Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI CAPM - Certified Associate in Project Management (CAPM)

Page: 5 / 8
Total 1320 questions

What key component of the project charter defines the conditions for dosing a project phase?

A.

Purpose

B.

Approval requirements

C.

Exit criteria

D.

High-level requirements

What does expert judgment provide as an input to the resource management plan?

A.

Geographic distribution of facilities and resources

B.

Physical resource management policies and procedures

C.

Estimated lead times based on lessons learned

D.

Templates for the resource management plan

A disadvantage associated with virtual teams is that they:

A.

Require communication technology that is not readily available.

B.

Create difficulties when including people with disabilities.

C.

Often cannot accommodate teams that work different hours or shifts.

D.

Create the possibility for misunderstandings to arise.

What quantitative risk analysis technique is used to select the optimum course of action from a number of alternatives?

A.

Sensitivity analysis

B.

Simulation

C.

Decision tree analysis

D.

Influence diagram

Which set of competencies should a project manager have?

A.

Leadership, strategic and business management, and technical project management

B.

Expertise in the Industry, leadership and business management, and bilingual skills

C.

Technical project management, expertise in every role, and PMP certification

D.

Expertise in every detail on project activities. PMP certification, and leadership

Which of the following is the key construction to controlling the costs and achieving the schedule in projects with high variability?

A.

Learn methods

B.

collaborative teams

C.

Generalizing specialists

D.

Knowledge sharing

Which grid shows which resources are tied to work packages?

A.

Work breakdown structure (WBS)

B.

Responsibility assignment matrix (RAM)

C.

Project assignment chart

D.

Personnel assignment matrix

The project manager released a report A few stakeholders express the view that report should

have been directed to them

Which of the 5Cs of written communications does the project manager need to address?

A.

Correct grammar and spelling

B.

Concise expression and elimination of excess words

C.

Clear purpose and expression directed to the needs of the reader

D.

Coherent logical flow of ideas

The correct equation for schedule variance (SV) is earned value:

A.

minus planned value [EV - PV].

B.

minus actual cost [EV - AC].

C.

divided by planned value [EV/PV],

D.

divided by actual cost [EV/AC].

Which risk response strategy is common for both positive and negative risks?

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Which is an example of Administer Procurements?

A.

Negotiating the contract

B.

Authorizing contractor work

C.

Developing the statement of work

D.

Establishing evaluation criteria

A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

A.

Manage Stakeholder Expectations.

B.

Monitor and Control Risks.

C.

Plan Risk Management.

D.

Report Performance.

Creating the project scope statement is part of which process?

A.

Manage Scope

B.

Collect Requirements

C.

Define Scope

D.

Validate Scope

Which roles does the project manager resemble best?

A.

Orchestra conductor

B.

Facilities supervisor

C.

Functional manager

D.

School principal

A software team has completed a critical feature and demonstrated it to the project sponsor.

What kind of stakeholder communication was used in this scenario?

A.

Informal written

B.

Formal verbal

C.

Formal written

D.

Informal verbal

An input to the Create WBS process is a:

A.

project charter.

B.

stakeholder register.

C.

project scope statement.

D.

requirements traceability matrix.

How can a project manager ensure effective project stakeholder engagement?

A.

Build a stakeholder responsibility matrix

B.

Hold weekly project staff meetings

C.

Improve interpersonal and team leadership skills

D.

Create detailed project reports for stakeholders

Why is tailoring required in a project?

A.

Because a one-size-fits-all approach avoids complications and saves time.

B.

Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required.

C.

Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project.

D.

Project managers should apply every process in the PMBOK Guide to the project, so tailoring is not required.

Which tool or technique is used in Close Procurements?

A.

Contract plan

B.

Procurement plan

C.

Closure process

D.

Procurement audits

Which provides the basic framework for managing a project?

A.

Project life cycle

B.

Work breakdown structure (WBS)

C.

Enterprise environmental factors

D.

Project initiation

What tool or technique is used in the Collect Requirements process?

A.

Inspection

B.

Decomposition

C.

Product analysis

D.

Prototypes

What type of meeting is held to discuss prioritized product backlog items?

A.

Status

B.

Daily standup

C.

Iteration planning

D.

Release planning

What scenario describes when a project must be created due to market demand?

A.

A public company authorizes a project to create a new service for electric car sharing to reduce pollution.

B.

A car company authorizes a project to build more fuel-efficient cars in response to gasoline shortages.

C.

Researchers develop an autonomous car. with several new features to be commercialized in the future.

D.

Stakeholders request that raw matenais be changed due to locally high costs.

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

In an adaptive project environment, which action helps the project manager ensure that the team is comfortable with changes?

A.

