Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI CAPM - Certified Associate in Project Management (CAPM)

Page: 7 / 8
Total 1337 questions

The diagram below is an example of a:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

What is one of the objectives of Project Risk Management?

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.

Which cost is associated with nonconformance?

A.

Liabilities

B.

Inspections

C.

Training

D.

Equipment

Which action should the project manager take after the team finishes executing the scope?

A.

Verify the deliverables to ensure that they are correct and meet the customer ' s satisfaction.

B.

Accept all the deliverables and deliver them to the customer for final acceptance.

C.

Conduct a joint session with the customer, change the deliverables, and then request approval.

D.

Check that all change requests were implemented and release deliverables to the customer.

Conflict should be best addressed in which manner?

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

A project manager is working on project cost management. The following information is current.

* Planned value = 30

* Actual cost = 35

* Earned value = 28

Considering this data, which project indicator is correct?

A.

Schedule Variance (SV) = 2

B.

Cost Performance Index (CPI) = 0.80

C.

Schedule Performance Index (SPI) = 1.93

D.

Cost Variance (CV) = 7

Which of the following is an example of facit knowledge?

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

The following is a network diagram for a project.

The free float for Activity H is how many days?

A.

4

B.

5

C.

10

D.

11

What type of meeting is held to discuss prioritized product backlog items?

A.

Status

B.

Daily standup

C.

Iteration planning

D.

Release planning

Which of the following are outputs of define scope process in project scope management

A.

Requirements documentation and requirements traceability matrix

B.

Scope management plan and requirements management plan

C.

Project Scope statement and project documents updates

D.

Scope baseline and project documents updates

Projects programs subsidiary portfolios.... objectives refer to?

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to?

A.

Operations Management

B.

Project Management

C.

Program Management

D.

Portfolio Management

The process of defining how the project scope will be validated and controlled is known as:

A.

Define Scope.

B.

Develop Project Management Plan.

C.

Plan Scope Management.

D.

Plan Quality Management.

A stakeholder is reading project documents given by the project manager. The stakeholder is

curious about the difference between a verified deliverable and an accepted deliverable.

Which of the following definitions can the project manager use to explain the difference?

A.

An accepted deliverable is approved by the project team; a verified deliverable is approved and formally signed off by the customer or sponsor.

B.

An accepted deliverable has been checked and confirmed for accuracy through the Control Quality process; a verified deliverable meets acceptance criteria that is formally signed off and approved by the customer or sponsor.

C.

An accepted deliverable meets acceptance criteria and is formally signed off and approved by the customer or sponsor, a verified deliverable is a completed project deliverable that has been checked and confirmed for accuracy through the Control Quality process

D.

An accepted deliverable meets acceptance criteria and is signed off by the project manager; a verified deliverable meets acceptance criteria and is signed off by the customer or sponsor.

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOK®)

Assigned risk ratings are based upon:

A.

Root cause analysis.

B.

Risk probability and impact assessment.

C.

Expert judgment.

D.

Revised stakeholders ' tolerances.

The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?

A.

Plan Resource Management

B.

Estimate Activity Resources Communications

C.

Estimate Costs

D.

Acquire Resources

The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

A.

Close Procurements.

B.

Control Procurements.

C.

Plan Procurements.

D.

Conduct Procurements.

A temporary endeavor that creates a unique product or service is called a:

A.

Project

B.

Plan

C.

Program

D.

Portfolio

What is the name of a graphic display of project team members and their reporting relationships?

A.

Role dependencies chart

B.

Reporting flow diagram

C.

Project organization chart

D.

Project team structure diagram

What is the function of a Project Management Office (PMO)?

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client ' s overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization ' s business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

What should a project manager do to prepare a risk management plan with a lot of technical uncertainty?

A.

Get expert judgment.

B.

Count on personal experience.

C.

Ask project sponsors.

D.

Delay the project until technical uncertainty is clarified

A project manager should consider the impact of project..............manager following

A project manager should consider the impact of project decisions on supporting and maintaining the product along with project results Which process is the project manager following?

