PMI CAPM - Certified Associate in Project Management (CAPM)
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
Which of the following is an input to Direct and Manage Project Execution?
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:
Which is an output of the Collect Requirements process?
A tool and technique used during the Collect Requirements process is:
Which of the following can be used as an input for Define Scope?
Which of the following is an input to the Develop Project Charter process?
Prototype development may be used as a tool for which of the following risk response strategies?
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
Who determines which dependencies are mandatory during the Sequence Activities process?
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
A project lifecycle is defined as:
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:
Projects are separated into phases or subprojects; these phases include:
Which type of dependency is contractually required or inherent in the nature of the work?
Expected monetary value (EMV) is computed by which equation?
The diagram below is an example of a:
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
Which baselines make up the performance measurement baseline?
Which of the following is a tool or technique used in the Acquire Project Team process?
Which of the following is an output of Define Scope?
The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?
The process improvement plan details the steps for analyzing processes to identify activities which enhance their:
The process for performing variance analysis may vary, depending on:
What are the identified risks for doing excessive decomposition in a WBS?
Which input will be used when tasked with developing the human resource plan?
In the basic communication model, which term refers to the method that is used to convey the message?
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
The probability and impact matrix is primarily used to:
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
A graphic display of project team members and their reporting relationships is known as a:
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?
Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?
Which is an enterprise environmental factor?
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?
An input to the Control Quality process is:
Variance and trend analysis is a tool and technique used in which process?
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
The following is a network diagram for a project.
The free float for Activity E is how many days?
Project Scope Management is primarily concerned with:
Which tools or techniques are used during the Close Project or Phase process?
The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:
Requirements documentation will typically contain at least: