Outputs of the Control Communications process include:

A.

expert judgment and change requests

B.

work performance information and change requests

C.

project management plan updates and work performance information

D.

issue logs and organizational process assets updates

Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

A.

The Delphi technique

B.

Nominal group technique

C.

Affinity diagram

D.

Brainstorming

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

A.

Control chart

B.

Earned value

C.

Variance

D.

Trend

A project management office manages a number of aspects including the:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

An input required in Define Scope is an organizational:

A.

structure.

B.

process asset.

C.

matrix.

D.

breakdown structure.

The procurement process that documents agreements and related documentation for future reference is known as:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

When would resource leveling be applied to a schedule model?

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?

A.

-700

B.

-200

C.

200

D.

500

An output of Control Schedule is:

A.

A project schedule network diagram

B.

A schedule management plan

C.

Schedule data

D.

Schedule forecasts

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

A.

Resource breakdown structure

B.

Staffing management plan

C.

Project organizational chart

D.

Scope management plan

What is an objective of the Develop Project Team process?

A.

Feelings of trust and improved cohesiveness

B.

Ground rules for interaction

C.

Enhanced resource availability

D.

Functional managers becoming more involved

Which of the following processes are part of the Project Integration Management Knowledge Area?

A.

Develop Project Management Plan, Collect Requirements, Create WBS

B.

Develop Project Management Plan, Control Scope, Develop Schedule

C.

Develop Project Charter, Define Scope, Estimate Costs

D.

Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase

When can pre-assignment of project team members occur?

A.

When the project uses capital expenditures

B.

When the required staff can be acquired from outside sources

C.

When the project would be ignored due to travel expenses

D.

When the project is the result of specific people being promised as part of a competitive proposal

The formal and informal interaction with others in an organization industry, or professional environment is known as:

A.

negotiation

B.

organizational theory

C.

meeting

D.

networking

What is the number of stakeholders, if the project has 28 potential communication channels?

A.

7

B.

8

C.

14

D.

16

Who selects the appropriate processes for a project?

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

A.

Work breakdown structure

B.

Organizational breakdown structure

C.

Resource breakdown structure

D.

Bill of materials

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

A.

Scope audits

B.

Scope reviews

C.

Quality audits

D.

Control chart

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

A.

Fixed Price with Economic Price Adjustments Contract (FP-EPA)

B.

Cost-Reimbursable Contract (CR)

C.

Firm-Fixed -Price Contract (FFP)

D.

Fixed-Price-Incentive-Fee Contract (FPIF)

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

A.

Define Activities.

B.

Sequence Activities.

C.

Define Scope.

D.

Control Schedule.

Which tools or techniques will a project manager use for Develop Project Team?

A.

Negotiation

B.

Roles and responsibilities

C.

Recognition and rewards

D.

Prizing and promoting

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

A.

0.45

B.

0.56

C.

0.70

D.

1.36

Conflict should be best addressed in which manner?

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

An output of the Create WBS process is:

A.

Scope baseline.

B.

Project scope statement.

C.

Organizational process assets.

D.

Requirements traceability matrix.

Which type of analysis would be used for the Plan Quality process?

A.

Schedule

B.

Checklist

C.

Assumption

D.

Cost-Benefit

An output of the Develop Project Team process is:

A.

change requests

B.

team performance assessments

C.

project staff assignments

D.

project documents updates

A project manager is creating a project charter to provide a direct link between the project and the organization's strategic objectives. What must be considered when creating this document?

A.

High-level requirements and the project team

B.

Key stakeholder list and contingency reserve

C.

Detailed milestone schedule and project objectives

D.

Project purpose and high-level project description

The completion of the project scope is measured against the:

A.

requirements documentation.

B.

project scope statement.

C.

project management plan.

D.

work performance measurements.

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

A.

Two

B.

Four

C.

Five

D.

Twelve

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

A.

Manage Stakeholder Expectations.

B.

Monitor and Control Risks.

C.

Plan Risk Management.

D.

Report Performance.

Plan-do-check-act is also known as:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?

A.

Project

B.

Scope

C.

Contract

D.

Program

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Which input will be used when tasked with developing the human resource plan?

A.

Project management plan

B.

Activity resource requirements

C.

Resource calendar

D.

Project staff assignments

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (T&M).

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

A.

Scope baseline

B.

Scope management plan

C.

Change management plan

D.

Cost baseline

Which is one of the determining factors used to calculate CPI?

A.

EV

B.

SPI

C.

PV

D.

ETC

An input to the Collect Requirements process is the:

A.

stakeholder register.

B.

project management plan.

C.

project scope statement.

D.

requirements management plan.

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

A.

Corrective action

B.

Defect repair

C.

Preventative action

D.

Probable action

In the basic communication model, which term refers to the method that is used to convey the message?

A.

Decode

B.

Encode

C.

Medium

D.

Noise

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

A.

Sensitivity analysis

B.

Three-point estimate

C.

Modeling and simulation

D.

Expected monetary value analysis

Which technique is utilized in the Control Schedule process?

A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

What is project management?

A.

A logical grouping of project management inputs, outputs, tools, and techniques

B.

Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

C.

Launching a process that can result in the authorization of a new project

D.

A formal, approved document that defines how the project is executed, monitored, and controlled

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

When cost variance is negative and schedule variance is positive, the project is:

A.

under budget and behind schedule.

B.

over budget and ahead of schedule.

C.

on schedule.

D.

complete; all planned values have been earned.

Which of the following is an output of the Conduct Procurements process?

A.

Project statement of work

B.

Selected sellers

C.

Risk register updates

D.

Teaming agreements

What is one of the objectives of Project Risk Management?

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.