A.

Project Cost Management

B.

Project Integration Management

C.

Project Resources Management

D.

Project Scope Management

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

A.

Timing

B.

Methodology

C.

Risk categories

D.

Budgeting

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

What kind of skills should a project manager use when attempting to achieve consensus by balancing the conflicting and competing goals of project stakeholders?

A.

Interpersonal skills and the ability to manage people

B.

Strategic and business management skills

C.

Technical and business management skills

D.

Business analysis skills and expertise

Which technique is utilized in the Control Schedule process?

A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

A.

Checksheets

B.

Histograms

C.

Flowcharts

D.

Control charts

Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

A.

Risk, resource, and communications management plans

B.

Scope, quality, and resource management plans

C.

Procurement, integration, and risk management plans

D.

Communications, schedule, and cost management plans

A project management office manages a number of aspects including the:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

Which of the following describes the similarities of the process groups and project life cycle?

A.

The life cycle involves three project management process groups.

B.

Both provide a basic framework to manage the project.

C.

Each project must have a life cycle and all processes in the five process groups.

D.

The project life cycle is managed by executing the processes within the five process groups.

The process of identifying and documenting relationships among the project activities is known as:

A.

Control Schedule.

B.

Sequence Activities.

C.

Define Activities.

D.

Develop Schedule.

A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?

A.

Withdraw/avoid

B.

Smooth /accommodate

C.

Collaborate/problem solve

D.

Compromise/ reconcile

A project stakeholder is requesting changes to the project plan. Which process group addresses this?

A.

Initiating Process Group

B.

Planning Process Group

C.

Executing Process Group

D.

Monitoring and Controlling Process Group

In which Project Cost Management process is work performance data included?

A.

Plan Cost Management

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?

A.

Product and sprint backlog

B.

Key performance indicators (KPIs) and baseline

C.

Increments and bottlenecks

D.

Burndown and burnup charts

Which scenario is most desirable during the execution phase of a project?

A.

Apply and use quality controls to ensure expectations are met throughout the project

B.

Communicate quality failures to the sponsor for feedback

C.

Conduct all quality inspections at the end of the project

D.

Only correct quality issues found if it will keep you within the budget

Which of the following is an example of an organizational system that is arranged based on the job being performed?

A.

Simple

B.

Multi-divisional

C.

Functional

D.

Project-oriented

Which document can help a project manager to leverage historical project information?

A.

Lessons learned register

B.

Schedule baseline

C.

Work performance data

D.

Deliverable acceptance forms

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

A.

Transfer

B.

Share

C.

Avoid

D.

Accept

What prototyping technique shows a sequence or navigations through a series of images or illustrations?

A.

Storyboarding

B.

Wireframes

C.

Data simulation

D.

Report prototyping

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.

Which type of life cycle would the project manager use in this case?

A.

Predictive life cycle

B.

Waterfall life cycle

C.

Hybrid life cycle

D.

Product life cycle

Which is an aspect of the requirements management plan?

A.

Detailed project scope statement

B.

Creation of work breakdown strucure (WBS)

C.

Impact analysis

D.

Duration for implementation

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Which of the following is an output of the Conduct Procurements process?

A.

Project statement of work

B.

Selected sellers

C.

Risk register updates

D.

Teaming agreements

Which type of dependency is contractually required or inherent in the nature of the work?

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Co-location is a tool and technique of:

A.

Develop Human Resource Plan.

B.

Manage Project Team.

C.

Develop Project Team.

D.

Acquire Project Team.

Which characteristic do projects and operational work share in common?

A.

Performed by systems

B.

Constrained by limited resources

C.

Repetitiveness

D.

Uniqueness

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

A.

Project Risk Management

B.

Project Human Resource Management

C.

Project Scope Management

D.

Project Stakeholder Management

A project lifecycle is defined as:

A.

a collection of generally sequential and sometimes overlapping project phases.

B.

a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

C.

a recognized standard for the project management profession.

D.

the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.