When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

A.

divided among each of the phases or subprojects.

B.

repeated for each of the phases or subprojects.

C.

linked to specific phases or subprojects.

D.

integrated for specific phases or subprojects.

Which conflict resolution technique produces the most lasting results?

A.

Withdraw/avoid

B.

Smooth/accommodate

C.

Compromise/reconcile

D.

Collaborate/problem solve

Which process involves identifying and documenting the logical relationships between project activities?

A.

Develop Schedule

B.

Sequence Activities

C.

Create WBS

D.

Applying leads and lags

One of the tools and techniques of the Manage Project Team process is:

A.

organization charts.

B.

ground rules.

C.

organizational theory,

D.

conflict management.

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

A.

Smooth/accommodate

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Force/direct

Which of the in an adaptive project environment, which action helps the project manager?

A.

Project charter and project management plan

B.

Communications management plan and scope management plan

C.

Quality management plan and risk management plan

D.

Project scope statement and communications management plan

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

Cash Flow Statement of the Project Investment Unit: US$ Billion

Period: 0, 1, 2, 3, 4, 5, 6, 7, 8

Cash inflow: 0, 0, 0, 0, 1200, 1200, 1200, 1200

Cash outflow: 0, 700, 800, 500, 700, 700, 700, 700, 700

Net cash flow (NCF): 0, -700, -800, 300, 500, 500, 500, 500, 500

Accumulative total of net cash flow: 0, -700, -1500, -1200, -700, -200, 300, 800, 1300

A.

Static payback period = 3 + |-1200| / 500 = 5.4

B.

Static payback period = 6 + |300| / 500 = 6.6

C.

Static payback period = 5 + |-200| / 500 = 5.4

D.

Static payback period = 4 + |-700| / 500 = 5.4

Success is measured by benefits realization for a:

A.

strategic plan

B.

project

C.

portfolio

D.

program

A project manager is leading a technology project that is about to enter the execution phase. The project requires the procurement of certain key components from an external vendor. The project manager has been notified that because of a government regulation, some parts can no longer be used in the country and the vendor will be unable to deliver them.

What should the project manager do?

A.

Identify the impact and follow the procurement plan.

B.

Identify the impact and follow the project management plan.

C.

Identify the impact and follow the risk management plan.

D.

Identify the impact and follow the change control plan.

A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members know their roles and responsibilities. What are the four elements of a RACI chart?

A.

Recommend, accountable, consult, and inform

B.

Responsible, accountable, consult, and inform

C.

Recommend, approve, coordinate, and inform

D.

Responsible, accountable, coordinate, and inform

Which tools or techniques are used in the Plan Schedule Management process?

A.

Benchmarking, expert judgment, and analytical techniques

B.

Statistical sampling, benchmarking, and meetings

C.

Negotiations, pre-assignment, and multi-criteria decision analysis

D.

Expert judgment, analytical techniques, and meetings

Stakeholder communication requirements should be included as a component of:

A.

enterprise environmental factors

B.

organizational process assets

C.

the project management plan

D.

the stakeholder register

Select three elements that apply to agile/ adaptive environments

A.

Frequent team checkpoints

B.

Colocation

C.

Access to information

D.

Virtual team members

E.

Geographically dispersed team

What characteristic of servant leadership supports resource management in an agile environment?

A.

Lecturing

B.

Construing

C.

Measuring

D.

Coaching

What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives ' ?

A.

Executing

B.

Planning

C.

Initiating

D.

Monitoring and Controlling

A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical project manager working with a business program manager and the client ' s project manager. The technical lead is requesting two new developers.

Which plan should the project manager use to identify who is responsible for finding the budget for additional developers?

A.

Cost management plan

B.

Business management plan

C.

Stakeholder engagement plan

D.

Resource management plan

A project is at the closing stage. The project manager asks the team to perform closing functions at the next meeting. Which two procedures will the project team perform? (Choose two)

A.

Project audit

B.

Deliverable acceptance

C.

Risk register tracking

D.

Stakeholder mapping

E.

Issue log update

A project team is meeting to seek solutions on a new problem that occurred recently. The meeting is comprised of two parts: the first is a generation of ideas and the second is an analysis.

Which technique is the team using?

A.

Checklists

B.

Interview

C.

Focus group

D.

Brainstorming

Risk categorization is a tool or technique used in which process?

A.

Plan Risk Responses

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

For a 10-day project, activity B ' s duration is three days, and activity C’s duration is two days What is the duration of activity A if activities B and C are performed in parallel?

A.

3 days

B.

