PMI CAPM - Certified Associate in Project Management (CAPM)
In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?
Specification of both the deliverables and the processes is the focus of:
Which tool or technique is required in order to determine the project budget?
Outputs of the Control Communications process include:
The following is a network diagram for a project.

The total float for the project is how many days?
Project Scope Management is primarily concerned with:
The process of obtaining seller responses, selecting a seller, and awarding a contract is called:
The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:
Progressively elaborating high-level information into detailed plans is performed by the:
The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?
Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?
High-level project risks are included in which document?
The following is a network diagram for a project.

What is the critical path for the project?
Which items are components of a project management plan?
Every project creates a unique product, service, or result that may be:
Tools and techniques used in Direct and Manage Project Work include:
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:
Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:
The zero duration of milestones in project planning occurs because milestones:
The degree, amount, or volume of risk that an organization or individual will withstand is called risk:
Which tools or techniques are used during the Close Project or Phase process?
Which stakeholder approves a project's result?
Completion of the product scope is measured against the product:
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?
Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?
The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:
The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?
What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?
The following is a network diagram for a project.

The free float for Activity H is how many days?
Which term describes an assessment of correctness?
Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:
Those who enter into a contractual agreement to provide services necessary for a project are:
The purpose of the Project Communications Management Knowledge Area is to:
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?
The component of the risk management plan that documents how risk activities will be recorded is called:
A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
An issue log is an input to which Project Human Resource Management process?
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:
A tool or technique used in the Control Procurements process is:
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?
Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?
When should quality planning be performed?
Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?