PMI CAPM - Certified Associate in Project Management (CAPM)
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.
Which technique is the project manager using?
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
Which two processes should be used to influence costs in the early stages of a project?
A firm contracted an event management company to conduct the annual sales day event. The agreement states that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract Is this?
Which action should the project manager take after the team finishes executing the scope?
When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process.
When managing costs in an agile environment, what should a project manager consider?
What charts and (igures should project managers use during the Perform Quantitative Risk Analysis process?
In which type of organization does the project manager have the maximum influence
In an agile and adaptive project, which scope management entity invokes stakeholder engagement?
Which statement summarizes the role of the change control board?
A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.
Which type of life cycle would the project manager use in this case?
Which of the following is an example of an organizational system that is arranged based on the job being performed?
To which knowledge area does the Collect Requirements process belong?
Which tool should a project manager consider to deal with multiple sources of risk?
In which Project Cost Management process is work performance data included?
A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?
What is the best tool to calculate the critical path on a project?
A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?
What can increase the complexity of the Manage Stakeholder Engagement process?
What is the purpose of the project schedule management.
A project team is evaluating criteria to determine project viability. Which of these activities will provide insight into making a go/no-go decision to start the project?
A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.
What should the project manager do to address this issue?
What tool or technique is primarily used to plan risk responses'?
What can a requirements traceability matrix enable regardless of the project methodology being used?
A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?
A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure effective requirements elicitation. What should the business analyst do?
A software project has completed the first iteration, and the testing manager noted that some features were not incorporated and would not approve the software. The business unit manager who will use the software is satisfied with the software and wants to start the rollout.
What should the project manager do?
What is the equation to calculate cost variance (CV)?
A few project team members are having issues understanding the requirements as described. Which action should be taken to resolve this issue?
A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?
Calculate the Schedule Performance Index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.
Which are required to create the schedule management plan?
A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?
A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?
After an internal deliverable review session with the team, the project manager indicates some issues that need to be fixed before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and the required network. How would the project manager define extra costs?
In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.
Which of the following elements is the team using?
Which method should be used to elicit a cross-functional requirement?
A project is in the planning phase and ready for plan review and approval when a sponsor switch happens. What should the next course of action be?
During project execution, a key resource leaves the team for another job. What should the project manager do in this situation?
A project manager is performing a specific process and has..........is being referred to?
A project manager is performing a specific process and has a list of accepted deliverables One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables Which process is being referred to?
Which organizational process asset can make an impact on the outcome of a project?
In an adaptive project environment, which action helps the project manager ensure that the team is comfortable with changes?
Which of the following is a goal of the project charter?
What is an example of an emerging trend in procurement management?
Which statement describes the various purposes of project scheduling?
Which three of the following interpersonal skills does a project manager rely on when developing the project management plan? (Choose three)
An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?
Two members of the team are having a conflict..............or partially resolve the problem
Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.
Which technique should the project manager use?
Which is an example of an internal enterprise environmental factor?
