Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI CAPM - Certified Associate in Project Management (CAPM)

Page: 1 / 8
Total 1337 questions

Which of the following projects is a quality candidate for adaptive approaches?

A.

Installing new computers across offices

B.

Retrofitting an old building

C.

Upgrading an information system

D.

Designing a new suspension bridge

A risk that arises as a direct result of implementing a risk response is called a:

A.

contingent risk

B.

residual risk

C.

potential risk

D.

secondary risk

Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

A.

Histogram

B.

Quality audits

C.

Benchmarking

D.

Performance measurement analysis

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

A.

One

B.

Five

C.

Six

D.

Seven

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

A.

It represents how and when the project will deliver the products, services, and results defined in the project scope

B.

It creates a formal record of the project and shows the organizational commitment to the project

C.

It describes how the scope will be defined, developed, monitored, controlled and validated

D.

It provides the needs of a stakeholder or stakeholder group

Which baselines make up the performance measurement baseline?

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

A.

Compromising

B.

Collaborating

C.

Smoothing

D.

Problem Solving

What estimating technique is used when there is limited information?

A.

Analogous estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Three-point estimating

Documented identification of a flaw in a project component together with a recommendation is termed a:

A.

corrective action.

B.

preventive action.

C.

non-conformance report,

D.

defect repair.

Given the following information, what is the schedule variance (SV) for this project?

Early start date (ES): 16 weeks

Actual time: 12 weeks

Schedule performance index (SPI): 1.3

A.

5

B.

2

C.

3

D.

4

What type of change requires the submission of a change request?

A.

Changes in assigned resources

B.

Changes in a technical solution

C.

Changes in status reporting

D.

Changes in the project ' s scope

Labor, materials, equipment, and supplies are examples of:

A.

Resource attributes.

B.

Resource types.

C.

Resource categories.

D.

Resource breakdown structures (RBS).

The project manager and the project team are in the process of documenting procurement decisions. Which of the following will be the procurement strategy?

A.

Payment types, delivery methods, and procurement phases

B.

Procurement metrics, make-or-buy decisions, and procurement statement of work

C.

Vendor selection criteria, stakeholder roles and responsibilitys, and prequalified sellers

D.

Timetable procurement activities, product cost, and knowledge transfer schedule

Which of the following does a portfolio combine?

A.

Projects, programs, and operations

B.

Operations, strategies, and business continuity

C.

Projects, programs, and risks

D.

Projects, change management, and operations

A tool or technique in Perform Quality Control that a project manager would use is:

A.

quality audits.

B.

process analysis.

C.

benchmarking.

D.

inspection.

What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives ' ?

A.

Executing

B.

Planning

C.

Initiating

D.

Monitoring and Controlling

In an interactive communication model, how is the sender ensured that the message was understood by the receiver?

A.

The receiver decodes the message

B.

The receiver responds to the message with feedback.

C.

The receiver transmits the message

D.

The receiver acknowledges their receipt of the message

A new business analyst has joined the team in the middle of a project and the requirements traceability matrix has been updated. What should the business analyst do next?

A.

Review the project management plan.

B.

Share the requirements traceability matrix the same way it was shared previously.

C.

Consult the business analysis communications management plan.

D.

Ask the project manager to share the updated requirements traceability matrix at the next meeting.

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

A.

Project document updates

B.

Activity list

C.

Activity attributes

D.

Project calendars

Managing procurement relationships and monitoring contract performance are part of which process?

A.

Conduct Procurements

B.

Plan Procurements

C.

Administer Procurements

D.

Close Procurements

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

A.

Interactive

B.

Push

C.

Verbal

D.

Oral

An input to the Plan Stakeholder Management process is:

A.

The project charter.

B.

The stakeholder analysis.

C.

A communication management plan.

D.

A stakeholder register.

During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:

A.

Conduct Procurements.

B.

Close Procurements.

C.

Administer Procurements,

D.

Plan Procurements.

What are the formal and informal policies, procedures, and guidelines that could impact how the project ' s scope is managed?

A.

Organizational process assets

B.

Enterprise environmental factors

C.

Project management processes

D.

Project scope management plan

A project manager has recently been assigned a new agile project and needs to determine an appropriate leadership style. The project manager aims to empower the team members so they feel committed and motivated to deliver value.

Which leadership style should be used for this project?

A.

A servant leadership style

B.

A laissez-faire leadership style

C.

A collaborative leadership style

D.

A directive leadership style

Which of the following are outputs from the process of creating a work breakdown structure (WBS)?

A.

Project scope statement and accepted deliverables

B.

Scope baseline and project documents update

C.

