PMI CAPM - Certified Associate in Project Management (CAPM)
Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:
A procurement management plan is a subsidiary of which other type of plan?
Which enterprise environmental factors are considered during Estimate Costs?
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
Organizations perceive risks as:
Which Process Group typically consumes the bulk of a project's budget?
Which activity is an input to the Conduct Procurements process?
The Verify Scope process is primarily concerned with:
What is the total float of the critical path?
Which of the following investigates the likelihood that each specific risk will occur?
The scope of a project cannot be defined without some basic understanding of how to create the specified:
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?
When is a project finished?
Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
Portfolio Management is management of:
Which action should a project manager take to ensure that the project management plan is effective and current?
When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:
The project scope statement and resource calendars are inputs to which Project Time Management process?
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
Which of the following project documents is an input to the Control Scope process?
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
In a weak matrix, the project managers role is:
A required input for Create WBS is a project:
Which characteristic do projects and operational work share in common?
Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?
Co-location is a tool and technique of:
The process of identifying the stakeholders' information needs is completed during:
Project contracts generally fall into which of the following three broad categories?
Which of the following correctly explains the term "progressive elaboration'?
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
How is the schedule variance calculated using the earned value technique?
Which of the following is a tool and technique used in the Develop Schedule process?
Which of the following is an input to the Direct and Manage Project Execution process?
Which is an output from Distribute Information?
Tools and techniques used for Plan Communications include the communication:
What is the responsibility of the project manager and the functional manager respectively?
Which is used to solicit proposals from prospective sellers?
When sequencing activities, what does the common acronym FF stand for?
Types of internal failure costs include:
The purpose of inspection in Perform Quality Control is to keep errors:
The progressive detailing of the project management plan is called:
Which can be used to determine whether a process is stable or has predictable performance?
Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?
The precedence diagramming method (PDM) is also known as:
