Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI CAPM - Certified Associate in Project Management (CAPM)

Page: 4 / 8
Total 1320 questions

When does Monitor and Control Risks occur?

A.

At project initiation

B.

During work performance analysis

C.

Throughout the life of the project

D.

At project milestones

Project reporting is a tool that is most closely associated with which process?

A.

Communicate Plan

B.

Manage Communications

C.

Report Performance

D.

Control Communications

Which of the following documents allows the project manager to assess risks that may require near term action?

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

A.

Identify Risks

B.

Control Risks

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

Which statement describes the Monitor Communications process?

A.

Evaluates the differences between the communications management plan and the reality of communications in a project

B.

Ensures that the information needs of the project and the stakeholders are met

C.

Ensures that project information is created, collected, and distributed in a timely and appropriate manner

D.

Develops an appropriate approach and plan for communication of project activities

If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?

A.

Plan Quality Management

B.

Control Quality

C.

Risk Management

D.

Plan Scope Management

A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.

Which entities will the project manager attempt to influence?

A.

The project and the organization

B.

The organization and the industry

C.

The subject matter experts and the project

D.

The change control board and the organization

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

An input to Develop Project Charter is a/an:

A.

Business case.

B.

Activity list.

C.

Project management plan.

D.

Cost forecast.

The features and functions that characterize a result, product, or service can refer to:

A.

project scope

B.

product scope

C.

service scope

D.

product breakdown structure

What can the project manager find among the factors that could lead a project to be tailored

A.

Company Culture

B.

Return on investment

C.

Earned Value

D.

Schedule Performance Index

When cost variance is negative and schedule variance is positive, the project is:

A.

under budget and behind schedule.

B.

over budget and ahead of schedule.

C.

on schedule.

D.

complete; all planned values have been earned.

A project team is brainstorming about the best methods and practices to adopt for an upcoming project. What is the project team trying to follow?

A.

Portfolios

B.

Standards

C.

Concepts

D.

Programs

The process of identifying and documenting relationships among the project activities is known as:

A.

Control Schedule.

B.

Sequence Activities.

C.

Define Activities.

D.

Develop Schedule.

Which type of analysis is used as a general management technique within the Plan Procurements process?

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

The chart below is an example of a:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

A.

Historical information and the lessons-learned database.

B.

Historical information and the stakeholder register.

C.

Organizational process assets and the lessons-learned database.

D.

Project documents and historical information.

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

A.

Update

B.

Preventive action

C.

Defect repair

D.

Corrective action

In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?

A.

Ensures a thorough unit test case coverage

B.

Ensures an accurate reflection of the stakeholders ' intentions

C.

Ensures that the business problem is solved

D.

Ensures the successful delivery of business value

Which process is included in the Project Integration Management Knowledge Area?

A.

Manage Project Team

B.

Collect Requirements

C.

Sequence Activities

D.

Direct and Manage Project Work

Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

A.

Teaming

B.

Collective bargaining

C.

Sharing

D.

Working

A project manager should consider the impact of project..............manager following

A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?

A.

Project Cost Management

B.

Project Integration Management

C.

Project Resources Management

D.

Project Scope Management

A project is composed of three phases that are implemented in parallel without affecting one another. The baselines for each individual phase have been approved by the major stakeholders, and there is a minimal ability to vary the baselines during the execution of the project.

Which methodology did the project manager adopt?

A.

Incremental approach

B.

Predictive approach

C.

Hybrid approach

D.

Iterative approach

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

A.

Project team

B.

Focus group

C.

Change control board

D.

Project stakeholders

Due to new market conditions a five-year project......need to be updated

Due to new market conditions a five-year project requires a full revision of project objectives. Which components to the stakeholder engagement plan need to be updated?

A.

Scope and impact of change to stakeholders

B.

Project scope and stakeholders goals

C.

Engagement level of key stakeholders

D.

Stakeholders expectations for the project

Which type of graphic is displayed below?

A.

Work breakdown structure

B.

Context diagram

C.

Control chart

D.

Pareto diagram

After defining activities in project schedule management, which processes should a project manager follow?

A.

Sequence Activities and Estimate Activity Durations

B.

Estimate Activity Durations and Control Schedule

C.

Develop Schedule and Control schedule

D.

Review Activities and Develop Schedule

Which type of risk diagram is useful for showing time ordering of events?

A.

Ishikawa

B.

Milestone

C.

Influence

D.

Decision tree

How does a requirements traceability matrix help to determine whether a product is ready for delivery?

A.

It captures assigned tasks and their estimated durations.

B.

It confirms the completion of all stories in the backlog.

C.

It assesses the quality of test cases and expected results.

D.

It tracks links between the approved requirements and each work product.

Which additional considerations should the project manager make when managing risks in an agile/adaptive project?

A.

Add more risk categories

B.

Identify, analyze, and manage risk during each iteration of the project

C.

Add new values to the probability and impact matrix

D.

Increase the reserves because of the high variability environment

Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?

A.

Leadership management

B.

Technical project management

C.

Strategic management

D.

Business management

Which factors should be considered for cross-cultural communication?

A.

Background, personality, and communications management plan

B.

Personality, background, and escalation process

C.

Sponsor relationship, personality and background

D.

Current emotional state, personality, and background

Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

A.

The Delphi technique

B.

Nominal group technique

C.

Affinity diagram

D.

Brainstorming

A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?

A.

Expand the scope of the project.

B.

Schedule the tasks in sequence.

C.

Increase quality review cycles.

D.

Schedule the tasks in parallel.

The definition of operations is a/an:

A.

organizational function performing the temporary execution of activities that produce the same product or provide repetitive service.

B.

temporary endeavor undertaken to create a unique product, service, or result.

C.

organization that provides oversight for an administrative area.

D.

organizational function performing the ongoing execution of activities that produce the same product or provide repetitive service.

What tool should a project manager use to efficiently manage project resources?

A.

List of project resources

B.

Resource breakdown structure

C.

Resources detailed in the project scope

D.

Resource requirements

A new business analyst has joined the team in the middle of a project and the requirements traceability matrix has been updated. What should the business analyst do next?

A.

Review the project management plan.

B.

Share the requirements traceability matrix the same way it was shared previously.

C.

Consult the business analysis communications management plan.

D.

Ask the project manager to share the updated requirements traceability matrix at the next meeting.

What prototyping technique shows a sequence or navigations through a series of images or illustrations?

A.

Storyboarding

B.

Wireframes

C.

Data simulation

D.

Report prototyping

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

A.

Sensitivity analysis

B.

Three-point estimate

C.

Modeling and simulation

D.

Expected monetary value analysis

In which organizational structure would the project manager have most authority?

A.

Matrix-weak

B.

Matrix-balanced

C.

Matrix-strong

D.

Organic or simple

The individual or group that provides resources and support for a project and is accountable for success is the:

A.

sponsor

B.

customer

C.

business partners

D.

functional managers

In which type of organization does the project manager have the maximum influence

A.

Centralized

B.

Composite

C.

Simple Organic

D.

Multi-divisional

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

A.

Change request

B.

Risk response

C.

Risk management plan

D.

Lessons learned

A Project manager is failing to secure critical equipment on time, and this resulting in delays in the manufacturing of the final product. Which knowledge area is the project manager handling?

A.

Project Resource Management

B.

Project Quality Management

C.

Project Schedule Management

D.

Project integration Management

A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?

A.

0.88

B.

1.12

C.

0.58

D.

1.58

An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

A.

Customer request

B.

Market demand

C.

Technological advance

D.

Strategic opportunity

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

A.

dictionary.

B.

chart.

C.

report.

D.

register.