PMI CAPM - Certified Associate in Project Management (CAPM)

Page: 3 / 8
Total 1305 questions

In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

A.

Technical approach

B.

Technical capability

C.

Business size and type

D.

Production capacity and interest

Specification of both the deliverables and the processes is the focus of:

A.

Change control

B.

Configuration control

C.

Project monitoring and control

D.

Issue control

Which tool or technique is required in order to determine the project budget?

A.

Cost of quality

B.

Historical relationships

C.

Project management software

D.

Forecasting

Outputs of the Control Communications process include:

A.

expert judgment and change requests.

B.

work performance information and change requests.

C.

organizational process asset updates and an issue log.

D.

project management plan updates and an issue log.

The following is a network diagram for a project.

The total float for the project is how many days?

A.

3

B.

5

C.

7

D.

9

Project Scope Management is primarily concerned with:

A.

Developing a detailed description of the project and product.

B.

Determining how requirements will be analyzed, documented, and managed.

C.

Defining and controlling what is and is not included in the project.

D.

Formalizing acceptance of the completed project deliverables.

The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

A.

Close Procurements.

B.

Control Procurements.

C.

Plan Procurements.

D.

Conduct Procurements.

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

A.

exploit

B.

avoid

C.

mitigate

D.

share

Progressively elaborating high-level information into detailed plans is performed by the:

A.

project management office

B.

portfolio manager

C.

program manager

D.

project manager

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?

A.

0.83

B.

0.9

C.

1.11

D.

1.33

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

A.

Influencing

B.

Motivation

C.

Negotiation

D.

Trust building

High-level project risks are included in which document?

A.

Business case

B.

Risk breakdown structure

C.

Project charter

D.

Risk register

The following is a network diagram for a project.

What is the critical path for the project?

A.

A-B-D-G

B.

A-B-E-G

C.

A-C-F-G

D.

A-C-E-G

Which items are components of a project management plan?

A.

Change management plan, process improvement plan, and scope management plan

B.

Agreements, procurement management plan, and work performance information

C.

Schedule management plan, project schedule, and resource calendars

D.

Scope baseline, project statement of work, and requirements traceability matrix

Every project creates a unique product, service, or result that may be:

A.

tangible

B.

targeted

C.

organized

D.

variable

Tools and techniques used in Direct and Manage Project Work include:

A.

Process analysis and expert judgment

B.

Analytical techniques and a project management information system

C.

Performance reviews and meetings

D.

Expert judgment and meetings

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

A.

management

B.

response

C.

tolerance

D.

appetite

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

A.

Verified deliverables.

B.

Validated deliverables.

C.

Acceptance criteria.

D.

Activity resource requirements.

The zero duration of milestones in project planning occurs because milestones:

A.

Are unpredictable and challenge the Plan Schedule Management process.

B.

Occur at random times in the project plans.

C.

Represent a moment in time such as a significant project point or event.

D.

Represent both significant and insignificant points in the project and are difficult to anticipate.

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

A.

appetite

B.

tolerance

C.

threshold

D.

management

Which tools or techniques are used during the Close Project or Phase process?

A.

Reserve analysis and expert judgment

B.

Facilitation techniques and meetings

C.

Expert judgment and analytical techniques

D.

Performance reviews and meetings

Which stakeholder approves a project's result?

A.

Customer

B.

Sponsor

C.

Seller

D.

Functional manager

Completion of the product scope is measured against the product:

A.

prototypes

B.

requirements

C.

analyses

D.

benchmarks

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

A.

Smooth/accommodate

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Force/direct

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?

A.

0.8

B.

1

C.

1.25

D.

1.8

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

A.

0.03

B.

0.06

C.

0.10

D.

0.50

The following is a network diagram for a project.

The free float for Activity H is how many days?

A.

4

B.

5

C.

10

D.

11

Which term describes an assessment of correctness?

A.

Accuracy

B.

Precision

C.

Grade

D.

Quality

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

A.

portfolio

B.

program

C.

selection

D.

sub portfolio

Those who enter into a contractual agreement to provide services necessary for a project are:

A.

buyers

B.

sellers

C.

business partners

D.

product users

The purpose of the Project Communications Management Knowledge Area is to:

A.

Monitor and control communications throughout the entire project life cycle.

B.

Maintain an optimal flow of information among all project participants.

C.

Develop an appropriate approach for project communications.

D.

Ensure timely and appropriate collection of project information.

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

A.

Internal

B.

External

C.

Discretionary

D.

Mandatory

The component of the risk management plan that documents how risk activities will be recorded is called:

A.

tracking

B.

scoping

C.

timing

D.

defining

A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

A.

Quality assurance.

B.

A stakeholder management plan.

C.

Project team building.

D.

Integrated change control.

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

A.

Procurement documents

B.

Inspection and audits

C.

Estimate budget

D.

Risk register

An issue log is an input to which Project Human Resource Management process?

A.

Manage Project Team

B.

Acquire Project Team

C.

Plan Human Resource Management

D.

Develop Project Team

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

A.

Result

B.

Product

C.

Service

D.

Improvement

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

A.

triangular distribution

B.

tornado diagram

C.

beta distribution

D.

fishbone diagram

A tool or technique used in the Control Procurements process is:

A.

Expert judgment.

B.

Performance reporting.

C.

Bidder conferences.

D.

Reserve analysis.

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

A.

Feedback analysis

B.

Stakeholder analysis

C.

Communication management plan

D.

Stakeholder management plan

The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

A.

Collect Requirements.

B.

Conduct Procurements.

C.

Estimate Activity Durations.

D.

Estimate Activity Resources.

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

A.

Expert judgment.

B.

Analytical techniques.

C.

Earned value management.

D.

Group decision-making techniques.

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

A.

Direct

B.

Interactive

C.

Pull

D.

Push

When should quality planning be performed?

A.

While developing the project charter

B.

In parallel with the other planning processes

C.

As part of a detailed risk analysis

D.

As a separate step from the other planning processes

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

A.

Historical relationships

B.

Dependency determination

C.

Bottom-up estimating

D.

Rolling wave planning