What is the purpose of an adaptive standup meeting?

A.

To review what work has been completed, remove impediments, and calculate velocity

B.

To ask the team what work has been completed, calculate velocity, and determine what work will be completed

C.

To ask the team what work has been completed, ask what work will be completed, and report impediments

D.

To update the burndown chart, calculate velocity, and report impediments

A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical project manager working with a business program manager and the client's project manager. The technical lead is requesting two new developers.

Which plan should the project manager use to identify who is responsible for finding the budget for additional developers?

A.

Cost management plan

B.

Business management plan

C.

Stakeholder engagement plan

D.

Resource management plan

On which type of project.... only after the final iteration?

On wtiich type of project lite cycle is ihe deliverable produced trough a series of ileralrons considering thai the deliverable ts completed only after the Imal iteration?

A.

Incremental life cycle

B.

Predictive life cycle

C.

Iterative life cycle

D.

Adaptive life cycle

A project is in its final stages when a competitor releases a similar product. This could make the project redundant. What should the project manager do next?

A.

Initiate change control.

B.

Address risk mitigation.

C.

Escalate this to the project sponsor.

D.

Initiate project closure.

A project manager should consider the impact of project..............manager following

A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?

A.

Project Cost Management

B.

Project Integration Management

C.

Project Resources Management

D.

Project Scope Management

A project manager is working on the communications management plan. Which of these documents are inputs to consider?

A.

Stakeholder engagement plan and organizational process assets

B.

Project schedule and stakeholder register

C.

Quality management plan and risk register

D.

Basis of estimates and scope baseline

It’s time to perform code review on a software project that has over three million lines of code written. Which management tool should the project manager use?

A.

Pareto chart

B.

Regression analysis

C.

Statistical sampling

D.

Automated testing tools

Which scenario is most desirable during the execution phase of a project?

A.

Apply and use quality controls to ensure expectations are met throughout the project

B.

Communicate quality failures to the sponsor for feedback

C.

Conduct all quality inspections at the end of the project

D.

Only correct quality issues found if it will keep you within the budget

Which of the following projects is a quality candidate for adaptive approaches?

A.

Installing new computers across offices

B.

Retrofitting an old building

C.

Upgrading an information system

D.

Designing a new suspension bridge

A project receives budget approval, but the risk of extra costs is expected. Which of these inputs should the project manager check in order to make a qualitative risk analysis?

A.

The risk management plan and the assumption log

B.

Costs estimates and cost forecast

C.

The risk management plan and the basis of estimates

D.

The assumption log and the project charter

What three strategies are used to respond to threats?

A.

Escalate, accept, and mitigate

B.

Accept share, and avoid

C.

Escalate, transfer, and exploit

D.

Mitigate, accept, and prioritize

How can working in iterations increase the quality of the product being built?

A.

Teams have to do less planning and focus more on quality.

B.

The project manager has more time to document goals in advance.

C.

Less testing is required since it is done at the end of the project.

D.

Requirements are frequently clarified by users of the product.

A project manager was assigned to a project to implement a manufacturing system in a food factory. The main project objective is to deliver machines that are ready to process food. The project manager decides that this particular project does not require the use of timeboxed iterations.

Which method should the project manager adopt?

A.

SAFe®

B.

Kanban

C.

Feature-driven development (FDD)

D.

Scrum

A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?

A.

Escalate this issue to the project management office (PMO).

B.

Escalate this issue to the chief financial officer (CFO).

C.

Escalate this issue to the procurement team.

D.

Escalate this issue to the project sponsor.

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

A.

Scope baseline

B.

Organizational process assets

C.

Enterprise environmental factors

D.

Risk register

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

An input to Conduct Procurements is:

A.

Independent estimates.

B.

Selected sellers.

C.

Seller proposals.

D.

Resource calendars.

Which item is an example of personnel assessment?

A.

Resource calendar

B.

Tight matrix

C.