5 days

C.

7 daysD .10 days

Specification of both the deliverables and the processes is the focus of:

A.

Change control

B.

Configuration control

C.

Project monitoring and control

D.

Issue control

A project charter is an output of which Process Group?

A.

Executing

B.

Planning

C.

Initiating

D.

Closing

What process in Project Schedule Management identifies and documents specific actions to be performed to produce a project’s deliverables?

A.

Plan Schedule Management

B.

Define Activities

C.

Develop Schedule

D.

Estimate Activity Durations

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

A.

$50

B.

$100

C.

$125

D.

$175

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

A.

Static payback period = 6 + 1300 / 500 = 6.6

B.

Static payback period = 3 + 1200 / 500 = 5.4

C.

Static payback period = 5 + 700 / 500 = 5.4

D.

Static payback period = 5 + 200 / 500 = 5.4

The process to ensure that appropriate quality standards and operational definitions are used is:

A.

Plan Quality.

B.

Perform Quality Assurance.

C.

Perform Quality Control.

D.

Total Quality Management.

The product scope description is used to:

A.

Gain stakeholders ' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

Which of the following is an output of the Define Activities process?

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

A production support system is being managed by a team. The team members cannot plan their work in advance, even for a week, because they do not know when new support issues will be submitted. The team cannot start working on new issues until they finish existing issues, no matter how long it takes to finish the existing issues.

Which method should be used in this situation?

A.

SAFe®, as it does not allow for scaling work across different teams in the organization.

B.

Extreme Programming (XP), as it does not allow for moving on to new items until the existing items are finished.

C.

Kanban, because the team does not start new work until the existing work is finished.

D.

Scrum, as it allows for completing the whole architecture up front without leaving any technical debt for the future.

The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

A.

Close Procurements.

B.

Control Procurements.

C.

Plan Procurements.

D.

Conduct Procurements.

Recognition and rewards are tools and techniques of which process?

A.

Develop Team

B.

Manage Team

C.

Control Resources

D.

Plan Resource Management

Which is the tool or technique that is used to obtain the list of activities from the work packages?

A.

Data analysis

B.

Leads and lags

C.

Precedence diagramming method

D.

Decomposition

What is the difference between verified and accepted deliverables?

A.

Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.

B.

Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.

C.

Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.

D.

Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process.

Which type of managers do composite organizations involve?

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

Match the project life cycle type with its corresponding definition.

The precedence diagramming method (PDM) is also known as:

A.

Arrow Diagram.

B.

Critical Path Methodology (CPM).

C.

Activity-On-Node (AON).

D.

schedule network diagram.

Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?

A.

A self-organizing approach to increase team focus and maximize collaboration

B.

A virtual team to minimize feeling of isolation and gaps on sharing knowledge

C.

A distributed team to improve tracking progress, productivity, and performance

D.

A norming approach that requires team members to adjust their behavior and work together

In which domain of project management would a Pareto chart provide useful information?

A.

Project Scope Management

B.

Project Time Management

C.

Project Communications Management

D.

Project Quality Management

Reserve analysis is a tool and technique used in which process?

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

When executing a project, a recently hired subject matter expert (SME) who reviewed the execution progress remarked that the schedule could be crashed and that the schedule was not assessed properly. What should the project manager do next?

A.

Update the schedule baseline

B.

Review the schedule baseline

C.

Initiate a change request

D.

Update the risk register

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Due to organizational changes, a new product owner joins a project The product owner wants to review the process used to obtain team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.

What process should the project manager review with the product owner?

A.

Acquire Resources

B.

Plan Resource Management

C.

Estimate Activity Resources

D.

Control Resources

A project manager should communicate to stakeholders about resolved project issues by updating the:

A.

project records

B.

project reports

C.

stakeholder notifications

D.

stakeholder register

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three)

A.

High-level deliverables

B.

Phase transitions

C.

Project objectives

D.

Success criteria

E.

Cost

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

A.

Force/direct

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Collaborate/problem solve

A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project. Which approach should the project manager select for the project?

A.

Predictive

B.

Hybrid

C.

Kanban

D.

Adaptive

Which process involves developing an approximation of the monetary resources needed to complete project activities?

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take to account for risk management n this environment’

A.

Occasionally identify evaluate, and classify risks

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Which activity is an input to the Conduct Procurements process?

A.

Organizational process assets

B.

Resource availability

C.

Perform Integrated Change Control

D.

Team performance assessment

During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three)

A.

End user

B.

Product owner

C.

Subject matter experts (SMEs)

D.

Project sponsor

E.

Project team