PMI CAPM - Certified Associate in Project Management (CAPM)
Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
What is an objective of the Develop Project Team process?
Which document includes the project scope, major deliverables, assumptions, and constraints?
A collection of projects managed as a group to achieve strategic objectives is referred to as a:
Which is a tool or technique used in Define Scope?
What is one of the objectives of Project Risk Management?
What is the total float of the critical path?
Organizations perceive risks as:
An output of the Develop Project Team process is:
Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?
A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:
The project management processes presented in the PMBOK Guide® should:
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:
Which input will be used when tasked with developing the human resource plan?
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
The cost benefit analysis tool is used for creating:
Administer Procurements is part of which Process Group?
At the end of the project, what will be the value of SV?
Which of the following can be used as an input for Define Scope?
The risk shared between the buyer and seller is determined by the:
One of the objectives of a quality audit is to:
Which baselines make up the performance measurement baseline?
Which of the following is an output of Close Procurements?
In the basic communication model, which term refers to the method that is used to convey the message?
The staffing management plan is part of the:
Inputs to the Plan Risk Management process include the:
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
When cost variance is negative and schedule variance is positive, the project is:
After Define Activities and Sequence Activities, the next process is:
What happens to a stakeholder's project influence over time?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
Prototype development may be used as a tool for which of the following risk response strategies?
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
Plan-do-check-act is also known as:
Which statement correctly describes the value of a business case?
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:
Which of the following is a tool and technique used to monitor risk?
Which of the following is a tool or technique used in the Acquire Project Team process?
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
Which of the following is a project constraint?
Funding limit reconciliation is a tool and technique used in which process?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
The probability and impact matrix is primarily used to:
An input to the Collect Requirements process is the:
An input of the Create WBS process is:
