PMI CAPM - Certified Associate in Project Management (CAPM)
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?
The three processes of Project Cost Management are:
Inputs to the Plan Risk Management process include the:
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
A tool and technique used during the Collect Requirements process is:
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Which of the following is an output of Close Procurements?
What are the identified risks for doing excessive decomposition in a WBS?
Which of the following is an input to Direct and Manage Project Execution?
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
The cost benefit analysis tool is used for creating:
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
Which is an output of the Collect Requirements process?
Funding limit reconciliation is a tool and technique used in which process?
An input to the Estimate Activity Resources process is:
Which of the following is a tool and technique used to monitor risk?
The process for performing variance analysis may vary, depending on:
The initial development of a Project Scope Management plan uses which technique?
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
The total of the planned value (PV) is also known as:
Risk exists the moment that a project is:
The staffing management plan is part of the:
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
Risk responses reflect an organization's perceived balance between:
A tool and technique used during the Define Scope process is:
Which of the following is a group decision-making technique?
Which of the following is a strategy to deal with positive risks or opportunities?
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:
Which of the following is a project constraint?
Which activity may occur at project or phase closure?
The probability and impact matrix is primarily used to:
A large portion of a projects budget is typically expended on the processes in which Process Group?
Which document describes the necessary information to determine if a project is worth the required investment?
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
An input to the Plan Cost Management process is:
Which of the following includes how requirements activities will be planned, tracked, and reported?
Processes in the Planning Process Group are typically carried out during which part of the project life cycle?
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
Inputs to the Plan Schedule Management process include:
An input to Close Project or Phase is:
An input to the Manage Project Team process is:
The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:
In the Plan Stakeholder Management process, expert judgment is used to:
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
An input to Conduct Procurements is:
Which item is an input to the Define Activities process?
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
