PMI CAPM - Certified Associate in Project Management (CAPM)
The project manager is new to the company in order to effectively manage the project, which components of the organizational governance framework does the project manager need to take into account?
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
A project manager is identifying the risks of a project. Which technique should the project manager use?
During a retrospective, the team finds that all of the user stories are not complete. What should be done with the incomplete user stories?
Which project performance domain is the work breakdown structure (WBS) developed?
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
At what stages of project should the identify Stakeholder process be performed?
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedulevariance (SV) for Task 8?
Construction of a building has stopped due to a supplier ' s failure to deliver concrete. The project schedule is behind by three months.
What should the project manager do to overcome this problem and put the project back on track?
At which point of the project is the uncertainty the highest and the risk of failing the greatest?
An input to the Collect Requirements process is the:
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.
Which technique is the project manager using?
A tool and technique used during the Define Scope process is:
Which can be used to determine whether a process is stable or has predictable performance?
Which of the following factors within a company cloud trigger the creation of a project?
Which type of dependency is contractually required or inherent in the nature of the work?
What is the definition of Direct and Manage Project Execution?
Plan Communications Management develops an approach and plan for project communications based on stakeholders ' needs and requirements and:
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
In an interactive communication model, how is the sender ensured that the message was understood by the receiver?
The procurement process that documents agreements and related documentation for future reference is known as:
Which role does the project manager resemble best?
Which organizational process asset can make an impact on the outcome of a project?
The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?
The project manager has following information about duration for an activity:
* Most likely [tM] - 15 days
* Pessimistic [tP] - 20 days
* Optimistic [tO] - 10 days
What is the estimated duration of this activity, according to the triangular distribution technique?
Which statement describes the relationship between Manage Quality process and Control process?
After winning a large government contract, a company needs to hire a portfolio manager What vital qualification should candidates possess?
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
Which of the following characteristics are found in a functional organizational structure?
A recently hired project manager is looking for templates to use for projects on which they will work. To what category of enterprise environmental factors should the project manager refer?
The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:
A project manager is assigned to a project during the execution phase and consults the documents created by the previous project manager.
Which document should the project manager study to identify the ownership of the project outcome?
Who identifies project requirements in the early phase of the project?
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
Which tool or technique is required in order to determine the project budget?
In which process might a project manager use risk reassessment as a tool and technique?
A project team has completed the sprint review and the users are impressed by the demo. However, another functionality included in the sprint that was not discussed in the review is not ready for production deployment.
What should the project team do?
Which term refers to the work performed to deliver results with specified features and functions?
During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?
Which of the following is an example of an internal factor that influences the outcome of the project?
In one of the project meetings during project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?
Which of the following tasks focuses on decomposing work packages?
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?
In an agile or adaptive environment. when should risk be monitored and prioritized?
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
Resource calendars are included in the:
A project ' s aim, from a business perspective, is moving an organization from one level to another to achieve a specific objective. What is the goal for a project ' s successful completion?