Accepted deliverables and enterprise environmental factors

D.

Scope baseline and work performance information

When closing a project or phase, part of the process may require the use of which type of analysis?

A.

Reserve analysis

B.

Regression analysis

C.

Document analysis

D.

Product analysis

In a weak matrix, the project managers role is:

A.

part-time

B.

full-time

C.

occasional

D.

unlimited

What does earned value (EV) measure?

A.

Budgeted work that has been completed

B.

Total costs incurred while accomplishing work

C.

Budget associated with planned work

D.

Cost efficiency of budgeted resources

Which action should a project manager take to ensure that the project management plan is effective and current?

A.

Conduct periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards.

D.

Complete the quality control checklist.

Which of the following is a narrative description of products, services, or results to be delivered by a project?

A.

Project statement of work

B.

Business case

C.

Accepted deliverable

D.

Work performance information

Calculate the Schedule Performance Index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.

A.

2.0

B.

45

C.

0.5

D.

15

What is one of the main purposes of the project chatter?

A.

Formal authorization of the existence of the project

B.

Formal acceptance of the project management plan

C.

Formal approval of the detailed project budget

D.

Formal definition of stakeholder roles and responsibilities

Which item is an example of personnel assessment?

A.

Resource calendar

B.

Tight matrix

C.

Team-building activity

D.

Focus group

Which of the following is a strategy to deal with positive risks or opportunities?

A.

Mitigate

B.

Transfer

C.

Exploit

D.

Avoid

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

A.

Plan Procurement Management

B.

Control Procurements

C.

Collect Requirements

D.

Plan Cost Management

Select three processes that are associated with Project Schedule Management.

A.

Define Activities

B.

Plan Resource Management

C.

Estimate Activity Durations

D.

Develop Schedule

E.

Acquire Resources

Which of the following lists of tools and techniques is used when conducting procurements?

A.

Expert judgement, procurement negotiations, bidder conferences, proposal evaluation advertising and independent estimates

B.

Budgeting procurement negotiations, bidder conferences, proposal evaluation and advertising, and seller ' s proposal C. Expert judgement, procurement negotiations bidder conferences, proposal evaluation and advertising, and make-or-buy decisions

C.

Agreements procurement negotiations, bidder conferences, proposal evaluation and advertising selected seller

Which of the following is a tool or technique used in the Determine Budget process?

A.

Variance analysis

B.

Three-point estimating

C.

Bottom-up estimating

D.

Historical relationships

A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.

Which entities will the project manager attempt to influence?

A.

The project and the organization

B.

The organization and the industry

C.

The subject matter experts and the project

D.

The change control board and the organization

What process is included in Project Integration Management?

A.

Monitor and Control Project Work

B.

Control Scope

C.

Control Schedule

D.

Develop Team

A project team working on an automobile manufacturing project is detailing the parts needed for a car door design. The door is composed of several parts that have to be developed in sequence, as the frame is needed before other parts can be designed and built. What activity is the team involved in?

A.

Creating a work breakdown structure (WBS)

B.

Identifying risks and issues in the project

C.

Developing a stakeholder engagement plan

D.

Developing a communications management plan

How can a project manager evaluate project team development?

A.

Produce team performance assessments.

B.

Hold weekly meetings to engage every member

C.

Complete a personal skill assessment on each team member

D.

Provide recognition awards to team members

Which enterprise environmental factors should be considered when creating a new procurement contract?

A.

Supply chains

B.

Trial engagements

C.

Lessons learned register

D.

Local laws and regulalk

Outputs of the Control Communications process include:

A.

expert judgment and change requests.

B.

work performance information and change requests.

C.

organizational process asset updates and an issue log.

D.

project management plan updates and an issue log.

Which tools or techniques will a project manager use for Develop Project Team?

A.

Negotiation

B.

Roles and responsibilities

C.

Recognition and rewards

D.

Prizing and promoting

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

A.

Product scope description

B.

Procurement statement of work

C.

Project schedule

D.

Work breakdown structure (WBS)

A production support system is being managed by a team. The team members cannot plan their work in advance, even for a week, because they do not know when new support issues will be submitted. The team cannot start working on new issues until they finish existing issues, no matter how long it takes to finish the existing issues.

Which method should be used in this situation?

A.

SAFe®, as it does not allow for scaling work across different teams in the organization.

B.

Extreme Programming (XP), as it does not allow for moving on to new items until the existing items are finished.

C.

Kanban, because the team does not start new work until the existing work is finished.

D.

Scrum, as it allows for completing the whole architecture up front without leaving any technical debt for the future.