PMI CAPM - Certified Associate in Project Management (CAPM)
When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?
Analogous cost estimating relies on which of the following techniques?
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
In which Project Management Process Group is the project charter developed?
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
Which standard has interrelationships to other project management disciplines such as program management and portfolio management?
Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?
Which piece of information is part of the WBS Dictionary?
Which of the following factors is lowest at the start of the project?
Which type of estimating is used to improve the accuracy of an activity's duration?
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
Which of the following Process Groups covers all nine Project Management Knowledge Areas?
Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?
In Project Cost Management, which input is exclusive to the Determine Budget process?
Which technique helps to determine the risks that have the most potential impact on a project?
The definition of operations is a/an:
What causes replanning of the project scope?
Which type of chart is a graphic representation of a process showing the relationships among process steps?
Which is a communication method used in the Report Performance process?
Which of the following is an output of the Perform Integrated Change Control process?
Which process should be conducted from the project inception through completion?
Which of the following strategic considerations often results in project authorization?
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
Which is a major component of an agreement?
Match each tool or technique with its corresponding Project Cost Management process.
What does leadership involve?
Two members of the team are having a conflict..............or partially resolve the problem
Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.
Which technique should the project manager use?
A project sponsor has asked the project manager to determine how soon the project can be completed. Which of the following methods can a project manager use to find this information?
A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.
Which of the following project delivery approaches should be recommended?
For a 10-day project, activity B ' s duration is three days, and activity C’s duration is two days What is the duration of activity A if activities B and C are performed in parallel?
A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members know their roles and responsibilities. What are the four elements of a RACI chart?
Perform Quantitative Analysis focuses on:
Which of the following is the key construction to controlling the costs and achieving the schedule in projects with high variability?
A project team is closing out a phase and updating the organizational knowledge base What organizational process asset (OPA) will the team update?
An adaptive project manager is told that a new industry regulation will affect an upcoming deliverable. Where should this be recorded?
A construction project is underway, and during... tasks impacted the painting work
A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job What kind ot relationship between the tasks impacted the painting work?
A project is at risk of delivering the solution late because of poor quality that prevents the user acceptance testing (UAT) from being finalized. The product owner does not want to sign off until all the Severity 1 (S1) defects are fixed. What should the project manager do to manage this risk?
A product owner asked for a change in one of the requirements during the elicitation phase. What should the business analyst do?
Which of the following lists represents trends and emerging practices in Project Risk Management?
A business manager wants to start a project to launch a new product and submits a business case to the Portfolio Steering Committee for review. The committee asks the manager for details about the expected business value of the project.
How can the manager document the business value for the Portfolio Steering Committee?
On which type of project.... only after the final iteration?
On wtiich type of project lite cycle is ihe deliverable produced trough a series of ileralrons considering thai the deliverable ts completed only after the Imal iteration?
What are the project management processes associated with project quantity management?
A project team has completed the sprint review and the users are impressed by the demo. However, another functionality included in the sprint that was not discussed in the review is not ready for production deployment.
What should the project team do?
A project's business analyst has to understand the newly acquired technology and the impact it will have on the organization. Which tool should be used to understand the new technology?
A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI’s Talent Triangle best relates to this need to improve?
A production support system is being managed by a team. The team members cannot plan their work in advance, even for a week, because they do not know when new support issues will be submitted. The team cannot start working on new issues until they finish existing issues, no matter how long it takes to finish the existing issues.
Which method should be used in this situation?
Why is required in a project?
An international company that is starting to practice an adaptive approach has several development teams located globally. They are having problems with multiple time zones and repetitive project schedule slippage.
What effective tools should the project teams use to collaborate?

A close-up of a list Description automatically generated