Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI CAPM - Certified Associate in Project Management (CAPM)

Page: 3 / 8
Total 1337 questions

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?

A.

Add the milestones to the risk register, as time is short.

B.

Add the two milestones to the project plan, as they are mandatory.

C.

Calculate the duration of the two milestones stated in the contract.

D.

Start the project as soon as possible, as time is short.

Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

A.

The Delphi technique

B.

Nominal group technique

C.

Affinity diagram

D.

Brainstorming

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

A.

Plan Cost Management

B.

Plan Scope Management

C.

Plan Stakeholder Management

D.

Plan Schedule Management

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Which of the following tools and techniques is used in the Verify Scope process?

A.

Inspection

B.

Variance analysis

C.

Expert judgment

D.

Decomposition

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

A.

Organizational process assets

B.

Change management plan

C.

Communications management plan

D.

Resource management plan

A team is working on a project using an adaptive approach. During project execution, the project gets delayed by one month due to an unforeseen risk. What should the team do next to deliver this project?

A.

Stop working on the project completely, even if the team can continue working on the tasks with the identified risk.

B.

Accept the project delay and add the risk to the lessons learned document for the next project.

C.

Change the delivery date and deliver the initially agreed-upon scope after mitigation of the identified risk.

D.

Reprioritize the work based on the increased visibility of the current risks.

An output of the Perform Integrated Change Control process is:

A.

Deliverables.

B.

Validated changes.

C.

The change log.

D.

The requirements traceability matrix.

A business analyst has encountered a conflict related to competing requirements on an existing project. What tool should the business analyst use to resolve this issue?

A.

Peer review

B.

Procurement management

C.

Weighted ranking

D.

Risk assessment

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

A.

Complete project phase

B.

Project life

C.

The project life cycle

D.

Project cycle

A Scrum team has a product backlog and a sprint backlog. Which of the following is a correct statement related to these artifacts?

A.

The product backlog does not contain a prioritized list of requirements.

B.

The sprint backlog contains items to be completed during the current sprint.

C.

The sprint backlog contains the list of items prioritized by the product owner.

D.

The product backlog is a subset of the sprint backlog.

Which of the following is an input to the Develop Project Charter process?

A.

Work performance information

B.

Project management plan

C.

Business case

D.

Change requests

The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?

A.

If the operation team members were trained externally

B.

If the transition process was agreed upon during the build

C.

If the end-user documentation was more thorough

D.

If the operations manager was invited to all sprint reviews

Information collected on the status of project activities being performed to accomplish the project work is known as what?

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Which process involves identifying and documenting the logical relationships between project activities?

A.

Develop Schedule

B.

Sequence Activities

C.

Create WBS

D.

Applying leads and lags

Which of the following events would result in a baseline update?

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

A.

Cost management plan

B.

Quality management plan

C.

Communications management plan

D.

Risk management plan

Which type of estimating is used to improve the accuracy of an activity ' s duration?

A.

Analogous

B.

Parametric

C.

Three-point

D.

What-if scenario analysis

An input to the Plan Cost Management process is:

A.

Cost estimates.

B.

Resource calendars,

C.

The project charter,

D.

The risk register.

Which of the following tasks focuses on decomposing work packages?

A.

Adjust duration estimates

B.

Define activities

C.

Complete rolling wave planning

D.

Develop milestone list

Which type of chart is a graphic representation of a process showing the relationships among process steps?

A.

Control

B.

Bar

C.

Flow

D.

Pareto

Which tasks should a project manager accomplish in order to manage project scope correctly?

A.

Define. Validate, and Control Scope. Control Schedule; Control Costs and Manage Stakeholder Engagement

B.

Collect Requirements. Define Scope. Create WBS. Develop Schedule, and Manage Stakeholder Engagement

C.

Plan Scope Management; Collect Requirements; Define. Validate, and Control Scope; and Create WBS

D.

Define. Validate, and Control Scope. Control Costs. Manage Stakeholder Engagement, and keep budget under control

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

A.

Static payback period = 6 + 1300 / 500 = 6.6

B.

Static payback period = 3 + 1200 / 500 = 5.4

C.

Static payback period = 5 + 700 / 500 = 5.4

D.

Static payback period = 5 + 200 / 500 = 5.4

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.

Which technique is the project manager using?

A.

Three-point estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Data analysis

Which statement describes the relationship between Manage Quality process and Control process?

A.

Manage Quality is all about following planned processes and provedures for quality, while Control Quality is about making sure that the product which is produced conforms to customer specifications.

B.

