Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI CAPM - Certified Associate in Project Management (CAPM)

Page: 6 / 8
Total 1337 questions

Which three techniques can be estimate costs?

A.

Financing, bottom-up estimating, and expert judgment

B.

Cost aggregation, analogous estimating, and financing

C.

Expert judgment, financing, and cost aggregation

D.

Expert judgment, analogous estimating, and bottom-up estimating

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

A.

Communications management plan

B.

Human resource plan

C.

Quality management plan

D.

Procurement management plan

Completion of the product scope is measured against the product:

A.

prototypes

B.

requirements

C.

analyses

D.

benchmarks

Company A’s accountant sends notification about a change in the company’s tax classification.

What would a project have to be initiated?

A.

To change business and technological strategies

B.

To improve processes and services

C.

To meet regulatory and legal requirements

D.

To satisfy stakeholder requests

Which of the following documents allows the project manager to assess risks that may require near term action?

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Which of the following involves making information available to project stakeholders in a timely manner?

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

What are the project management processes associated with project quantity management?

A.

Plan Quality Management, Manage Quality, and Control Quality

B.

Plan Quality Management, Manage Quality, and Cost of Quality

C.

Manage Quality, Customer Satisfaction, and Control Quality

D.

Customer Satisfaction, Control Quality, and Continuous Improvement

Project contracts generally fall into which of the following three broad categories?

A.

Fixed-price, cost reimbursable, time and materials

B.

Make-or-buy, margin analysis, fixed-price

C.

Time and materials, fixed-price, margin analysis

D.

Make-or-buy, lump-sum, cost-plus-incentive

Tools and techniques used for Plan Communications include the communication:

A.

requirements analysis, communication technology, communication models, and communication methods.

B.

methods, stakeholder register, communication technology, and communication models.

C.

requirements, communication technology, communication requirements analysis, and communication methods.

D.

management plan, communication technology, communication models, and communication requirements analysis.

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

A.

Follow organizational methodology and produce all required deliverables.

B.

Discuss the processes and deliverables needed to meet the project objectives with the team.

C.

Identify the processes and deliverables for only the current phase first.

D.

Integrate hybrid approach processes and deliverables to meet the short delivery timeline.

What important qualities should project managers possess for strategic and business management?

A.

Skills and behaviors related to specific domains of project management

B.

Knowledge and competencies needed to guide and motivate a team

C.

Skills and behaviors needed to help an organization achieve its goals

D.

Expertise in the industry and organization that deliver better outcomes

During a sprint demo, the customer says that one of the user stories is not ready for customer use. Which checklist should the team look at to find out what has been missed for the user story?

A.

Burndown chart

B.

Velocity chart

C.

Definition of ready (DoR)

D.

Definition of done (DoD)

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

A.

operate separately.

B.

move together in batches,

C.

overlap and interact.

D.

move in a sequence.

Which set of competencies should a project manager have?

A.

Leadership, strategic and business management, and technical project management

B.

Expertise in the Industry, leadership and business management, and bilingual skills

C.

Technical project management, expertise in every role, and PMP certification

D.

Expertise in every detail on project activities. PMP certification, and leadership

Which tool or technique is used to manage change requests and the resulting decisions?

A.

Change control tools

B.

Expert judgment

C.

Delphi technique

D.

Change log

A project manager is working with the team to prepare the estimates for various work items. The team needs to compare the relative sizing of the items. What should the project manager suggest the team use?

A.

Project task estimation

B.

Dependency planning

C.

Story point estimation

D.

Sprint planning

Which action is included in the Control Costs process?

A.

Identify how the project costs will be planned, structured, and controlled

B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs

C.

Develop an approximation of the monetary resources needed to complete project activities

D.

Monitor cost performance to isolate and understand variances from the approved cost baseline

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

A.

Identify Risks

B.

Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses

What internal enterprise environmental factor (EEF) can impact a project?

A.

Cultural influences

B.

Physical environmental elements

C.

Commercial databases

D.

Infrastructure

Which piece of information is part of the WBS Dictionary?

A.

Responsible organization

B.

Change requests

C.

Validated deliverables

D.

Organizational process assets

The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:

A.

Methodology

B.

Risk category

C.

Risk attitude

D.

Assumption analysis

How is the schedule variance calculated using the earned value technique?

A.

EV less AC

B.

AC less PV

C.

EV less PV

D.

AC less EV

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

A.

Informal communication

B.

Internal communication

C.

Formal communication

D.