Having control over the planning and delivery of the products without delegating decisions

B.

Giving access to information to the team and frequent team checkpoints

C.

Selecting different team members to take the project manager role during reviews with stakeholders

D.

Asking the control change board to approve changes before notifying the team

The scope of a project cannot be defined without some basic understanding of how to create the specified:

A.

objectives

B.

schedule

C.

product

D.

approach

What process is used to identify quality requirements and/or standards for a project and its deliverables ' ?

A.

Manage Quality

B.

Plan Quality Management

C.

Control Quality

D.

Perform Qualitative Risk Analysis

Who selects the appropriate processes for a project?

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Plan-do-check-act is also known as:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.

Which statement correctly describes the value of a business case?

A.

It provides the necessary information to determine if a project is worth the required investment.

B.

It provides for alternative dispute resolution procedures in event of contract default.

C.

It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

D.

It is used to help a project manager understand the scope of commercial advantages.

A project team is working on a new driverless vehicle and is organizing a workshop with experts to analyze the data received from the prototype. Who should the project manager invite to provide expert advice?

A.

The subject matter experts (SMEs) identified in the stakeholder register

B.

The senior experts with high status in the academic community

C.

The major stakeholders nominated by the project sponsor

D.

The usual review participants holding recognized certifications

When closing a project or phase, part of the process may require the use of which type of analysis?

A.

Reserve analysis

B.

Regression analysis

C.

Document analysis

D.

Product analysis

Which item is an input to the Define Activities process?

A.

Schedule data

B.

Activity list

C.

Risk register

D.

Scope baseline

The following is a network diagram for a project.

What is the critical path for the project?

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Quality metrics are an output of which process?

A.

Plan Quality

B.

Perform Quality Control

C.

Perform Quality Assurance

D.

Perform Qualitative Risk Analysis

The project manager is creating the communications management plan Which group of inputs Is required to begin?

A.

Work performance reports, change requests, and risk register

B.

Work performance data, project documents, and stakeholder engagement plan

C.

Project charter, project management plan, and project documents

D.

Work performance data, stakeholder register, and team management plan

In a weak matrix, the project managers role is:

A.

part-time

B.

full-time

C.

occasional

D.

unlimited

A firm contracted an event management company to conduct the annual sales day event. The agreement states that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract Is this?

A.

Time and material (T8M)

B.

Fixed price incentive fee (FPIF)

C.

Cost plus fixed fee (CPFF)

D.

Cost plus award fee (CPAF)

Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

A.

Risk, resource, and communications management plans

B.

Scope, quality, and resource management plans

C.

Procurement, integration, and risk management plans

D.

Communications, schedule, and cost management plans

An output of the Plan Quality Management process is:

A.

A process improvement plan,

B.

Quality control measurements.

C.

Work performance information,

D.

The project management plan.

A project team is starting to work on a project based on a Kanban approach. In order to frame the capacity of the team ' s workflow at any moment, the project manager will need to restrict the maximum amount of activities to be performed.

Which element will the project manager handle?

A.

Capacity limit

B.

Pull system

C.

Work in progress

D.

Virtual board

A graphic display of project team members and their reporting relationships is known as a:

A.

Resource calendar.

B.

Project organization chart.

C.

Resource breakdown structure (RBS).

D.

Responsibility assignment matrix (RAM).

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

How can a project manager evaluate project team development?

A.

Produce team performance assessments.

B.

Hold weekly meetings to engage every member

C.

Complete a personal skill assessment on each team member

D.

Provide recognition awards to team members

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

A.

Identify Risks

B.

Perform Qualitative Risk Analysis

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

A.

Brainstorming

B.

Strategies for opportunities

C.

Decision tree analysis

D.

Risk data quality assessment

Which type of organizational structure is displayed in the diagram provided?

A.

Balanced matrix

B.

Projectized

C.

Strong matrix

D.

Functional

A project manager has recently been assigned a new agile project and needs to determine an appropriate leadership style. The project manager aims to empower the team members so they feel committed and motivated to deliver value.

Which leadership style should be used for this project?

A.

A servant leadership style

B.

A laissez-faire leadership style

C.

A collaborative leadership style

D.

A directive leadership style

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

A.

Checksheets

B.

Histograms

C.

Flowcharts

D.

Control charts

Following a project planning meeting with the team, a few team members approach the project manager to follow up on actions required. How can the project manager assess the effectiveness of the meeting?

A.

Send the meeting minutes to all team members to verify that the required information is readily available.

B.

Ask the team members to provide feedback for meetings in the phase retrospective.

C.

Review the actions from the meeting with each of the project team members to ensure their understanding.

D.

Consult the communications management plan to determine the success criteria for meetings.