PMI CAPM - Certified Associate in Project Management (CAPM)
Which project risk listed in the table below is most likely to occur?
Those who enter into a contractual agreement to provide services necessary for a project are:
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?
Which tool or technique is required in order to determine the project budget?
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:
Which tools or techniques are used during the Close Project or Phase process?
At the start of a typical project life cycle, costs are:
A project manager should communicate to stakeholders about resolved project issues by updating the:
The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:
Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:
Project Stakeholder Management focuses on:
Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:
Activity cost estimates and the project schedule are inputs to which Project Cost Management process?
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
Whose approval may be required for change requests after change control board (CCB) approval?
The degree, amount, or volume of risk that an organization or individual will withstand is called risk:
Which element does a project charter contain?
A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:
During which process does the project team receive bids and proposals?
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedulevariance (SV) for Task 8?
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
Completion of the product scope is measured against the product:
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
Requirements documentation will typically contain at least:
Which enterprise environmental factors may influence Plan Schedule Management?
The following is a network diagram for a project.
What is the critical path for the project?
A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:
Which Manage Communications tool or technique focuses on identifying and managing barriers?
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
Which Project Time Management process includes bottom-up estimating as a tool or technique?
A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:
The process of defining how the project scope will be validated and controlled is known as:
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?