Control Quality is all about following planned process and procedures for quality, while Manage Quality is about making sure that the product which is produced conforms to customer specifications.

C.

Manage Quality and Control Quality are the same

D.

Manage Quality is part of Quality Management and Control is a subset of the Stakeholder Management Process group

Which role does the project manager resemble best?

A.

Orchestra conductor

B.

Facilities supervisor

C.

Functional manager

D.

School principal

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

A.

Historical information and the lessons-learned database.

B.

Historical information and the stakeholder register.

C.

Organizational process assets and the lessons-learned database.

D.

Project documents and historical information.

During which process of Project Cost Management does a project manager produce the cost baseline?

A.

Estimate Costs

B.

Control Schedule

C.

Determine Budget

D.

Develop Project Charter

A Project manager is using agile in a project. As development life cycle is adaptive, how does the project manager handle key stakeholder involvement?

A.

Key stakeholders are regularly involved

B.

Key stakeholders are continuously involved

C.

Key stakeholders are involved at specific milestones

D.

Key stakeholders are always involved

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

A.

adaptive

B.

reflexive

C.

predictive

D.

iterative

In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?

A.

The organization

B.

The project

C.

The industry

D.

The product

Two members of the team are having a conflict..............or partially resolve the problem

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.

Which technique should the project manager use?

A.

Withdraw/Avoid

B.

Smooth/Accommodate

C.

Compromise/Reconcile

D.

Collaborate/Problem Solve

A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?

A.

Project plan

B.

Business case

C.

Budget requirement

D.

Project charter

Which tool or technique is used to develop the human resource management plan?

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

An output of the Plan Quality Management process is:

A.

A process improvement plan,

B.

Quality control measurements.

C.

Work performance information,

D.

The project management plan.

Which of the following is an output of the Distribute Information process?

A.

Project calendar

B.

Communications management plan

C.

Organizational process assets updates

D.

Project document updates

Which of the following factors is lowest at the start of the project?

A.

Cost of changes

B.

Stakeholder influences

C.

Risk

D.

Uncertainty

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

A.

Fixed Price with Economic Price Adjustments Contract (FP-EPA)

B.

Cost-Reimbursable Contract (CR)

C.

Firm-Fixed -Price Contract (FFP)

D.

Fixed-Price-Incentive-Fee Contract (FPIF)

Which of the following is used as input to prepare a cost management plan?

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

What tern describes an intentional activity to modify a nonconforming product or product component?

A.

Preventive action

B.

Corrective action

C.

Defect repair

D.

Updates

Which type of risk diagram is useful for showing time ordering of events?

A.

Ishikawa

B.

Milestone

C.

Influence

D.

Decision tree

One of the objectives of a quality audit is to:

A.

highlight the need for root cause analysis.

B.

share the process documentation among stakeholders.

C.

offer assistance with non-value-added activities.

D.

identify all of the gaps or shortcomings.

Outputs of the Control Communications process include:

A.

expert judgment and change requests

B.

work performance information and change requests

C.

project management plan updates and work performance information

D.

issue logs and organizational process assets updates

An adaptive project manager is migrating the company ' s new website. The project manager must work with the team to invest full capacity on this project because it is the company ' s top-ranked project in the portfolio. In order to increase throughput and provide consistent delivery, the project manager needs to assign members who are currently involved with other projects.

How should the project manager assign the team members to this project?

A.

Task switching

B.

Multitasking

C.

Prediction

D.

Full allocation

Which three of the following are the most widely used techniques that a business analyst should implement to gather requirements? (Choose three)

A.

Current state analysis

B.

Facilitated workshops

C.

Scheduled interviews

D.

Shop floor observation

E.

Brainstorming sessions

The scope of a project cannot be defined without some basic understanding of how to create the specified:

A.

objectives

B.

schedule

C.

product

D.

approach

Which organizational process assets update is performed during the Close Procurements process?

A.

Procurement audit

B.

Lessons learned

C.

Performance reporting

D.

Payment requests

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

A.

BAC

B.

EAC

C.

ETC

D.

WBS

When sequencing activities, what does the common acronym FF stand for?

A.

Fixed Fee

B.

Free Float

C.

Fixed Finish

D.

Finish-to-Finish

In order to detect quality Issues earlier in the project life cycle, the project manager is using an agile/adaptive environment. What is the main difference between waterfall and agile/adaptive development approaches tor Project Quality Management?

A.

The frequency of the quality and review steps

B.

The number of deliverables

C.

The duration of each of the quality and review steps

D.

The tools used in the quality and review steps