CAPM)

Page: 1 / 8
Total 1320 questions

Which process is engaged when a project team member makes a change to project budget with project manager ' s approval

A.

Manage Cost Plan

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Which is the main benefit of managing and tailoring strategies in the Stakeholder Engagement process?

A.

Increased support and minimized resistance from stakeholders

B.

Increased performance of the project team

C.

Maintenance of stakeholder satisfaction because costs and scope are under control

D.

Updated project documents, as requested by stakeholders

Which output is the approved version of the time-phased project budget?

A.

Resource calendar

B.

Scope baseline

C.

Trend analysis

D.

Cost baseline

Which tool or technique is an examination of industry and specific vendor capabilities?

A.

Independent estimates

B.

Market research

C.

Analytical techniques

D.

Bidder conferences

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Which item is a cost of conformance?

A.

Training

B.

Liabilities

C.

Lost business

D.

Scrap

Which are the most important competencies required for a project manager?

A.

Leadership, bilingualism, experience, and technical Knowledge

B.

PMP certification, experience, technical Knowledge, and post-graduate education

C.

Leadership, strategic and business management, project management knowledge, and technical knowledge

D.

Communication skills, project management knowledge, PMP certification, and availability to travel

Which statement about identification and engagement of stakeholders during a project is correct?

A.

Project stakeholders should be Identified and engaged in every phase of the project to influence the success of the project directly.

B.

Project stakeholders should be identified and engaged once the prototype is completed to provide their feedback but refrain from making inputs during the project.

C.

Project stakeholders should be identified when the project chatter is being completed and engaged during requirements gathering.

D.

Project stakeholders should be identified and engaged during requirements elicitation but not during the Define Scope process.

Which process numerically analyzes the effect of identified risks on overall project objectives?

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Which element does a project charter contain?

A.

Management reserves

B.

Work breakdown structure

C.

Stakeholder list

D.

Stakeholder register

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

A.

Communications management plan

B.

Human resource plan

C.

Quality management plan

D.

Procurement management plan

During the execution of a predicted project, the need for a new product feature has been proposed by the customer. What should the project manager do next?

A.

Decline any request by the customer and continue the project as initially planned.

B.

Accept the customer ' s request and continue with elicitation of the new product features.

C.

Investigate the possibility of using the management reserve to pay for the extra hours the team will need to work.

D.

Investigate the effect that such an integration will have on the project plan and propose a change request.

The primary benefit of the Plan Schedule Management process is that it:

A.

provides guidance to identify time or schedule challenges within the project.

B.

tightly links processes to create a seamless project schedule.

C.

guides how the project schedule will be managed throughout the project.

D.

creates an overview of all activities broken down into manageable subsections.

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

A.

Text-oriented formal

B.

Resource management plan

C.

Organization chart

D.

Responsibility assignment matrix (RAM)

Which of the following is a tool and technique used to monitor risk?

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

Most experienced project managers know that:

A.

every project requires the use of all processes in the PMBOK® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

How is program success measured?

A.

By delivering the benefit of managing the program ' s projects in a coordinated manner

B.

By the quality, timeliness, cost-effectiveness, and customer satisfaction of the product or service

C.

By completing the right projects to achieve objectives rather than completing projects the right way

D.

By aggregating the successes of the individual projects in the program

Which Process Group and Knowledge Area include the Sequence Activities process?

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

In order to detect quality Issues earlier in the project life cycle, the project manager is using an agile/adaptive environment. What is the main difference between waterfall and agile/adaptive development approaches tor Project Quality Management?

A.

The frequency of the quality and review steps

B.

The number of deliverables

C.

The duration of each of the quality and review steps

D.

The tools used in the quality and review steps

Which tools or techniques will a project manager use for Develop Project Team?

A.

Negotiation

B.

Roles and responsibilities

C.

Recognition and rewards

D.

Prizing and promoting

A weighting system is a tool for which area of Conduct Procurements?

A.

Plan contracting

B.

Requesting seller responses

C.

Selecting seller ' s

D.

Planning purchase and acquisition

Which of the following answers includes an input, a technique, and an output of the Plan Stakeholders Engagement process?

A.

Project management plan, data gathering, and stakeholder engagement plan

B.

Business documents, meetings, and stakeholder register

C.

Organizational process assets, data gathering, and project document updates

D.

Project management plan, data analysis, and change requests

The project manager implemented the stakeholder engagement plan and realized that some uploads should be made. Which components of the project management plan should be modified?

A.

Project charter and stakeholder engagement plan

B.

Risk management plan and stakeholder engagement plan

C.

Communications management plan and stakeholder engagement plan

D.

Project charter and communications management plan

A business analyst is working on a project that follows an adaptive life cycle. Due to budgetary constraints, the sponsor asks the team to focus on critical requirements. What should the business analyst do?