Team-building activity

D.

Focus group

Reserve analysis is a tool and technique used in which process?

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

A.

Direct

B.

Interactive

C.

Pull

D.

Push

An example of a group decision-ma king technique is:

A.

Nominal group technique.

B.

Majority.

C.

Affinity diagram.

D.

Multi-criteria decision analysis.

Which input to the Plan Risk Management process provides information on high-level risks?

A.

Project charter

B.

Enterprise environmental factors

C.

Stakeholder register

D.

Organizational process assets

Plan Schedule Management is a process in which Knowledge Area?

A.

Project Scope Management

B.

Project Human Resource Management

C.

Project Integration Management

D.

Project Time Management

The process of prioritizing risks for further analysis or action is known as:

A.

Plan Risk Management.

B.

Plan Risk Responses.

C.

Perform Qualitative Risk Analysis.

D.

Perform Quantitative Risk Analysis.

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

A.

Work packages.

B.

Accepted deliverables.

C.

The WBS dictionary.

D.

The scope baseline.

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

Which process involves developing an approximation of the monetary resources needed to complete project activities?

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

The ability to influence cost is greatest during which stages of the project?

A.

Early

B.

Middle

C.

Late

D.

Completion

Which tool or technique is used to manage change requests and the resulting decisions?

A.

Change control tools

B.

Expert judgment

C.

Delphi technique

D.

Change log

A project manager builds consensus and overcomes obstacles by employing which communication technique?

A.

Listening

B.

Facilitation

C.

Meeting management

D.

Presentation

Enterprise environmental factors are an input to which process?

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

Budget at completion (BAC)

D.

Variance at completion (VAC)

Which tool or technique is used to develop the human resource management plan?

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

A.

Expert judgment.

B.

Analytical techniques.

C.

Earned value management.

D.

Group decision-making techniques.

The Perform Integrated Change Control process occurs in which Process Group?

A.

Initiating

B.

Executing

C.

Monitoring and Controlling

D.

Planning

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

A.

Monitor and Control Project Work

B.

Perform Quality Assurance

C.

Close Project or Phase

D.

Control Scope

A temporary endeavor that creates a unique product or service is called a:

A.

Project

B.

Plan

C.

Program

D.

Portfolio

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

A.

Human resource management plan.

B.

Activity resource requirements.

C.

Personnel assessment tools,

D.

Multi-criteria decision analysis.

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

A.

Efficient

B.

Effective

C.

Push

D.

Pull

An output of the Manage Stakeholder Engagement process is:

A.

change requests

B.

enterprise environmental factors

C.

the stakeholder management plan

D.

the change log

An input to Develop Project Charter is a/an:

A.

Business case.

B.

Activity list.

C.

Project management plan.

D.

Cost forecast.

When does the project team determine which dependencies are discretionary?

A.

Before the Define Activities process

B.

During the Define Activities process

C.

Before the Sequence Activities process

D.

During the Sequence Activities process

An input to the Identify Stakeholders process is:

A.

The project management plan.

B.

The stakeholder register.

C.

Procurement documents.

D.

Stakeholder analysis.

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

A.

Stakeholder register

B.

Scope management plan

C.

Stakeholder management plan

D.

Project charter

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

A.

Organizational process updates

B.

Quality metrics

C.

Change requests

D.

Quality control measurements

In which Knowledge Area is the project charter developed?

A.

Project Cost Management

B.

Project Scope Management

C.

Project Time Management

D.

Project Integration Management

Which document describes the necessary information to determine if a project is worth the required investment?

A.

Cost baseline

B.

Service level agreement

C.

Memorandum of understanding

D.

Business case

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

A.

Timing

B.

Methodology

C.

Risk categories

D.

Budgeting

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Organizational theory is a tool used in which Project Human Resource Management process?

A.

Manage Project Team

B.

Acquire Project Team

C.

Develop Project Team

D.

Plan Human Resource Management