PMI CAPM - Certified Associate in Project Management (CAPM)
Which of the following are components of the project management plan?
Who determines which dependencies are mandatory during the Sequence Activities process?
What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?
The project leam is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?
During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.
What could be missing from the business case?
What is the difference between quality metrics and quality measurements?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Which of the following is an input to the Direct and Manage Project Execution process?
An organization ' s project management office (PMO) has issued guidelines that require a specific template to be used for onboarding resources for a project. Where can the project manager find this template?
How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?
In which of the Risk Management processes is the project charter used as an input?
Which three of the following are key traits of a project leader? (Choose three)
Projects programs subsidiary portfolios.... objectives refer to?
Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to?
Which process determines the risks that might affect the project?
Which of the following tasks is related to perform the qualitative risk analysis process?
If a project manager effectively manages project knowledge, a key benefits is that:
A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?
Which tool should a project manager use to calculate cost variance for a project?
When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:
On a clinical trial project, the project manager is worried about maintaining control of the project. The project manager decides to use a requirements traceability matrix.
What is the advantage of using this tool?
Which of the following is an output of the Conduct Procurements process?
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost performance index (CPI) for Task 2?
An adaptive project manager is migrating the company ' s new website. The project manager must work with the team to invest full capacity on this project because it is the company ' s top-ranked project in the portfolio. In order to increase throughput and provide consistent delivery, the project manager needs to assign members who are currently involved with other projects.
How should the project manager assign the team members to this project?
How many Project Management Process Groups are there?
What is a tool to improve team performance?
An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float.
What is the likelihood the team will complete all 20 story points in the upcoming sprint?
Which of the following are outputs from the process of creating a work breakdown structure (WBS)?
Why is required in a project?
Which of the following is an input to Control Scope?
A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?
An input of the Create WBS process is:
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
" Tailoring " is defined as the:
Which of the following is an example of tacit knowledge
The following is a network diagram for a project.
The free float for Activity H is how many days?
A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?
Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?
Which of the following is an input to the Perform Qualitative Risk Analysis process?
What tool or technique can improve a products final characteristics?
What is one of the objectives of Project Risk Management?
The stakeholder register is an output of:
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
Perform Quality Control is accomplished by:
Which of the following is provided by the critical path method?
Which tasks should a project manager perform in order to manage the project schedule effectively?
What organizational process asset (OPA) might impact a project ' s outcome?