A.

Prioritize requirements.

B.

Document requirements.

C.

Trace requirements.

D.

Validate requirements.

What is a tool or technique used in the Control Quality process?

A.

Attribute sampling

B.

Parametric estimating

C.

Statistical sampling

D.

Expert judgment

What is the function of a Project Management Office (PMO)?

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client ' s overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization ' s business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

A.

enterprise environmental factors.

B.

organizational process assets.

C.

project management plan,

D.

project funding requirements.

Which is an output from Distribute Information?

A.

Earned value analysis

B.

Trend analysis

C.

Project records

D.

Performance reviews

It’s time to perform code review on a software project that has over three million lines of code written. Which management tool should the project manager use?

A.

Pareto chart

B.

Regression analysis

C.

Statistical sampling

D.

Automated testing tools

What type of project structure is a hierarchically organized depiction of the resources by type?

A.

Organizational breakdown structure (OBS)

B.

Resource breakdown structure (RBS)

C.

Work breakdown structure (WBS)

D.

Project breakdown structure (PBS)

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

A.

ends.

B.

begins.

C.

delays.

D.

deviates.

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

A.

Business case

B.

Work breakdown structure

C.

Requirements documentation

D.

Risk register

An adaptive project manager is told that a new industry regulation will affect an upcoming deliverable. Where should this be recorded?

A.

Risk register

B.

Sprint board

C.

Sprint planning

D.

User story

The activity tailoring is necessary because:

A.

the members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide, this is required for all projects

B.

each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide

C.

the members of the project team need to understand the PMBOK Guide processes, which are applied to all projects

D.

each project is unique, and the project team must plain how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide

Which tool or technique is effective in a project in which the deliverable is not a service or result?

A.

Inspection

B.

Variance analysis

C.

Decomposition

D.

Product analysis

Cost baseline is an output of which of the following processes?

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Estimate Activity Resources

During a sprint demo, the customer says that one of the user stories is not ready for customer use. Which checklist should the team look at to find out what has been missed for the user story?

A.

Burndown chart

B.

Velocity chart

C.

Definition of ready (DoR)

D.

Definition of done (DoD)

What is a tailoring consideration in Project Integration Management?

A.

Validation and control

B.

Benefits

C.

Technology support

D.

Physical location

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

A.

Compromising

B.

Collaborating

C.

Smoothing

D.

Problem Solving

Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

A.

Portfolio

B.

Project

C.

Program

D.

Operations

Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?

A.

Post project artifacts in a transparent fashion and engage stakeholders on a regular basis.

B.

Make surveys among the stakeholders and meet with the team once a month.

C.

Create a social network and post news there.

D.

Create personalized emails for each stakeholder, asking for requests and reviewing objectives with them periodically.

A software project has completed the first iteration, and the testing manager noted that some features were not incorporated and would not approve the software. The business unit manager who will use the software is satisfied with the software and wants to start the rollout.

What should the project manager do?

A.

Escalate the issue to the project management office (PMO).

B.

Organize a meeting between the two managers.

C.

Ask the project team to resolve all of the open issues.

D.

Escalate to the sponsor to decide when to commence the rollout.

How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?

A.

Less time spent on defining scope early on

B.

More time spent on defining scope early on

C.

Less time spent on scope management process

D.

Project scope management is the same in all projects

Which of the following best correspond to the organizational process assets (OPAs) that affect the project?

A.

Policies and lessons learned from other projects

B.

Information technology software and employee capability

C.

Resource availability and employee capability

D.

Marketplace conditions and legal restrictions

During what project management process does the project team begin identifying risks?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to determine if the solution provides the functionality for typical usage by a stakeholder with in-depth business knowledge.

Which evaluation technique is most effective for this situation?

A.

Day-in-the-life testing

B.

Exploratory testing

C.

User acceptance testing

D.

Integration testing

What earned value (EV) measure indicates the cost efficiency of the work completed?

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

To-complete performance index (TCPI)

D.

Variance at completion (VAC)

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

A project team working on an automobile manufacturing project is detailing the parts needed for a car door design. The door is composed of several parts that have to be developed in sequence, as the frame is needed before other parts can be designed and built. What activity is the team involved in?

A.

Creating a work breakdown structure (WBS)

B.

Identifying risks and issues in the project

C.

Developing a stakeholder engagement plan

D.

Developing a communications management plan

Which subsidiary management plan.... during the project ilfe cycle?

Which Subsidiary management plan would a project manager create to manage Information dissemination during the project life cycle?

A.

Stakeholder Engagement Plan

B.

Quality Management Plan

C.

Communications Management Plan

D.

Scope Management Plan