Horizontal communication

A project manager in a bank is developing market risk-related processes and is midway through the project. More than half of the product backlog items are developed and delivered to the customer. Due to regulatory and compliance changes in the industry, new backlog items were added to the product backlog with a significant impact on the project schedule. Who should the project manager send this change request to?

A.

The project steering committee (PSC)

B.

The project management office (PMO)

C.

The change control board (CCB)

D.

The change management committee (CMC)

In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?

A.

Add this risk to the lessons learned register on project completion.

B.

Add the stakeholder to the stakeholder register and add the risk to the risk register.

C.

Make sure proper testing gets completed to minimize the risk highlighted.

D.

Ignore the risk from this stakeholder as this stakeholder never showed up at the start of the project.

What is the purpose of the project management process groups?

A.

To define a new project

B.

To track and monitor processes easily

C.

To logically group processes to achieve specific project objectives

D.

To link specific process inputs and outputs

The following is a network diagram for a project.

The total float for the project is how many days?

A.

5

B.

9

C.

12

D.

14

Match each tool or technique with its corresponding Project Cost Management process.

What is a tailoring consideration for Project Scope Management ' ?

A.

Life cycle approach

B.

Continuous improvement

C.

Validation and control

D.

Project complexity

Which of the following is an input to Direct and Manage Project Execution?

A.

Performance reports

B.

Project charter

C.

Outputs from planning processes

D.

Enterprise environmental factors

Which output is the approved version of the time-phased project budget?

A.

Resource calendar

B.

Scope baseline

C.

Trend analysis

D.

Cost baseline

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

A.

Project sponsor

B.

Project manager

C.

Person responsible for project scheduling

D.

Person who is most familiar with the task

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

A.

Uniform

B.

Continuous

C.

Discrete

D.

Linear

Which Process Group includes the Manage Stakeholder Engagement process?

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Initiating

What is an emerging practice in stakeholder engagement?

A.

Confirming that all identified stakeholders are engaged and actually affected by the work

B.

Assuring that team leadership is primarily involved in stakeholder engagement

C.

Ensuring that stakeholders do not change after stakeholder identification

D.

Ensuring that stakeholders most affected by the work are involved as collaborative team partners

Which is a major component of an agreement?

A.

Change request handling

B.

Risk register templates

C.

Lessons learned register

D.

Procurement management plan

How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?

A.

Less time spent on defining scope early on

B.

More time spent on defining scope early on

C.

Less time spent on scope management process

D.

Project scope management is the same in all projects

A product owner asked for a change in one of the requirements during the elicitation phase. What should the business analyst do?

A.

Provide the information to the product manager for approval.

B.

Provide the information to the project manager to seek approval or rejection.

C.

Reject the change as the project scope has already been defined.

D.

Accept the modification and update the requirements traceability matrix.

Which behavior is a management trait?

A.

Asking what and why

B.

Challenging the status quo

C.

Innovating

D.

Relying on control

Which of the following are components of the technical project management skill?

A.

Ability to explain business aspects of the project, business strategy, goals and objectives, and business value.

B.

Ability to deal with people, to be collaborative, and to apply persuasion and negotiation.

C.

Ability to focus on relationships with people, inspire trust, and implement decisions and actions that support the business strategy.

D.

Ability to plan and prioritize, gather the right artifacts available for each project, and focus on critical success factors.

Which of the following characteristics are found in a functional organizational structure?

A.

Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget

B.

Limited project manager authority, limited resource availability, and a part-time project manager ' s role

C.

Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager ' s role

D.

High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

Which of the following sets are inputs to the Collect Requirements process?

A.

Project charter and requirements documentation

B.

Project charter and business documents

C.

Project charter and stakeholder requirements

D.

Business documents and requirements traceability matrix

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

A.

Organizational breakdown structure (OBS)

B.

Work performance information

C.

Work package

D.

Work breakdown structure (WBS)

Which tool or technique is used in the Perform Integrated Change Control process?

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

An element of the project scope statement is:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

Which document includes the project scope, major deliverables, assumptions, and constraints?

A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

For what project management process is work performance information an output?

A.

Implement Risk Responses

B.

Plan Stakeholder Engagement

C.

Monitor Stakeholder Engagement

D.

Plan Quality Management

When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process.

A.

Develop Schedule

B.

Define Activities

C.

Define Scope

D.

Collect Requirements

Which of the following activities are included as part of a project manager ' s responsibilities?

A.

Direct, control, and focus on structure.

B.

Problem solve , achieve the bottom line, and focus on success.

C.

Control, maintain project status, and develop.

D.

Inspire, engage, and build relationships with people.