PMI CAPM - Certified Associate in Project Management (CAPM)
An output of the Direct and Manage Project Work process is:
What are the Project Procurement Management processes?
The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
An input to Conduct Procurements is:
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:
A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:
A reward can only be effective if it is:
Which tool or technique is used in the Estimate Costs process?
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
Which tool or technique is an examination of industry and specific vendor capabilities?
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
The process of prioritizing risks for further analysis or action is known as:
Which grid shows which resources are tied to work packages?
Which input to the Plan Risk Management process provides information on high-level risks?
Plan Schedule Management is a process in which Knowledge Area?
A regression line is used to estimate:
Inputs to the Plan Schedule Management process include:
An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:
A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:
Which process involves developing an approximation of the monetary resources needed to complete project activities?
A project manager should document the escalation path for unresolved project risks in the:
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
The Monitoring and Controlling Process Group includes processes that:
The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:
An element of the project scope statement is:
Which of the following are outputs of the Define Scope process in Project Scope Management?
Due to today's competitive global market, organizations require more than technical project management skills. Which of the following skills can support long-range strategic objectives that contribute to the bottom line?
Which tasks should a project manager perform in order to manage the project schedule effectively?
Which type of project life cycle uses an iteration plan?
In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?
Which of the following technology platforms is most effective for sharing information when managing virtual project teams?
In a project using agile methodology, who may perform the quality control activities?
Which of the following are processes associated with Project Cost Management?
In which organizational structure would the project manager have most authority?
What purpose does the hierarchical locus of stakeholder communications serve?
In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?
How should a project manager plan communication for a project which has uncertain requirements?
How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?
During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project's components. What should be included in the WBS?
What is one of the main purposes of the project chatter?
A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.
Which process is the project manager executing?
A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?
The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?
What organizational asset can influence the Plan Risk Management process?
What is the role of project management in terms of organizational strategy?
