PMI CAPM - Certified Associate in Project Management (CAPM)
A tool and technique used during the Perform Qualitative Risk Analysis process is:
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
The purpose of inspection in Perform Quality Control is to keep errors:
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
Which cost estimate technique includes contingencies to account for cost uncertainty?
Which of the following project documents is an input to the Control Scope process?
Labor, materials, equipment, and supplies are examples of:
Which of the following types of a dependency determination is used to define the sequence of activities?
The progressive detailing of the project management plan is called:
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
The project scope statement and resource calendars are inputs to which Project Time Management process?
Which of the following is the primary output of the Identify Risks process?
The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?
Which of the following events would result in a baseline update?
The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?
Which of the following statements is true regarding project and product lifecycles?
Which of the following tools and techniques is used in the Verify Scope process?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Which of the following is an example of schedule compression?
Which of the following is a tool and technique used in the Develop Schedule process?
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
One of the tools and techniques of the Manage Project Team process is:
In which process is a project manager identified and given the authority to apply resources to project activities?
The project manager needs to review the templates in use. The templates are part of the:
Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:
Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?
Which process should be conducted from the project inception through completion?
How many Project Management Process Groups are there?
The definition of operations is a/an:
Which of the following is a tool or technique of the Define Activities process?
Which of the following documents allows the project manager to assess risks that may require near term action?
Which is a communication method used in the Report Performance process?
A required input for Create WBS is a project:
Which Process Group contains those processes performed to define a new project?
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
Types of internal failure costs include:
In which process might a project manager use risk reassessment as a tool and technique?
Which of the following reduces the probability of potential consequences of project risk events?
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
